PART 1. TEXAS COMMISSION ON ENVIRONMENTAL QUALITY
CHAPTER 299. DAMS AND RESERVOIRS
The Texas Commission on Environmental Quality (commission or agency) proposes the repeal of §§299.1 - 299.5, 299.11 - 299.18, 299.21 - 299.31, 299.51, and 299.61; and new §§299.1 - 299.7, 299.11 - 299.17, 299.21 - 299.33, 299.41 - 299.46, 299.51, 299.52, 299.61, 299.62, 299.71, and 299.72.
BACKGROUND AND SUMMARY OF THE FACTUAL BASIS FOR THE PROPOSED RULES
The existing dam safety rules, adopted in 1986, were developed after significant changes were made to the standards used to evaluate dams by the National Dam Safety Program. Even though the agency's Dam Safety Program has undergone significant changes since then, no changes have been made to the existing rules since their adoption in 1986. The commission proposes to repeal the existing rules in Chapter 299 and proposes new, updated rules in Chapter 299.
In recent years, three distinct reviews were conducted of the Dam Safety Program rules. The reviews included: 1) the Executive Director's Task Force on Dam Safety (a task force of 26 stakeholders representing a wide cross section of interests) in 1998; 2) the House Natural Resources Subcommittee on Dam Safety in November of 1998; and 3) a peer review by the Association of State Dam Safety Officials, at the request of the agency, in 2003. The reviews made several recommendations for significant modifications and updates to the existing rules. This rulemaking incorporates many of the recommendations.
Two stakeholder meetings were held in 2005 with approximately 40 individuals representing owners, professional engineers, associations, sponsors of Natural Resources Conservation Service assisted project dams, federal agencies, and state agencies. Owners included members of the general public. Environmental groups were also invited but did not attend. Considerable input was received and incorporated in this rulemaking. Dam safety rules from at least ten states were also reviewed in 2005.
Other meetings were held in 2005 and 2006 with the Texas Association of Watershed Sponsors, Texas Water Conservation Association, and American Society of Civil Engineers to discuss the proposed rule package.
Two additional stakeholder meetings were held in 2008 with approximately 40 individuals, including several individuals who participated in the 2005 stakeholder meetings. Considerable input was again received and incorporated in this rulemaking.
The State Auditor's Office has prepared An Audit Report on the Dam Safety Program at the Texas Commission on Environmental Quality, published in May 2008. It is recommended in this report that the commission should revise the rules to address key dam safety practices.
These proposed new rules make the program more similar to federal and other state programs.
The existing rules are proposed to be repealed and new rules are proposed. The proposed new rules relate to design, review, and approval of construction plans and specifications; construction, operation and maintenance, inspection, repair, removal, emergency management, site security, and enforcement of proposed and existing dams. The proposed new rules would revise existing criteria to make them more consistent with current engineering industry practices. The proposed new rules would also add requirements for emergency action plans, gate operating plans, and security plans and would better define an owner's responsibilities.
The proposed new rules would also provide options for upgrading existing dams. These proposed new rules would ease some of the inspection burden by removing small- and intermediate-size, low-hazard dams from a periodic inspection schedule.
The proposed new rules would improve the organizational flow of the requirements and would update all relevant cross-references and citations.
The commission proposes administrative changes throughout the proposed rules to be consistent with Texas Register requirements and agency guidelines. These changes include spelling out acronyms, updating references to the commission's predecessor agencies, and updating cross-references.
The commission proposes to repeal all sections of the current chapter and proposes new sections that improve organization and readability. The proposed reorganization of this chapter would remove redundancy in the requirements and place similar requirements in the same section.
SECTION BY SECTION DISCUSSION
Proposed new §299.1, Applicability, would establish the applicability of this chapter.
Existing §299.1(1), relating to the definition of dam, would be moved in part to proposed new §299.1 to clarify how this chapter applies to different types of dams and to be consistent with the definition used in federal regulations.
Proposed new §299.1(a) would limit the applicability of this chapter to certain types of dams and would ensure that the commission's rules correspond to federal regulations. Figure: 30 TAC §299.1(a)(2) would be added to make the definition clearer.
Proposed new §299.1(b) would include language indicating that all requirements for dams are included in this chapter, but would not relieve the owner from meeting the requirements for water rights and Edwards Aquifer protection plans. This is necessary to ensure that owners are aware of other requirements that may apply to their dams.
Proposed new §299.1(c) would include language from existing §299.1(1) and would add federally owned dams from existing §299.21, Applicability, and above-ground water storage tanks to the list of dams to be consistent with the practice of the Dam Safety Program.
Proposed new §299.1(d) would include language that all dams shall meet the size and hazard requirements of the chapter, including those exempt from the requirements of Subchapter C, Construction Requirements, and those that are granted an exception under §299.5, Exception. This language is necessary to make it clear that all owners of dams shall follow the requirements and to prevent dams from being constructed without using standards as outlined in this chapter.
Existing §299.1, Definitions, would be repealed and moved to proposed new §299.2, Definitions. The definitions for "Effective crest of the dam," "Probable maximum flood (PMF)," and "Probable maximum precipitation (PMP)," "Existing dam," "Height of dam," "Normal storage capacity," and "Proposed dam" would be moved from existing §299.1 to the proposed new §299.2, renumbered to accommodate the addition of new definitions now found in proposed new §299.2, and changed to clarify the language to avoid misinterpretation. The commission determined that there was a need for clearer definitions because a number of questions have been raised on the interpretation of these definitions.
The definition for "Dam" would be moved from existing §299.1 to new §299.2(14), renumbered to accommodate the addition of new definitions, and changed to clearly identify a dam as being a barrier, or barriers, constructed for the purpose of impounding water. The definition would be expanded to include a dam's appurtenant structures as being part of the dam and to indicate that it would be used for the purpose of either permanently or temporarily impounding water. The commission determined that this is a more inclusive definition, similar to the federal definition.
The definition for "Deliberate impoundment" would be moved from existing §299.29, Deliberate Impoundment, and would be included in the list of definitions in proposed new §299.2(17), instead of in the text of the rules to avoid confusion. The formatting and the rule language would be modified to be consistent with Texas Register requirements and agency guidelines, but there are no substantive changes.
The definition of "Deficient dam" would be included in proposed new §299.2(16) to ensure that the commission's rules correspond to the definition in the federal regulations.
The definitions for "Spillway design flood" and "Spillway evaluation flood" would be deleted and replaced by the term "Design flood" to proposed new §299.2(18) to remove redundancy and avoid confusion. "Design flood" includes both deleted terms.
The definition for "Hazard classification" would be moved from existing §299.13, Hazard Classification Criteria, to proposed new §299.2(29) and changed to clarify the language. The commission determined that the language in existing §299.13 has been confusing since numerous questions have been received concerning the definition.
The definition for "Maximum storage capacity" would be moved from existing §299.1 to proposed new §299.2(36). The definition would be expanded to reflect that, for purposes of these rules, the storage capacity does not include areas that would be below natural ground. The commission determined that the maximum storage capacity was related to the amount of water that would be released during a failure of the dam and that water impounded below natural ground would not be released during such an event.
The definition for "Owner" would be included to list the different persons that could be identified as an owner of a dam. Proposed new §299.2(44)(A) would list an owner as a person who holds legal possession or ownership of an interest in a dam. Proposed new §299.2(44)(B) would list an owner as a person who is the fee simple owner of the surface estate of the tract of land on which the dam is located. Proposed new §299.2(44)(C) would list an owner as a person who is a sponsoring local organization of a dam constructed by the Natural Resources Conservation Service. Proposed new §299.2(44)(D) would list an owner as a person who has a lease, easement, or right-of-way to construct, operate, or maintain a dam. This is necessary to list all potential owners of a dam.
The definitions for "Abandon," "Accepted engineering practices," "Alteration," "Appurtenant structures," "Breach," "Breach analysis," "Breach inundation area," "Closure of dam," "Closure section," "Commence construction," "Conceptual design," "Construction," "Construction change order," "Dam failure," "Detention dam," "Drawdown," "Emergency action plan," "Emergency repairs," "Emergency spillway," "Engineering inspection," "Enlargement," "Fetch," "Inundation map," "Loss of life," "Main highways," "Maintenance," "Maintenance inspection," "Minimum freeboard," "Minor highways," "Modification," "NAD83 conus datum," "NAVD88 datum," "Outlet," "Piping," "Principal spillway," "Professional engineer," "Reconstruction," "Rehabilitation," "Removal," "Repairs," "Reservoir," "Safe manner," "Seal," "Secondary highways," "Secure location," "Spillway," "Sponsoring local organization," "Stability analysis," and "Substantially complete" would be added to proposed new §299.2 to clearly define terms and words that are unique to the dam safety industry for clarity of their use in this chapter.
Existing §299.2, General, and existing §299.3, Duties, Obligations, and Liabilities of Dam Owners, would be repealed and the requirements contained in those sections would be either deleted or moved from the repealed sections to new sections to improve the organization and readability.
Proposed new §299.3(a) would include that the executive director may require an owner to obtain an independent team of consultants or other dam safety experts to evaluate the adequacy of the dam or appurtenant structures if the executive director has determined that the dam constitutes a significant threat to human life or property. Language would also be added to provide the requirements for use of an independent team of professional engineers or other dam experts and will be included in a guidance document developed by the executive director. The commission determined that an independent team would be better able to evaluate all aspects of the adequacy of the dam and make recommendations. This process has been used successfully at least two times for dams in Texas. These determinations may be necessary for certain dams in order to ensure their safety and compliance with these rules.
Proposed new §299.3(b) would require an owner submitting an application for a water rights permit that includes a dam to provide documentation that ensures that the owner submits the proper materials to ensure that the requirements of this rule will be met during the application review.
Existing §299.4, Registered Engineer, would be repealed and the proposed new §299.4 would be renamed "Professional Engineer" to agree with the term used by the Texas Board of Professional Engineers.
Proposed new §299.4(a)(1) would include language from existing §299.4 that would be rewritten for ease of readability. Proposed new §299.4(a)(2) would include language that professional engineers shall prepare evaluations, analyses, and reports as required in this chapter. This change was made to ensure that all duties of a professional engineer would be in one rule to avoid confusion. Proposed new §299.4(a)(3) would include language from existing §299.26, Construction Inspection, to ensure that all duties of a professional engineer would be in one rule to avoid confusion and would ensure that the requirements do not conflict with contract requirements of the engineering industry. Proposed new §299.4(a)(4) would include, in the list of duties of a professional engineer performing or supervising the engineering, inspections of high- and significant-hazard dams and large, low-hazard dams, as defined in proposed new §299.13, Size Classification Criteria, and §299.14, Hazard Classification Criteria. The commission determined that due to the size and hazard of these dams, this requirement would be necessary to ensure that the engineering characteristics of the dam and appurtenant structures are being evaluated according to accepted engineering practices.
Proposed new §299.4(b) concerning waiver of requirements by the executive director would include language from the last phrase of existing §299.4 and would be rewritten for ease of readability.
Existing §299.5, Exception, would be repealed and moved to the proposed new §299.5, Exception. Proposed new §299.5(a) would include language from existing §299.5 that would be modified to be consistent with Texas Register requirements and agency guidelines. The term "registered engineer" would be changed to "professional engineer" to agree with the term used by the Texas Board of Professional Engineers.
Language would be added in §299.5(b) to identify the materials the owner would need to submit to the executive director with the exception request. This requirement would clarify the types of material needed to be submitted by the owner with the exception request.
Proposed new §299.5(c) would include language to specify the method for either approving or denying the exception request. This is necessary to provide owners and engineers with the commission's procedure for addressing exception requests.
Proposed new §299.6, Changing Ownership of Dams, would include a requirement to notify the executive director when there is a change in ownership of a dam. This requirement was recommended in the report prepared by the 1998 Executive Director's Task Force on Dam Safety and would be necessary for the executive director to maintain a current list of owners and contact information in the event of an emergency.
Proposed new §299.7, Inventory of Dams, would include a requirement for the executive director to maintain an inventory of dams in Texas. The commission determined that the inventory would be essential to maintaining a database for information on the dam and owner, for providing statistics on dams during the legislative process, and for continuing to receive federal funds for the Dam Safety Program. The State Auditor's Office has also recommended that this requirement is essential to the Dam Safety Program.
Existing §299.11, Classification of Dams, would be repealed and moved to proposed new §299.12, Classification of Dams, for better organization of the subchapter.
Proposed new §299.11 concerning the evaluation of the hydrologic, hydraulic, and structural adequacy of a dam would include language from existing §299.2(b) and would be modified to be consistent with Texas Register requirements and agency guidelines.
Proposed new §299.11(1) would include language that the hydrologic and hydraulic adequacy of a dam would be evaluated using the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas . The commission determined that the procedures used in previous hydrologic and hydraulic studies needed to be reviewed and revised, and new research had been conducted on the hydrologic criteria, which would provide a more representative approach. This would result in less cost to owners for upgrading dams to meet the minimum hydrologic criteria. The new procedures are included in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas. This requirement would be necessary to ensure that professional engineers use the most current and easily verified procedures.
Proposed §299.11(2) concerning a list of conditions that may endanger a dam would include language from existing §299.2(b) and would be modified to be consistent with Texas Register requirements and agency guidelines.
Existing §299.12, Size Classification Criteria, would be repealed and moved to proposed new §299.13, Size Classification Criteria, for better organization in the subchapter.
Proposed new §299.12(a) concerning classification of dams by size and hazard and not on the condition of the dam would include language from existing §299.11 and would be modified to be consistent with Texas Register requirements and agency guidelines.
Proposed new §299.12(b) would include language that would allow a dam's hazard classification to be changed at any time based on an inspection and downstream hazard evaluation by the executive director or the owner's professional engineer; a breach analysis performed by either the executive director or the owner's professional engineer; or a review of current aerial photography and topographic maps along with field confirmation. During a stakeholders meeting in 2005, stakeholders expressed frustration that it appeared that a hazard classification could not be changed and that owners would be required to upgrade dams at a considerable cost when it may not be necessary. The commission determined that there has been a process in place for changing a hazard classification and that process would be included in the rules.
Existing §299.13, Hazard Classification Criteria, would be repealed and moved to proposed new §299.14, Hazard Classification Criteria, for better organization in the subchapter.
Proposed new §299.13, Size Classification Criteria, would include language from existing §299.12 that would be modified to be consistent with Texas Register requirements and agency guidelines and to be consistent with proposed new §299.1(a).
Existing §299.14, Hydrologic Criteria for Dams, would be repealed and moved to proposed new §299.15, Hydrologic and Hydraulic Criteria for Dams, for better organization in the subchapter.
Proposed new §299.14, Hazard Classification Criteria, would include language from existing §299.13 that would be modified to be consistent with Texas Register requirements and agency guidelines. Language in existing §299.14(b) indicated that the minimum hydrologic criteria would be based on both existing and planned future development. Stakeholders at a stakeholders meeting in 2005 indicated that designing for a future development that may not occur would be costly and recommended that the language be changed to be based on only a development existing at the time of the classification. In addition, language would be added to proposed new §299.14 that a breach analysis could be used as part of the classification. This language is necessary to provide owners with guidelines for the classification of dams. Language would be added to §299.14(1) - (3) to provide more detail for the loss of life (one to six lives or one or two inhabitable structures for significant-hazard dams and seven or more lives or three or more inhabitable structures for high-hazard dams in the breach inundation area downstream of the dam). This has been the practice of the Dam Safety Program since 1986 and would be added to rules.
Existing §299.15, Evaluation of Existing Dams, would be repealed and moved to proposed new §299.16, Structural Evaluation of Dams, for better organization in the subchapter.
Proposed new §299.15(a)(1) would be added to state that this subsection would apply only to proposed dams to distinguish between proposed and existing dams.
Proposed new §299.15(a)(1)(A) would reference proposed new Figure: 30 TAC §299.15(a)(1)(A) and would include language from existing §299.14(a) and existing Figure: 30 TAC §299.14(b) that would be modified for clarity and to be consistent with Texas Register requirements and agency guidelines. Language in existing Figure: 30 TAC §299.14(b) would also be modified to change the requirements for the percentage of the PMF for large-size, low-hazard dams, small-size, significant-hazard dams, large-size, significant-hazard dams, small-size, high hazard dams, and intermediate-size, high-hazard dams. This is necessary to be consistent with the language in proposed new §299.15(a)(3). Language would be added to proposed new Figure: 30 TAC §299.15(a)(1)(A) for interpolation of the information in the table. The upper limits for the interpolation for large dams are based on analysis of the heights of large dams in Texas (only one dam exceeds the 200-foot height) and the maximum storage capacity (300,000 acre-feet maximum storage capacity is in the middle of the maximum storage capacities for the large dams in Texas). The commission determined that dams with maximum storage capacities greater than 300,000 acre-feet should be at the upper range of the minimum hydrologic criteria. Stakeholders during the last stakeholder meeting in 2008 recommended a change in the table to provide more consistency.
Proposed new §299.15(a)(1)(B) would include language indicating that the minimum design flood hydrograph shall be based on size and hazard classification of a proposed dam at the time of the design and shall be calculated using the criteria in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas. The commission determined that the procedures used in previous hydrologic and hydraulic studies needed to be reviewed and revised, and new research had been conducted on the hydrologic criteria, which would provide a more representative approach. This would result in less cost to owners for upgrading dams to meet the minimum hydrologic criteria. The new procedures are included in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas . This requirement would be necessary to ensure that professional engineers use the most current and easily verified procedures.
Proposed new §299.15(a)(1)(C) would allow proposed dams and spillways or dams and spillway to be reconstructed, modified, enlarged, rehabilitated, or altered using hydrologic procedures of the Natural Resources Conservation Service to be acceptable, provided the procedures are shown to be equal to or more conservative than the procedures in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas . This is necessary to continue a policy that has been in place since 1986.
Proposed new §299.15(a)(2) would include language that any dam designed to withstand overtopping without failure of the dam, including the foundation and abutments, would be exempt from meeting the minimum hydrologic criteria. A dam that would be designed to withstand overtopping would be armored with a material to allow overtopping without failing under any flood event. A dam with this design would be exempt.
Proposed new §299.15(a)(3)(A) would include language that an existing dam, that was required to pass 100% of the PMF before the effective date of these rules and is shown to pass 75% or more of the PMF by a professional engineer, would not be required to be upgraded to minimum hydrologic criteria. The dam would be considered adequate to meet the minimum hydrologic criteria provided the owner has the following: 1) an emergency action plan that meets the requirements in proposed new §299.61, Emergency Action Plans; 2) an operation and maintenance program; 3) an inspection program; and 4) provides an annual report to the executive director, beginning 12 months after the effective date of this rule. The 1998 Executive Director's Task Force on Dam Safety and the stakeholders in the 2005 stakeholder meetings strongly recommended that existing dams be addressed differently than proposed dams. The commission agreed and determined that many of the dams that do not meet the minimum hydrologic criteria, were constructed, and possibly approved, under a previous set of rules and regulations and that a criteria of 75% of the PMF would be appropriate for the average of the extreme storms in the state. The commission also determined that the owners of these dams needed to meet additional requirements to maintain the dam in a safe manner. Nearly 40% of the high hazard dams in Texas would be considered adequate under this proposal compared to nearly 30% under the current rules.
Proposed new §299.15(a)(3)(B) would include language that a dam that was required to meet the minimum hydrologic criteria before the effective date of these rules, but is shown by a professional engineer to meet the minimum hydrologic criteria in Figure: 30 TAC §299.15(a)(1)(A), will not be required to be upgraded and the dam would be considered adequate to meet the new minimum hydrologic criteria. This is necessary to provide consistency with subsection (a)(3)(A).
Proposed new §299.15(a)(3)(C) includes language from existing §299.15(a) that would be modified to be consistent with Texas Register requirements and agency guidelines. In addition, language would be added that if an existing dam does not meet the minimum hydrologic criteria or if the hazard classification of an existing dam has been raised and the dam does not meet the minimum hydrologic criteria, the executive director may require the owner to submit to the executive director one of the following prepared by a professional engineer: 1) construction plans and specifications for upgrading the dam; 2) an analysis or other option to request a reduction in the minimum hydrologic criteria; or 3) a plan for an alternative to upgrading. The stakeholders in 2005 recommended that options be made available for dam owners. The commission agreed that options need to be available for owners to find the best solution for providing a safe dam.
Proposed new §299.15(a)(3)(D) would provide language that when a dam that meets the requirements of subsection (a)(3)(A) is required to be modified due to structural deficiencies, the executive director shall require the owner to submit final construction plans and specifications for the structural modifications without having to upgrade the dam to meet the minimum hydrologic criteria. This is necessary to provide owners with guidance for upgrading dams and to avoid unnecessary modifications.
Proposed new §299.15(a)(4)(A)(i) would include language that one of the options to reduce the minimum hydrologic criteria would be for a breach analysis to be prepared by a professional engineer. The breach analysis would model three different scenarios and would need to demonstrate that existing downstream improvements would not be adversely affected (defined as the downstream flooding differentials being less than or equal to one foot between breach and non-breach simulations in the affected area). The commission determined that a breach analysis is a viable option for owners to use in reducing the minimum hydrologic criteria since a differential of one foot or less would not cause additional flooding or loss of life.
Proposed new §299.15(a)(4)(A)(ii) would include language from existing §299.14(b) and existing §299.15(b) and would be modified to be consistent with Texas Register requirements and agency guidelines. Language would be added that other technical options would be included in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas. The commission determined that the procedures used in previous hydrologic and hydraulic studies needed to be reviewed and revised, and new research had been conducted on the hydrologic criteria, which would provide a more representative approach. This would result in less cost to owners for upgrading dams to meet the minimum hydrologic criteria. The new procedures are included in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas . This requirement would be necessary to ensure that professional engineers use the most current and easily verified procedures.
Proposed new §299.15(a)(4)(A)(iii) would include language that one of the options to reduce the minimum hydrologic criteria would be for the owner to provide documentation of the purchase of, or an easement for, the property downstream of the dam that would be impacted by a dam failure showing that it had been dedicated the land for non-residential and non-commercial use. The commission determined that options need to be available for owners to find the best solutions for providing a safe dam and that this option would be an acceptable non-structural option.
Proposed new §299.15(a)(4)(A)(iv) would include language that one of the options to reduce the minimum hydrologic criteria would be for the owner to provide documentation that the property downstream of the dam that would be impacted by a dam failure had been dedicated for non-residential and non-commercial use. The commission determined that options need to be available for owners to find the best solutions for providing a safe dam and that this option would also be an acceptable non-structural option.
Proposed new §299.15(a)(4)(B) would provide a process for the executive director to review and approve the owner's request for reduction of the minimum hydrologic criteria.
Proposed new §299.15(a)(4)(C) would provide a process for the executive director to deny the owner's request for reduction of the minimum hydrologic criteria.
Proposed new §299.15(b)(1) would include language that the hydraulic adequacy for proposed dams or dams proposed to be reconstructed, modified, enlarged, rehabilitated, or repaired would be evaluated using the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas . The commission determined that the procedures used in previous hydrologic and hydraulic studies needed to be reviewed and revised, and new research had been conducted on the hydrologic criteria, which would provide a more representative approach. This would result in less cost to owners for upgrading dams to meet the minimum hydrologic criteria. The new procedures are included in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas . This requirement would be necessary to ensure that professional engineers use the most current and easily verified procedures.
Proposed new §299.15(b)(2) would include language that an owner shall have a professional engineer address the stability of the spillways to determine if the spillways will adequately meet the minimum hydrologic criteria without being significantly damaged. The commission determined that spillway stability was not being addressed by professional engineers during evaluations of dams and spillways. Failure to ensure stability of spillways has led to spillways being severely damaged during storm events.
Proposed new §299.15(b)(3) would include language that an owner's professional engineer determine minimum freeboard for proposed large dams as outlined in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas . The commission determined that experience with dams during Hurricane Rita in 2005 indicated that freeboard could be essential during extreme storm events to prevent failure of a dam.
Proposed new §299.15(c) would include language that if it would become necessary for an owner of an existing dam to reevaluate the hydraulic adequacy, the owner shall have a professional engineer evaluate the hydraulic adequacy using the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas. The commission determined that the procedures used in previous hydrologic and hydraulic studies needed to be reviewed and revised, and new research had been conducted on the hydrologic criteria, which would provide a more representative approach. This would result in less cost to owners for upgrading dams to meet the minimum hydrologic criteria. The new procedures are included in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas . This requirement would be necessary to ensure that professional engineers use the most current and easily verified procedures.
Existing §299.16, Interim Alternatives, would be repealed and moved to proposed new §299.17, Alternatives to Upgrading Dams, for better organization in the subchapter.
Proposed new §299.16(a) concerning a requirement to submit a geotechnical, geological, and structural report to support the design of a proposed dam or a dam that is proposed to be reconstructed or structurally modified, enlarged, rehabilitated, or altered would include language from existing §299.23(c) Content of Construction Plans and Specifications, that would be modified to be consistent with Texas Register requirements and agency guidelines.
Proposed new §299.16(b) would include language requiring that an owner have a professional engineer develop a stability analysis as described in the most current version, at the time of the analysis, of the agency's Design and Construction Guidelines for Dams in Texas for proposed large- and intermediate-size dams and large and intermediate dams that are proposed to be reconstructed or structurally modified, enlarged, rehabilitated, or altered and submit the analysis with the construction plans and specifications. Stability analyses are necessary to evaluate slopes on larger dams to ensure that slopes are flat enough to prevent slope failures such as slides. The commission determined that there were problems in the past due to the lack of minimum stability criteria on a critical dam and determined that a guideline document would be the most appropriate place to include that criteria.
Proposed new §299.16(c) would include language that would allow the executive director to request that an owner of a possible deficient dam to perform geotechnical, structural, or stability analyses to determine if the integrity of the dam was threatened. The commission determined that this language would be necessary to determine safety needs and possibly prevent a failure of a dam.
Proposed new §299.16(d)(1) would include language that would allow the executive director to request an owner to have a person, that proposes to dredge a reservoir within 200 feet of a dam, have a professional engineer perform an evaluation to determine if the integrity of the dam would be compromised by the activity. Dredging too close to a dam could result in soil seams being exposed to reservoir water that would allow water to flow under the dam or upstream slopes being disturbed. These situations could result in a failure of the dam. The 200 feet should be sufficient distance to protect the dam.
Proposed new §299.16(d)(2) would include language that would allow the executive director to request that an owner has a person that proposes to install a utility line or pipeline in a dam that requires significant excavation in the dam or spillways and that a professional engineer perform an evaluation to determine if the integrity of the dam would be compromised by the activity. These proposals need to be evaluated since utility lines and pipelines can be under pressure, and utility lines and pipelines need to be installed with a specified amount of cover, which could mean a significant depth into the dam. Utility lines and pipelines can affect the stability of the dam, and these lines could break under pressure and cause the dam to fail.
Proposed new §299.16(d)(3) would include language that would allow the executive director to request that an owner has a person that proposes to construct a road across a dam or spillways or within 200 feet of the dam and that a professional engineer perform an evaluation to determine if the integrity of the dam would be compromised by the activity. These proposals need to be evaluated since traffic on the road can exceed the design loads for the dam and could cause depressions in the dam which could result in settlement of the dam or slides from water standing in the depression. A road, if not properly designed and constructed, could affect the stability of the dam. The 200 feet should be sufficient distance to protect the dam.
Proposed new §299.16(d)(4) would include language that would allow the executive director to request that an owner has a person that proposes to drill oil or gas wells or perform oil or gas exploration within 200 feet of a dam and that a professional engineer perform an evaluation to determine if the integrity of the dam would be compromised by the activity. Removal of oil and gas from a well or exploration for oil and gas could result in settlement of the foundation beneath a dam resulting in a failure of the dam. Equipment used by the drilling company could also cause damage to the dam resulting in cracking, slope failures, or possible failure of the dam. The 200 feet should be sufficient distance to protect the dam.
Proposed new §299.16(d)(5) would include language that would allow the executive director to request that an owner has a person that proposes to blast within 1/2 mile from a dam and that a professional engineer perform an evaluation to determine if the integrity of the dam would be compromised by the activity. Blasting can result in waves similar to earthquake waves. Under certain situations, blasting could result in cracks in the foundation or liquefaction of the foundation or embankment soils and failure could occur. The 1/2 mile should be sufficient distance to protect the dam.
Existing §299.17, Emergency Management, would be repealed and moved to proposed new §299.61 for better organization within the chapter.
Proposed new §299.17(a) would include language for alternatives to structural upgrading of a dam. The 1998 Executive Director's Task Force on Dam Safety and the stakeholders participating in the 2005 stakeholder meetings strongly recommended that there be alternatives to upgrading a dam. Structural upgrading is costly. The commission determined that many of the dams that do not meet the minimum hydrologic criteria were constructed, and possibly approved, under a previous set of rules and regulations and that a criteria of 75% of the PMF would be appropriate for the average of the extreme storms in the state. The commission also determined that the owner of the dams covered by the subsection needed to meet additional requirements to maintain the dam in a safe manner. The commission determined that alternatives could also include reduction of minimum hydrologic criteria according to §299.15(a)(4), removal of the dam, lowering the reservoir to a level that would allow it to meet the appropriate minimum hydrologic criteria, or a combination of structural or non-structural methods as proposed by the owner's professional engineer.
Proposed new §299.17(b) would provide a process for the executive director to review the owner's alternative plan for the dam.
Existing §299.18, Variance, would be repealed.
Existing §299.21, Applicability, would be repealed and moved to proposed new §299.21, Applicability.
Proposed new §299.21(a) concerning dams covered by the rules would include language from existing §299.21 that would be modified to be consistent with Texas Register requirements and agency guidelines. Existing §299.21 indicates that the subchapter would apply to dams requiring commission authorization. This language was not clear. The intent was that the subchapter would apply to dams requiring a water rights permit authorization as provided in Texas Water Code, §11.126(c). The proposed language would make that clarification and would also include any dam that is required to obtain approval of an Edwards Aquifer protection plan. The list of dams that would be subject to this subchapter would be expanded to ensure that the critical dams would have plans and specifications reviewed and construction monitored to prevent deficient dams from being built. The proposed new list would include dams originally designed and constructed with the assistance and written concurrence of the Natural Resources Conservation Service but that are being proposed to be reconstructed, modified, enlarged, rehabilitated, altered, or repaired without the assistance and written concurrence of the Natural Resources Conservation Service. This situation has already occurred for 22 dams. The list of dams covered in these rules was discussed with the Natural Resources Conservation Service office in Temple before being added to the rule. The list would also include dams used for temporary detention purposes and impounding a maximum storage capacity of over 200 acre-feet. These dams would potentially be located in areas where failure could cause loss of life and the dams have not been reviewed under the language in existing §299.21, and also include small, high- and significant-hazard dams exempted from a water rights permit under Texas Water Code, §11.142. The commission determined that these dams all need to be subject to this subchapter to prevent deficient dams from being constructed.
Proposed new §299.21(b) concerning dams excluded from these rules would include language from existing §299.21 and proposed new §299.22, Review and Approval of Construction Plans and Specifications, that would be modified to be consistent with Texas Register requirements and agency guidelines. The proposed subsection would clearly identify which dams were originally designed and constructed with the assistance and written concurrence of the Natural Resources Conservation Service and would not be subject to the subchapter. This was a concern expressed in one of the stakeholders meetings in 2005. Also, dams constructed for mining purposes and approved and inspected by the Mine Safety and Health Administration would be excluded to avoid duplication of the approval process. This was also a concern expressed in one of the stakeholder meetings in 2005. Another exclusion is small, low-hazard dams exempted from a water rights permit. These dams are generally built on farms and ranches for livestock use and are not located where a failure would result in loss of life. The subsection would also exempt maintenance and emergency repairs from being subject to the subchapter, which is in agreement with Texas Water Code, §11.144.
Existing §299.22, Approval of Plans and Specifications, would be repealed and moved to proposed new §299.22.
Existing §299.23, Content of Construction Plans and Specifications, would be repealed and moved to proposed new §299.22 and proposed new §299.16 for better organization within the subchapter.
Proposed new §299.22(a)(1) would include language from existing §299.22 that would be modified to be consistent with Texas Register requirements and agency guidelines. The requirement for sealing, signing, and dating the construction plans and specifications would ensure that the commission's rules correspond to the requirements of the Texas Board of Professional Engineers. The rule ensures that the requirements do not cover emergency repairs.
Proposed new §299.22(a)(2) would ensure that the commission's rules would be in addition to the requirements in Texas Water Code, §11.121 and 30 TAC Chapter 213, relating to Edwards Aquifer.
Proposed new §299.22(a)(3) would require that the plans and specifications for proposed dams would not be approved by the executive director unless the plans and specifications include language, or design criteria, that require the proposed contractor to develop a Storm Water Pollution Prevention Plan and submit a Notice of Intent for coverage under the State of Texas Construction General Permit. This is necessary to ensure that the commission's rules are consistent with federal requirements and language in 30 TAC §281.25(a)(4).
Proposed new §299.22(a)(4) would include language from existing §299.22 that would be modified to be consistent with Texas Register requirements and agency guidelines. The language would also ensure that the commission's rules would correspond to Texas Water Code, §11.126(c), and Texas Water Code, §11.144.
Proposed new §299.22(a)(5) would clarify that the construction of a proposed dam or the reconstruction, modification, enlargement, rehabilitation, alteration, or repair of an existing dam shall be performed according to approved construction plans and specifications unless construction change orders have been approved as indicated in proposed new §299.26, Construction Change Orders. This subsection is necessary to ensure that dams are built according to approved plans.
Proposed new §299.22(b)(1) would include language for options on the size of construction plans and a requirement for a scale. The standard size of construction plans is 22 inches by 34 inches. The option of submitting half-size plans would be allowed if the details are legible. This option would provide a small cost savings for owners. The language on scale would correspond with Texas Water Code, §11.126(b).
Proposed new §299.22(b)(1)(A) would include language requiring a vicinity map on the construction plans. Currently, most construction plans include a vicinity map. The commission determined that a map identifying all features would be essential to determine impact of the features on the dam and the dam's impact on the features. Each of the features on the vicinity map could have a significant impact on the design of the dam.
Proposed new §299.22(b)(1)(B) would include language from existing §299.23(a)(1) that would be modified to be consistent with Texas Register requirements and agency guidelines. New language would require latitude and longitude for the midpoint of the dam for ease in locating the dam in the field.
Proposed new §299.22(b)(1)(C) would include language from existing §299.23(a)(2) that would be modified to be consistent with Texas Register requirements and agency guidelines. New language would include the proposed bottom of the core trench and elevations of all features. The commission determined that the core trench is essential for a dam and that the core trench be excavated into impervious material (material that is difficult for water to flow through). The elevations are critical to ensure that any potential flow is being addressed to avoid potential for failure of the dam or appurtenant structures in the future.
Proposed new §299.22(b)(1)(D) concerning inclusion of a spillway profile on the construction plans would be moved from existing §299.23(a)(2) without change.
Proposed new §299.22(b)(1)(E) would include language from existing §299.23(a)(2) that would be modified to be consistent with Texas Register requirements and agency guidelines. New language would provide that the boring logs would only be included on the construction plans if they are not included in a separate geotechnical report, which is preferred. This is necessary so that engineers are not required to place the logs of borings on the construction plans, thereby creating insurance issues for the engineers.
Proposed new §299.22(b)(1)(F) concerning inclusion of a cross section of the dam on construction plans would be moved from existing §299.23(a)(3) without change.
Proposed new §299.22(b)(1)(G) concerning inclusion of detailed sections of outlet conduits, control works, and spillways on the construction plans would include language from existing §299.23(a)(4) that would be modified to be consistent with Texas Register requirements and agency guidelines.
Proposed new §299.22(b)(1)(H) concerning inclusion of different types of instrumentation on the construction plans would include language from existing §299.23(a)(5) that would be modified to be consistent with Texas Register requirements and agency guidelines.
Proposed new §299.22(b)(1)(I) concerning inclusion of requirements, or design criteria, for a contractor to develop a Storm Water Pollution Plan on construction plans would be modified to be consistent with federal requirements and language in §281.25(a)(4).
Proposed new §299.22(b)(1)(J) would include language that would require including other design standards as described in the most current version, at the time of the evaluation, of the agency's Design and Construction Guidelines for Dams in Texas . The commission determined that a guideline document would be the appropriate place to include other design standards instead of the rules.
Proposed new §299.22(b)(2) would include language for options on the size of construction plans and for a requirement for a scale. The standard size of construction plans is 22 inches by 34 inches. The option of submitting half-size plans would be allowed if the details are legible. This option would provide a small cost savings for owners. The language on scale would correspond with Texas Water Code, §11.126(b).
Proposed new §299.22(b)(2)(A) would require a vicinity map on the construction plans. Currently, most construction plans include a vicinity map. The commission determined that a map identifying all features would be essential to determine impact of the features on the dam and the dam's impact on the features. Each of the features in the language could have a significant impact on the design of the dam.
Proposed new §299.22(b)(2)(B) would include language from existing §299.23(a)(4) that would be modified to be consistent with Texas Register requirements and agency guidelines.
Proposed new §299.22(b)(2)(C) would include language from existing §299.23(a)(2) that would be modified to be consistent with Texas Register requirements and agency guidelines. Language would be added that the boring logs would only be included on the construction plans if they are not included in a separate geotechnical report, which is preferred. This is necessary so that engineers are not required to place the logs of borings on the construction plans, thereby creating insurance issues for the engineers.
Proposed new §299.22(b)(2)(D) concerning inclusion of requirements, or design criteria, for a contractor to develop a Storm Water Pollution Plan on the construction plans would be modified to be consistent with federal requirements and language in §281.25(a)(4).
Proposed new §299.22(b)(2)(E) would include language that
would require including other design criteria as described in the
most current version, at the time of the design, of the agency's
Proposed new §299.22(c)(1) concerning the requirement for
the various types of materials to be included in the specifications
would include language from existing §299.23(b)(1) that would
be modified to be consistent with Texas Register requirements and
agency guidelines.
Proposed new §299.22(c)(2) would include language from existing §299.23(b)(3)
that would be modified to be consistent with Texas Register requirements
and agency guidelines. Language would be added that construction plans
would not be substantially changed without either written approval
by the executive director or notification of the changes as defined
in proposed new §299.26. This is necessary to provide alternatives
for construction change order processing and approval to avoid delays
in construction and causing increased costs.
Proposed new §299.22(c)(3) concerning a requirement to be
included in the specifications for the proposed contractor to develop
a Storm Water Pollution Plan would be modified to be consistent with
federal requirements and language in §281.25(a)(4).
Proposed new §299.22(c)(4) would include language that would
require including other design specifications as described in the
most current version, at the time of the design, of the agency's Design and Construction Guidelines for Dams in Texas
. The commission determined that a guideline document
would be the appropriate place to include other design specifications
instead of the rules.
Proposed new §299.22(d)(1)(A) would list geotechnical, geological,
and structural evaluation reports for all proposed dams and dams that
are proposed to be reconstructed, modified, enlarged, rehabilitated,
altered, or repaired that may be required for review during the executive
director's review of plans and specifications. In the current review
method, professional engineers are requested to submit geotechnical,
geological, and structural reports. The commission determined that
these reports are necessary to properly evaluate the safety of the
proposed dam.
Proposed new §299.22(d)(1)(B) concerning a stability analysis
that may be required by the executive director would include language
from existing §299.23(c) that would be modified to be consistent
with Texas Register requirements and agency guidelines.
Proposed new §299.22(d)(1)(C) would include language from
existing §299.2(b) and would be modified to be consistent with
Texas Register requirements and agency guidelines for all proposed
dams and dams that are proposed to be reconstructed, modified, enlarged,
rehabilitated, altered, or repaired. The commission determined that
the procedures used in previous hydrologic and hydraulic studies needed
to be reviewed and revised, and new research had been conducted on
the hydrologic criteria, which would provide a more representative
approach. This would result in less cost to owners for upgrading dams
to meet the minimum hydrologic criteria. The new procedures are included
in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas
. This requirement is necessary to ensure that professional
engineers use the most current and easily verified procedures.
Proposed new §299.22(d)(1)(D) would require a report on the
proposed instrumentation for proposed large dams and existing large
dams proposed to be reconstructed, modified, enlarged, rehabilitated,
altered, or repaired. Instrumentation for large dams is recommended
to measure movement, settlement, pressure, and seepage flow. For large
dams, this instrumentation could be critical for monitoring to prevent
problems that could threaten the integrity of the dam. During construction,
the instrumentation would be used to monitor increases in pressure,
movement, and seepage flow. Language would be included for the frequency
of data collection to be included in the report because critical information
could be missed if the data collection is too infrequent.
Proposed new §299.22(d)(1)(E) would include requirements for
reports addressing site-specific conditions. Dam sites with good geotechnical
and geological conditions have already been used for dams in the past.
New dam sites are becoming more difficult to locate for proposed dams
as evidenced by problems experienced recently by owners' professional
engineers who did not prepare site-specific reports.
Proposed new §299.22(d)(2)(A) would require a quality control
and assurance plan for all proposed dams. The commission determined
that many of the problems associated with dams were the result of
improper construction that could have been prevented with a good quality
control and assurance plan. The executive director has examples of
dams constructed with limited or no quality control that have, or
are currently, experienced major problems.
Proposed new §299.22(d)(2)(B) would require a closure plan
for any proposed dams that requires a closure section. Closure of
the dam is one of the most critical parts of the construction of a
dam. It is essential that this closure section be placed properly,
in the right sequence, and within a reasonable amount of time to prevent
a failure of the project. The commission determined that review of
this plan would be necessary to prevent problems in the future.
Proposed new §299.22(d)(2)(C) would require submittal of a
plan, for review, for addressing emergencies that threaten the integrity
of the dam for all proposed high- and significant-hazard dams during
construction. History has shown that failures do occur during construction.
A properly prepared emergency plan can help the owner protect his
investment and protect downstream lives and property. Review of this
plan would be necessary to ensure that there is an appropriate method
for addressing emergencies.
Proposed new §299.22(e)(1) would clarify a review process,
which will be included in the most current version, at the time of
the review, of the agency's Design and Construction
Guidelines for Dams in Texas. The commission determined that
this issue is of concern to professional engineers who are trying
to get projects approved so that construction can start and that a
guideline document would best address the issue.
Proposed new §299.22(e)(2) would provide a process for the
executive director to notify the owner of the approval of construction
plans and specifications.
Proposed new §299.22(e)(2)(A) would explain the approval method
of a dam associated with a water rights permit. The subsection would
require that the water rights permit be issued and a time limitation
section be added to the water rights permit requiring construction
of a proposed dam or reconstruction, modification, enlargement, rehabilitation,
alteration, or repair of an existing dam to be started and completed
within a specified time frame before approval of the plans and specifications
is given. This language would ensure that the commission's rules would
be consistent with Texas Water Code, §11.121. These requirements
are also necessary to ensure that dams are not built before the water
rights permit is either issued or denied. If the permit is denied
and the dam was built, it would require action to have the dam removed,
which would be costly to the owner.
Proposed new §299.22(e)(2)(B) would explain for the approval
method of a dam submitted as part of an application for an Edwards
Aquifer protection plan. The language executive director would not
approve the plans and specifications for the dam until an Edwards
Aquifer protection plan has been issued by the appropriate regional
office. This language is necessary to ensure that dams are not built
without the approval of an Edwards Aquifer protection plan.
Proposed new §299.22(e)(3) - (6) would provide a process for
the executive director to approve or require revisions to construction
plans and specifications.
Proposed new §299.22(f)(1) would require the executive director
to reevaluate the approved construction plans and specifications of
a dam if construction did not commence within four years after approval.
The purpose for the reevaluation would be to determine if the approval
may be invalid due to any changes of the rules, regulations, and accepted
engineering practices, or downstream hazard classification, during
the four-year period. This determination would be made regardless
of any extension of time authorization is given. The commission determined
that new research or legislation could result in changes in the rules
or the Hydrologic and Hydraulic Guidelines for Dams in Texas
and the plans and specifications would no
longer be valid. This requirement would be necessary to ensure that
the dam is built under the most current rules.
Proposed new §299.22(f)(2) would provide a process for the
executive director to notify the owner that the construction plans
and specifications for a dam that construction had not commenced within
four years of the approval would have to be resubmitted.
Proposed new §299.22(f)(3) would require the plans and specifications
to meet the rules and regulations in effect at the time they are prepared.
Existing §299.24, Maintenance of Records, would be repealed
and moved to proposed new §299.23, Maintenance of Construction
Records, for better organization within the subchapter.
Proposed new §299.23(a) would include language from existing §299.24(a)
that would be modified to be consistent with Texas Register requirements
and agency guidelines. The requirement for maintaining construction
records would not only apply to construction of a proposed dam, but
also to reconstruction, modification, enlargement, rehabilitation,
alteration, or repair of an existing dam. This requirement would formalize
a practice that has been in place since 1986. Language on the type
of construction records would be added for clarity.
Proposed new §299.23(b) would include language from existing §299.24(a)
that would be modified to be consistent with Texas Register requirements
and agency guidelines. This requirement would be for high- and significant-hazard
dams to ensure that owners are alerted in advance of the requirements.
Proposed new §299.23(c) concerning the type of information
to include in construction records would include language from existing §299.24(b)
that would be modified to be consistent with Texas Register requirements
and agency guidelines.
Proposed new §299.23(d) would include a requirement that the
construction records be maintained by the owner in a secure location
at the construction site or at a location designated by the owner
that is immediately accessible to the owner until the completion of
construction. This requirement is necessary to prevent unauthorized
access to the records.
Proposed new §299.23(e) would include a requirement that after
construction the owner would transfer the construction records to
a permanent, secure location at a location designated by the owner
that is immediately accessible to the owner. This requirement is necessary
to prevent unauthorized access to the records and to allow the executive
director to review all records upon request.
Existing §299.25, Construction Progress Reports, would be
repealed and moved to proposed new §299.24, Construction Progress
Reports, for better organization within the subchapter.
Proposed new §299.24, Construction Progress Reports, would
include language from existing §299.25 that would be modified
to be consistent with Texas Register requirements and agency guidelines.
A requirement would be added to include the contractor's name and
the name and telephone number of the professional engineer or inspector
that will be on site during construction in the material submitted
to the executive director. This requirement would be necessary for
contacting personnel at the construction site for inspections or information
during construction.
Existing §299.26, Construction Inspection, would be repealed
and moved to proposed new §299.25, Construction Inspection, for
better organization within the subchapter.
Proposed new §299.25(a) - (c) would include language from
existing §299.26 that would be modified to be consistent with
Texas Register requirements and agency guidelines and to correspond
with Texas Water Code, §12.016. Language would be added to include
a process for notifying the owner of deficiencies or violations and
for the owner to bring the construction into compliance with the approved
plans and specifications as outlined in the most current version,
at the time of the design, of the agency's Design
and Construction Guidelines for Dams in Texas. These requirements
would be necessary to keep construction costs down due to a delay.
Existing §299.27, Plan and/or Specification Changes and Amendments,
would be repealed and moved to proposed new §299.26 for better
organization within the subchapter.
Proposed new §299.26(a), (b), (d), and (e) would include language
from existing §299.27 that would be modified to be consistent
with Texas Register requirements and agency guidelines. The term "before
work commences under the changes" would be removed so that critical
work would not be delayed while waiting for approval. The terms "changes"
and "amendments" would be changed to "construction change order" to
ensure that the commission's rules would correspond with terms used
in construction to avoid confusion of terms. Language included in
subsection (b) would require the owner to submit a construction change
order for approval before the proposed changes start unless an emergency
has occurred. In that case, a construction change order would be submitted
after the work is performed. This is necessary to avoid costly delays
in construction. Language would also be included to notify the executive
director by telephone or electronic mail of emergency action taken
within 24 hours after becoming aware of the emergency. This requirement
would be necessary to allow the executive director to be aware of
the emergency. Additional language would require that if the time
needed for an approval of a change order will require that the construction
be halted, the work may be performed once the construction change
order is signed, sealed, and dated by the owner's professional engineer.
Language would also require that if the construction change order
is not approved, the owner would be responsible for having the work
modified to reflect the approved construction change order. This is
necessary to avoid costly delays in construction.
Proposed new §299.26(c) would include language on the process
and time frame the executive director would use to review the construction
change order according to the most current version, at the time of
the review, of the agency's Design and Construction
Guidelines for Dams in Texas. These requirements would be necessary
for construction to continue in a timely manner and provide the method
necessary to get a construction change order approved so construction
would not be delayed.
Existing §299.28, Noncompliance with Approved Plans and Specifications,
would be repealed and moved in part to proposed new §299.25 and
proposed new §299.71, Enforcement, for better organization within
the chapter.
Proposed new §299.27(a) would require submittal of a written
request to close the dam, prepared by a professional engineer, to
the executive director to close the dam before beginning closure as
described in the most current version, at the time of the closure,
of the agency's Design and Construction Guidelines
for Dams in Texas. The request would also include submittal
of an emergency action plan and documentation that all parts of the
proposed plan for closure of the dam had been met, as described in §299.22(d)(2)(B).
The commission determined that closure of a dam is a critical part
of construction, and it would be necessary that all essential phases
of construction be completed before closure of the dam would start.
This requirement of a submission requesting approval from the executive
director would require the professional engineer to verify that these
essential phases are complete before a request for closure of the
dam would be made and the dam could be safely closed. The commission
also determined that emergencies could possibly occur during this
phase of construction. The requirement for an emergency action plan
would be necessary to ensure that the owner has a plan for warning
the public downstream and taking appropriate action if an emergency occurs.
Proposed new §299.27(b) would include language that the owner
may begin closure of the dam after receiving written approval by the
executive director. The commission made this change based on comments
expressed by professional engineers on the process for approval.
Proposed new §299.27(c) would include language requiring the
owner to notify the executive director that the gate operation plan
had been completed with the request for closure of the dam. This is
necessary to ensure that a plan for operation of the gates is in place
in the event the gates would need to be operated during closure of
the dam to protect the dam.
Existing §299.29, Deliberate Impoundment, would be repealed
and moved to proposed new §299.2(12) and proposed new §299.28,
Deliberate Impoundment, for better organization within the subchapter.
Proposed new §299.28, Deliberate Impoundment, would include
language from existing §299.29 that would be modified to be consistent
with Texas Register requirements and agency guidelines. The requirement
would clarify that the request for deliberate impoundment would be
made in writing after the dam was substantially complete and that
approval would be provided after the executive director verifies that
construction was substantially complete according to the owner's professional
engineer. The commission determined that this requirement was necessary
to clarify as to when and how a request for deliberate impoundment
be made.
Existing §299.30, Certificate of Completion, would be repealed
and moved to proposed new §299.29, Notification of Completion,
for better organization within the subchapter.
Proposed new §299.29(a) would include language from existing §299.30
that would be modified to be consistent with Texas Register requirements
and agency guidelines and to change the time frame for notification
of completion. The existing time frame for submission of the notification
was immediately after construction. A time frame of 45 calendar days
would be more practical to allow the professional engineer additional
time to ensure that the construction would be substantially complete
before submitting the notification. The requirement for sealing, signing,
and dating the notification would ensure that the commission's rules
correspond to the requirements of the Texas Board of Professional
Engineers. Additional language would be added to allow the professional
engineer to submit the notification separate from the record drawings,
which take longer to prepare and would put an added burden on the
professional engineer.
Proposed new §299.29(b) and (c) concerning the type of information
that professional engineers and owners would include in notification
of project completion would include language from existing §299.30
that would be modified to be consistent with Texas Register requirements
and agency guidelines.
Existing §299.31, Record Drawings and Permanent Reference
Mark, would be repealed and moved to proposed new §299.30, Record
Drawings, and proposed new §299.31, Permanent Reference Mark,
for better organization within the subchapter.
Proposed new §299.30(a) would include language from existing §299.31
that would be modified to be consistent with Texas Register requirements
and agency guidelines and to change the time frame for submission
of record drawings. The existing time frame for submission of the
record drawings was as soon as possible after construction. A time
frame of six months would be more reasonable to allow the professional
engineer additional time to ensure that all construction changes would
be documented before submitting the record drawings. Additional language
would be added to require the record drawings to be sealed, signed,
and dated. This requirement would ensure that the commission's rules
correspond to the requirements of the Texas Board of Professional Engineers.
Proposed new §299.30(b) would allow the owner to have a professional
engineer submit a sealed, signed, and dated letter instead of another
set of drawings if no changes were made during construction. This
would reduce the cost of the project for the owner.
Proposed new §299.31, Permanent Reference Mark, would include
language from existing §299.30 that would be modified to be consistent
with Texas Register requirements and agency guidelines. A new requirement
would be included to require latitude and longitude of the permanent
reference mark(s) for ease in locating the mark(s) in the field. The
commission determined that reference mark(s) are difficult to locate
over time without such coordinates.
Proposed new §299.32, Gate Operation Plan, would require an
owner of a proposed dam with a gated principal spillway to develop
a gate operation plan before the completion of construction. The commission
determined that proper operation of the gates is important for the
safety of the public and that it is necessary to have the plan developed
before the end of construction. A reservoir can fill to levels greater
than the normal storage capacity during one rainfall event, and the
owner would need to know what procedures to follow during the event
to avoid putting downstream people at risk.
Proposed new §299.33(a) would require development of operation
and maintenance procedures for proposed dams before completion of
construction. Good operation and maintenance procedures will protect
a dam against deterioration, prolong the dam's life, and should be
initiated as soon as the dam is completed. Good operation and maintenance
procedures will reduce the risk for the owner and for the downstream
public.
Proposed new §299.33(b) would include a requirement that the
owner of any proposed dam shall provide the date the owner will turn
over the operation and maintenance to a property owner association,
homeowner association, or any other designated group to the executive
director. The executive director has received numerous complaints
from property owners associations, homeowner associations, and other
groups that ownership has been changed to the property owners association,
homeowner association, and other group without the knowledge of the
property owners association, homeowner association, or other group
and the executive director has had difficulty locating the owner for
correcting problems at the dam. This requirement would be necessary
to have the parties identified at the end of construction so there
could be a continuity of maintenance to avoid deterioration of the dam.
Proposed new §299.41, Owner's Responsibilities, would include
language from existing §299.2(c) and existing §299.3 that
would be modified to be consistent with Texas Register requirements
and agency guidelines. As indicated in Texas Water Code, §12.052(f),
the owner of a dam is responsible for the operation and maintenance
of the dam. The commission determined that the operation and maintenance
of a dam is extremely important to prevent deterioration and possibly
failure of the dam or appurtenant structures. Aging dams are more
susceptible to deterioration. Over 89% of the dams listed in the agency's
inventory of dams are over 25 years old. Therefore, the requirements
for addressing maintenance items as quickly as possible have become
even more important.
Proposed new §299.42(a)(1) concerning the ability of the executive
director to enter a person's property for the purpose of inspecting
a dam to ensure that the commission's rules correspond with Texas
Water Code, §12.017.
Proposed new §299.42(a)(2) would require the periodic inspections
of dams by the executive director based on hazard classification on
a five-year frequency for all high- and significant-hazard dams and
all large, low-hazard dams. Small and intermediate, low- hazard dams
would not be included in a periodic inspection schedule, but could
be inspected for determining hazard classification or assessing various
types of problems or conditions. The commission has determined that
there are currently 1,661 high- and significant-hazard and large,
low-hazard dams and that these 1,661 dams could be inspected on a
five-year frequency by the current staff of seven full-time employees
and through outsourcing contracts. The 1998 Executive Director's Task
Force on Dam Safety also recommended a five-year frequency. The commission
also determined that these dams present the greater potential for
loss of life to the downstream public and should be inspected on a
regular basis, instead of inspecting all of the 7,068 dams listed
in the agency's inventory of dams.
Proposed new §299.42(a)(3) would describe the elements that
may be included in the executive director's inspection. The inspection
may include a visual inspection and evaluation of the dam, appurtenant
structures, and downstream area; taking measurements; taking photographs
for documentation; conducting an evaluation of the hazard classification;
and reviewing and evaluating the owner's operation, maintenance, inspection
programs, and the emergency action plan. The commission determined
that these elements are the essential parts of an inspection for evaluating
the safety, integrity, and operation of a dam and appurtenant structures.
Proposed new §299.42(a)(4) would provide that the executive
director prepare an inspection report complete with recommendations,
possibly including hydrologic, hydraulic, or structural evaluations,
and send a copy to the owner. Owners have requested copies of reports
so that they could determine the locations of problems and the recommendations
for correcting the problems.
Proposed new §299.42(a)(5) would require the owner to respond
to the executive director concerning an inspection, if requested,
and to provide a plan of action with time frames for addressing all
of the recommendations. The commission determined that the executive
director has been using this method over the last year with considerable
success and that there would be greater success if this was a requirement
in the rules.
Proposed new §299.42(b)(1) would require the owner to inspect
the dam and appurtenant structures on a regular time frame and during
emergency events. The commission determined that regular inspections
by the owner would be invaluable for detecting problems at an early
stage and allowing the owner to make corrections before the problems
become more extensive and costly to repair. Inspections after significant
rainfall events and during emergency events would also help detect
problems early and allow correction.
Proposed new §299.42(b)(2) would require the owner to notify
the executive director by telephone or electronic mail within 24 hours
and in writing within five days after becoming aware of any problems
or damage that poses a threat to the dam. This requirement would be
necessary to allow the executive director to document the problem
or damage.
Proposed new §299.42(b)(3) would require the owner to submit
all engineering reports prepared by the owner's professional engineer
under this section to the executive director for review within 45
calendar days after receipt of the report. Language would be added
to require the engineering inspection report to include the date of
the inspection, a description of the items observed during the inspection,
findings, and recommendations. This requirement would allow the executive
director to review the report as soon as possible and respond to the
owner so that corrections recommended by the executive director can
be made with other corrections.
Proposed new §299.42(b)(4) would include language that would
allow the owner to have an engineering inspection by a professional
engineer on a more frequent basis than described for the executive
director. The executive director may use an engineering inspection
report prepared by the owner's professional engineer or a professional
engineer from a federal agency in lieu of making a periodic inspection.
The language on the frequency of inspections by the owner was recommended
in the most recent stakeholder meeting. This language was recommended
by the 1998 Executive Director's Task Force on Dam Safety to avoid
duplication of effort.
Proposed new §299.43, Operation and Maintenance, would require
the owner to develop an operation and maintenance program. The commission
determined that a good operation and maintenance program protects
a dam against deterioration and prolongs the dam's life and that a
poorly maintained dam will deteriorate and could fail. Nearly all
parts of the dam and appurtenant structures are susceptible to deterioration
if not properly maintained. The executive director has numerous examples
of poorly maintained dams. This requirement is necessary to provide
owners with a tool for performing maintenance on a regular basis to
provide safe dams and appurtenant structures.
Proposed new §299.43(a) would require owners to implement
an operation and maintenance program. Language would be added that
the owner may use the most current version, at the time of the evaluation,
of the agency's Guidelines for Operation
and Maintenance of Dams in Texas, a manual, checklist, or some
other procedure to demonstrate implementation of the program. This
requirement is necessary to have owners develop some type of operating
and maintenance program using some type of procedure.
Proposed new §299.43(a)(1) would require schedules for engineering
and maintenance inspections in the owner's program. This requirement
would provide owners with an easy way of tracking inspections for
documentation purposes.
Proposed new §299.43(a)(2) would require the inclusion of
any restrictions imposed by the professional engineer's design in
the operation and maintenance manual. This requirement is necessary
because these restrictions are important for the safety of the dam
and must be followed.
Proposed new §299.43(a)(3) would list the types of maintenance
items to be addressed by the owner and when they should be addressed.
This would allow the owner to track his maintenance for each item
and have an easy way to check for maintenance items.
Proposed new §299.43(a)(4) would require inclusion of a plan
for monitoring any instrumentation at the dam and appurtenant structures.
This would allow the owner to track the instrumentation readings and
know when a reading becomes critical.
Proposed new §299.43(b) would require the owner to document
operation and maintenance activities undertaken and to provide the
documentation to the executive director upon request of the executive
director. The commission determined it is necessary for the owner
to document the operation and maintenance activities for the record
and that the review would be best performed when requested by the
executive director.
Proposed new §299.44(a) would require owners of all existing
intermediate- and large-size dams with a gated principal spillway
to develop a gate operation plan within two years after the effective
date of the rules. The commission determined that proper operation
of a gated principal spillway is important for the safety of the public
and that it is necessary to have an operation plan in place so the
owner would know what procedures to follow during normal operating
conditions or during flood events to avoid putting downstream people
at risk. The two-year time frame would allow the owner time to develop
the gate operation plan and to notify the executive director that
the plan is either completed or that a gate operation plan already
exists. Although not specifically identified in Texas Water Code, §12.052,
the commission determined that gate operation plans would be part
of the maintenance of dams (preserving from failure), and therefore,
they are added as a requirement in the rules.
Proposed new §299.44(b) would list the gate regulating procedures
and a method for coordinating releases, if applicable, that need to
be included in the gate operation plan. The commission determined
that these requirements are the most important parts of a gate operation
plan and that the owner needs to have a plan to follow during normal
operating conditions, flood events, and power failures.
Proposed new §299.44(c) would provide that the gate operation
plan is an appendix to the emergency action plan. A gate operation
plan would be considered an integral part of the emergency action
plan since it includes the procedures to follow during an emergency
operation of the gates. Language would be added to require that if
the owner submits a copy of the gate operation plan, the executive
director shall file it with the owner's emergency action plan in the
agency's confidential, permanent records. The Office of the Attorney
General determined in a letter opinion in 2005 that emergency action
plans are considered confidential and are not subject to public information
requests. A gate operation plan would be considered an integral part
of that plan.
Proposed new §299.45(a) would require an owner to make emergency
repairs under the supervision of a professional engineer and implement
the emergency action plan as soon as possible after the emergency
is discovered and evaluated without having to obtain approval from
the executive director. The commission determined that it is essential
that repairs are initiated as quickly as possible to avoid more significant
damage or a failure and that the emergency action plan is implemented
to alert the downstream public.
Proposed new §299.45(b) would require the owner to notify
the executive director by telephone or electronic mail within 12 hours
after the emergency is discovered and evaluated. This requirement
would be necessary to allow the executive director to be aware of
the emergency.
Proposed new §299.45(c) would require the owner to have a
professional engineer develop plans for permanent repairs after the
emergency repairs are completed and submit the plans for review and
approval. This requirement would be necessary to be consistent with
requirements of the Texas Board of Professional Engineers.
Proposed new §299.46(a) would require the owner to maintain
records and reports, if available, on the inspection, operation, and
maintenance of the dam. This requirement would be necessary to provide
a historical record of the dam in the event problems develop and a
record of all features at the dam. The commission determined that
in the event of a problem, records have been invaluable in developing
corrections to the problems.
Proposed new §299.46(b) would include a requirement that legible
or electronic copies be maintained by the owner in a secure location
designated by the owner that is accessible to the owner for the life
of the dam. Proposed new §299.46(c) would include a requirement
that the records, or access to the records, shall be provided to the
executive director upon request. These two requirements are necessary
to prevent unauthorized access to the records and to allow the executive
director to determine if the dam is being inspected, operated, and
maintained according to the requirements in the rules and accepted
engineering practices.
Proposed new §299.46(d) would include a new requirement that
an owner shall transfer all records to a new owner when there is an
ownership change. This requirement is necessary to ensure that the
new owner has access to all records.
Existing §299.51, Removal of Dams and Reservoirs, would be
repealed and moved to proposed new §299.51, Removal or Breach
of Dams, for better organization within the subchapter.
Proposed new §299.51(a) would require that the owner would
be required to submit plans to the executive director for the removal
or breaching of a dam. This requirement would be necessary to be consistent
with other sections in the rules and to ensure that the removal or
breach is properly designed.
Proposed new §299.51(b) would require that the owner have
a professional engineer submit plans for the removal or breach of
a dam as outlined in the most current version, at the time of the
design, of the agency's Dam Removal Guidelines.
The commission determined that removing or breaching a dam could alter
the flood characteristics of the stream and could endanger downstream
lives and property if not performed properly and that all items in
the guidelines be addressed to provide a safe situation to downstream
lives and property. The requirement for sealing, signing, and dating
the removal or breach plans would ensure that the commission's rules
correspond to the requirements of the Texas Board of Professional
Engineers.
Proposed new §299.51(c) would provide that the owner may also
be required to address environmental and social impacts for the removal
or breach of a dam as described in the most current version, at the
time of the design, of the agency's Dam Removal Guidelines
, which may require approval from other agencies
before construction can begin. The commission determined that removing
or breaching a dam could alter the environment and increase property
or human health and safety concerns downstream if not performed properly
and that all items needed to be addressed to minimize the risk downstream.
The commission also determined that the executive director's approval
may not be the only approval necessary to perform the removal or breach
of a dam.
Proposed new §299.51(d) would provide that the owner may be
required to restore the property to the condition of the site before
the dam was constructed. The commission determined that there are
cases where a dam may exist on property not owned by the dam owner
and the property owner may require the dam owner to restore the property
to pre-construction conditions.
Proposed new §299.51(e) concerning the requirements for written
approval of dam removal would include language for the review and
approval method for removal or breaching a dam. This is necessary
to provide owners with a review process.
Proposed new §299.51(f) would require that an owner shall
provide the executive director within 45 days of completion of the
breach or removal a notification of completion. Language would also
require that an inspection be conducted to verify that the dam had
been removed or breached. The commission determined that it is necessary
for the owner to notify the executive director so the executive director
can verify that the work had been completed according to the approved
plans to avoid a partially removed or partially breached dam being
left in place that could cause problems downstream if the breach enlarged
or continued to cut down, releasing additional waters downstream.
Proposed new §299.52, Abandonment of Dams, would include language
from existing §299.2(c) and would be modified to be consistent
with Texas Register requirements and agency guidelines. Language would
be included to provide that it would be the owner's responsibility
to remove or breach the dam at the owner's expense.
Existing §299.61, Emergency Action, would be repealed and
moved to proposed new §299.72, Emergency Orders, for better organization
within the chapter.
Proposed new §299.61(a) would require owners of all high-
and significant-hazard dams to prepare an emergency action plan to
follow in the event of, or threat of, a dam emergency. Emergency action
plans are essential to provide owners with a plan for promptly responding
during an emergency and minimizing consequences. An emergency may
occur with little or no warning, thereby providing minimal time to
assess and respond. These plans are designed to minimize impacts and
reduce reaction time. The commission determined that the need for
emergency action plans is one of the most critical requirements needed
for existing dams.
Proposed new §299.61(b) would include a requirement that would
give the owner two years to submit the emergency action plan after
the effective date of the rules. There are 1,654 dams that are currently
listed as high- and significant-hazards dams. Currently, there are
only 136 high- and significant-hazard dams that have been documented
by the executive director as having an emergency action plan. The
owners would need time to develop the emergency action plans.
Proposed new §299.61(c) would include a requirement that a
plan for addressing emergencies during construction of a proposed
high- or significant-hazard dam be submitted for review before either
requesting closure of the dam or upon completion of construction of
the dam, if the dam does not require a closure section. History has
shown that failures do occur during construction. A properly prepared
emergency action plan can help the owners protect their investment
and protect downstream lives and property. Review of this plan would
be necessary to ensure that there is a method for addressing emergencies.
Proposed new §299.61(d) would include language that the owner
should use guidelines provided by the executive director or a format
approved by the executive director before starting the plan. A guideline
would provide consistency between emergency action plans. The commission
determined that different guidelines will be provided depending on
the size of the dam.
Proposed new §299.61(e) concerns the review method for reviewing
an emergency action plan. This is necessary to provide with the process
for review of the emergency action plan.
Proposed new §299.61(f) would require that the emergency action
plan be filed in the agency's confidential, permanent records. The
Office of the Attorney General determined in an opinion letter in
2005 that emergency action plans are considered confidential and are
not subject to public information requests.
Proposed new §299.61(g) would require that the owner review
the emergency action plan annually, update the emergency action plan
as necessary, and submit annual updates to the executive director
beginning three years after the effective date of these rules. This
requirement would be necessary since personnel change and new personnel
need to be trained in order to react properly during an emergency
and to provide a time frame for the owner to submit any updates. Language
would also be added that if the emergency action plan had been reviewed
and the owner determined that no updates were necessary, the owner
would be required to notify the executive director in writing if updates
to the emergency action plan had not been adopted or implemented.
This requirement would be necessary to ensure that the owner is reviewing
the emergency action plan.
Proposed new §299.61(h) would include language requiring a
table top exercise of the emergency action plan on a frequency no
greater than five years. The success of an emergency action plan will
often depend upon the training of employees, including periodic exercises.
All parties need to know their roles and responsibilities. This requirement
would be necessary for the protection of the downstream public.
Proposed new §299.62, Security of Dams, would include a requirement
that owners of high-hazard dams, that may need increased security
due to the critical nature of the dam and reservoir, shall address
security at their dams after being notified in writing by the executive
director within six months of the effective date of these rules to
prevent unauthorized operation or access and meet backup power requirements
to ensure operation of the dam and appurtenant structures. The requirement
would be for these owners to develop a security plan within two years
of being notified by the executive director and submit the plan to
the executive director for review. The security plan would be filed
in the confidential, permanent records of the executive director.
If a request for a security plan is received, the executive director
will file a request for an opinion from the Office of the Attorney
General under Texas Government Code, §418.182. Over half of the
dams identified by the executive director as being dams with increased
security needs, have already had a security inspection and have been
advised of security needs. The commission determined that security
plans need to be developed on these dams because of their importance
in the state. The commission also determined that backup power requirements
need to be addressed by owners in the event of a power failure. This
became evident during Hurricane Rita in 2005, when one owner had to
operate spillway gates with backup power to prevent further damage
to the dam. The commission further determined that it was necessary
to provide a time frame for notifying the owners and to provide the
owners time to begin the process of addressing security. Although
not specifically identified in Texas Water Code, §12.052, the
commission determined that security plans would be part of the maintenance
of dams (preserving from failure), and therefore, they are added as
a requirement in the rules.
Proposed new §299.71, Enforcement, would include language
from existing §299.2(a) and existing §299.28 that would
be modified to be consistent with Texas Register requirements and
agency guidelines.
Proposed new §299.72, Emergency Orders, would include language
from existing §299.61 that would be modified to be consistent
with Texas Register requirements and agency guidelines, and to correspond
with Texas Water Code, Chapter 35.
FISCAL NOTE: COSTS TO STATE AND LOCAL GOVERNMENT
Nina Chamness, Analyst, Strategic Planning and Assessment Section,
determined that, for the first five-year period the proposed new rules
are in effect, significant fiscal implications are anticipated for
the agency. The agency will need additional funding for review and
inspection activities. Additional funding may also be needed for enforcement
and support activities. Fiscal implications, which may be significant,
are also anticipated for units of state or local government and individuals
who own or operate high- and significant-hazard dams in the state
due to the implementation or enforcement of the proposed rules.
The proposed rulemaking action repeals current rules relating to
the Dam Safety Program and replaces them with new rules. The proposed
new rules more closely align with federal requirements and are more
consistent with accepted engineering practices. They also address
criteria concerning the design, review, and approval of construction
plans and specifications for dams, as well as dam operation and maintenance,
inspection, repair, removal, emergency management, and site security.
New requirements for emergency action plans, gate operation plans,
and security plans are added and owner responsibilities are better
defined. Criteria for the enforcement of rules for proposed and existing
dams are also specified.
The proposed rules change the definition of a dam, thus affecting
the number of dams under regulation of the agency. This change would
more closely align the state definition of a dam with that of federal
rules and remove approximately 5,807 small- and intermediate-size,
low-hazard dams from agency inspection schedule out of a total of
approximately 7,460 small, intermediate, and large dams.
However, the proposed rules would also require the remaining estimated
1,654 high- and significant-hazard dams to be inspected every five
years, but of these dams, those designated to have increase security
needs would have to be inspected once every two years. The annual
inspection workload for the agency under the proposed rules would
be approximately 453 dams per year. At this time, the Dam Safety Program
uses Federal Emergency Management Agency grant funding to support
a portion of its inspection activities. The agency currently contracts
for the inspection of approximately 80 - 140 dams each year, and contracting
services would still be needed under the proposed rules to ensure
timely inspections requested by the public for low- and significant-hazard
dams. Since dam owners would be required to develop and implement
emergency action plans, gate operation plans, and security plans under
the new rules, agency staff would also be required to review and approve
these plans along with newly required annual reports on operation
and maintenance, written requests for the closure of dams, and reports
of changes in dam ownership. In addition, the agency must update and
ensure the completeness of the dam inventory database. Current staffing
levels will not permit the agency to comply with the increased inspection,
plan review, and administrative requirements of the proposed rules.
The agency estimates that it will need a minimum of $963,309 in the
first year to add eight additional Professional Engineers, three Engineering
Specialists, and one Administrative Technician to its staff in order
to adequately perform the tasks required by the proposed rules. The
agency would also need to request an estimated one-time cost of $250,000
in the first year to modify the Consolidated Compliance Enforcement
Data System database to incorporate data pertaining to the results
of Dam Safety Investigations. Total costs in year one would be approximately
$1.2 million. The second year the proposed rules are in effect, the
agency would need to add five additional Professional Engineers, two
Engineering Specialists, and one Administrative Technician to its
staff for a total of 20 staff members. Total costs for the second
through fifth year the proposed rules are in effect could be as much
as $1.6 million per year. Over a five-year period, funding needed
is estimated to be as much as $7.6 million. The agency would be required
to seek additional appropriated funds to adequately implement the
proposed rules.
Units of state or local governments, including river authorities,
which own or operate dams, would be affected by the new requirements
of the proposed rules. In particular, requirements for emergency action
plans, gate operation plans, and security plans are expected to result
in additional costs, which may be significant, depending upon the
size of the dam and the budget of the governmental entity. Staff estimates
that there are 17 high- or significant-hazard dams owned by state
agencies and approximately 985 high- or significant-hazard dams across
the state owned by municipalities, counties, river authorities, water
districts or soil and water conservation districts. If any of these
owners do not have plans, programs, or manuals that comply with the
proposed rules, staff estimates that it may cost as much as $20,000
to $30,000 per dam during the first two years to implement the proposed
rules. Maintenance and inspection requirements could cost these governmental
entities as much as $5,000 to $10,000 per year over the third through
fifth year the proposed rules would be in effect. Total costs for
state agencies and local governments over a five-year period could
be as much as $35,000 to $60,000 per dam, or $35 to $60 million statewide.
Local governments that have authority to increase fee revenue may
choose to do so to cover the anticipated costs associated with dam
maintenance or rehabilitation. However, staff experience has indicated
that local governments do not increase fee revenue for maintenance
and rehabilitation costs so no significant increases to the revenues
of local governments are anticipated.
PUBLIC BENEFITS AND COSTS
Nina Chamness also determined that for each year of the first five
years the proposed new rules are in effect, the public benefits anticipated
from the changes seen in the proposed rules will be greater protection
of public safety due to safer and better maintained dams.
Staff has estimated that there may be as many as 219 individually
owned, 407 business owned, and 26 public utility owned high- or significant-hazard
dams statewide. If any of these owners do not have plans, programs,
or manuals that comply with the proposed rules, staff estimates that
it may cost as much as $20,000 to $30,000 per dam per year in the
first two years to implement the proposed rules. Maintenance and inspection
requirements could cost these governmental entities as much as $5,000
to $10,000 per year over the third through fifth year the proposed
rules would be in effect. Costs over a five-year period could be as
much as $35,000 to $60,000 per dam or $22.8 to $39 million statewide
for business entities.
SMALL BUSINESS AND MICRO-BUSINESS ASSESSMENT
Adverse fiscal implications, some of which may be significant,
are anticipated for small- or micro-businesses that own high- or significant-hazard
dams. Current dam inventory data does not provide the information
needed to determine how many of the 219 individually owned, 407 business
owned, and 26 public utility owned high-or significant-hazard dams
are owned or operated by small or micro-businesses. Small or micro-businesses
would incur the same types of costs under the proposed rules as those
incurred by individuals, large businesses, or local governments.
SMALL BUSINESS REGULATORY FLEXIBILITY ANALYSIS
The commission has reviewed this proposed rulemaking and determined
that a small business regulatory flexibility analysis is not required
because the proposed rules are necessary to protect public safety.
These rules are similar to the federal requirements for dam safety
and are necessary for all dams as defined in these rules, regardless
of who owns the dams. As discussed throughout this preamble, there
are no other feasible alternatives to the requirements in these rules.
In addition, the proposed rules would exempt a number of existing
structures, which are more likely to be owned by small or micro-businesses,
from the definition of a dam. If a small or micro-business owns or
operates a high- or significant-risk dam, it must comply with the
proposed rules in order to protect public safety, public property,
and the environment.
LOCAL EMPLOYMENT IMPACT STATEMENT
The commission has reviewed this proposed rulemaking and determined
that a local employment impact statement is not required because the
proposed rules do not adversely affect a local economy in a material
way for the first five years that the proposed rules are in effect.
DRAFT REGULATORY IMPACT ANALYSIS DETERMINATION
The commission determined that a regulatory analysis under Texas
Government Code, §2001.0225, is not necessary for this rulemaking
since these proposed new rules do not meet the definition of a "major
environmental rule" as defined in Texas Government Code, §2001.0225(g)(3).
A "major environmental rule" is a rule that is specifically intended
to protect the environment or reduce risks to human health from environmental
exposure, and that may adversely affect in a material way the economy,
a sector of the economy, productivity, competition, jobs, or the public
health and safety of the state or a sector of the state. The purpose
of this rulemaking is to provide greater clarity in rules relating
to the Dam Safety Program, and increased protection of public health
and safety due to new requirements for emergency action plans, gate
operations plans, security plans, and increased inspection requirements.
While these rules could result in protection of the environment,
the primary intent of the rules is to protect property and human health
and safety as provided under Texas Water Code, §12.052(d). These
proposed new rules are also not intended to reduce risks to human
health from environmental exposure, but are instead intended to reduce
risks to property and humans from the failure of a dam. Revising and
clarifying the dam safety rules do not have any adverse effects on
the environment or public health and safety of the state or section
of the state; rather, a more detailed outline of the process for classification,
construction, upgrading, removal, and emergency management of dams
should improve the public health and safety of the state or a sector
of the state.
Even if this proposed rulemaking could be interpreted as specifically
intending to protect the environment or reduce risks to human health
from environmental exposure, these proposed new rules do not adversely
affect in a material way the economy, productivity, competition, jobs,
the environment, or the public health and safety of the state or a
sector of the state. While costs for maintenance and construction
of dams may increase for many owners, improvement in dam safety will
save money in the long run. The costs from dam failures could be great.
These rules should not adversely impact the economy, competition, or jobs.
Additionally, even if this rulemaking could be construed to be
a "major environmental rule," the rules do not exceed a standard set
by federal law, exceed an express requirement of state law, exceed
a requirement of a delegation agreement between the state and federal
law, and is not adopted solely under the agency's general powers.
These new rules will reflect accepted engineering practices. Based
on this assessment, the proposed rulemaking does not constitute a
major environmental rule that falls within the applicability of Texas
Government Code, §2001.0225, and thus is not subject to the regulatory
analysis provisions of §2001.0225.
The commission invites public comment regarding this draft regulatory
impact analysis determination.
TAKINGS IMPACT ASSESSMENT
The commission evaluated these proposed new rules and performed
an assessment of whether these proposed new rules constitute a takings
under Texas Government Code, Chapter 2007. The primary purpose of
this proposed rulemaking is to provide clarity and specificity, and
to add requirements reflecting the best practices of accepted engineering
practices for the classification, design, construction, upgrading,
repair, removal, and emergency management of dams and reservoirs.
The proposed rulemaking would substantially advance these stated purposes
because the proposed rules provide more detail and specificity. They
do implement current engineering industry standards, such as outlining
the process for removal of a dam and adding requirements for emergency
action plans, gate operation plans, and security plans.
Promulgation and enforcement of these proposed new rules would
be neither a statutory nor a constitutional taking of private real
property. The proposed new rules do not affect a landowner's rights
in private real property, in whole or in part, temporarily or permanently.
These proposed new rules do not burden, restrict, or limit the owner's
right to property nor will it reduce the land value by 25% or more
beyond that which would otherwise exist in the absence of the proposed
new rules. These proposed new rules do not change the classification
of an existing dam and reservoir; instead, the proposed new rules
initiate requirements upon owners, such as creating a security plan,
a gate operation plan, an emergency action plan, and an operation
and maintenance program. Therefore, there are no burdens imposed on
private real property, and the benefits to the state are more modern
dam and reservoir rules, which should result in safer dams in the
State of Texas. For these reasons, the proposed new rules do not constitute
a taking under Texas Government Code, Chapter 2007.
CONSISTENCY WITH THE COASTAL MANAGEMENT PROGRAM
The commission reviewed the proposed rules and found that they
are neither identified in Coastal Coordination Act Implementation
Rules, 31 TAC §505.11(b)(2) or (4), nor will they affect any
action/authorization identified in Coastal Coordination Act Implementation
Rules, 31 TAC §505.11(a)(6). Therefore, the proposed rules are
not subject to the Texas Coastal Management Program.
The commission invites public comment regarding this coastal management
program determination.
ANNOUNCEMENT OF HEARING
A public hearing on this proposal will be held in Austin on August
19, 2008, at 10:00 a.m. at the Texas Commission on Environmental Quality
complex at 12100 Park 35 Circle in Building E, Room 201S. The hearing
will be structured for the receipt of oral or written comments by
interested persons. Individuals may present oral statements when called
upon in order of registration. There will be no open discussion during
the hearing; however, an agency staff member will be available to
discuss the proposal 30 minutes prior to the hearing and will answer
questions before and after the hearing.
Persons who have special communication or other accommodation needs
who are planning to attend the hearing should contact Michael Parrish
at (512) 239-2548. Requests should be made as far in advance as possible.
SUBMITTAL OF COMMENTS
Comments may be submitted to Michael Parrish, MC 205, Texas Register
Team, Office of Legal Services, Texas Commission on Environmental
Quality, P.O. Box 13087, Austin, Texas 78711-3087, or faxed to (512)
239-4808. All comments should reference Rule Project Number 2008-005-299-CE.
Comments must be received by 5:00 p.m., August 25, 2008. Copies of
the proposed rulemaking can be obtained from the commission's web
site at http://www.tceq.state.us/nav/rules/propose_adopt.html
. For further information or questions concerning this proposal,
please contact Warren Samuelson, Field Operations Support Division,
at (512) 239-5195.
SUBCHAPTER A. GENERAL PROVISIONS
(Editor's note: The text of the following sections proposed
for repeal will not be published. The sections may be examined in
the offices of the Texas Commission on Environmental Quality or in
the Texas Register office, Room 245, James Earl Rudder Building, 1019
Brazos Street, Austin.)
STATUTORY AUTHORITY
These repeals are proposed under the authority granted to the commission
in Texas Water Code (TWC), §5.012, which provides that the commission
is the agency responsible for implementing the constitution and laws
of the state relating to conservation of natural resources and protection
of the environment; §5.013, which establishes the commission's
authority over various statutory programs, such as dam safety; §5.103
and §5.105, which establish the commission's general authority
to adopt rules; §12.052, which establishes the commission's authority
to promulgate rules for the safe construction, maintenance, repair,
and removal of dams located in this state; and §7.002, which
authorizes the commission to enforce provisions of the TWC.
These proposed repeals implement TWC, §§5.103, 5.105, and 12.052.
§299.1.Definitions.
§299.2.General.
§299.3.Duties, Obligations, and Liabilities of Dam Owners.
§299.4.Registered Engineer.
§299.5.Exception.
This agency hereby certifies that the proposal
has been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803561
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
(Editor's note: The text of the following sections proposed
for repeal will not be published. The sections may be examined in
the offices of the Texas Commission on Environmental Quality or in
the Texas Register office, Room 245, James Earl Rudder Building, 1019
Brazos Street, Austin.)
STATUTORY AUTHORITY
These repeals are proposed under the authority granted to the commission
in Texas Water Code (TWC), §5.012, which provides that the commission
is the agency responsible for implementing the constitution and laws
of the state relating to conservation of natural resources and protection
of the environment; §5.013, which establishes the commission's
authority over various statutory programs, such as dam safety; §5.103
and §5.105, which establish the commission's general authority
to adopt rules; §12.052, which establishes the commission's authority
to promulgate rules for the safe construction, maintenance, repair,
and removal of dams located in this state; and §7.002, which
authorizes the commission to enforce provisions of the TWC.
These proposed repeals implement TWC, §§5.103, 5.105, and 12.052.
§299.11.Classification of Dams.
§299.12.Size Classification Criteria.
§299.13.Hazard Classification Criteria.
§299.14.Hydrologic Criteria for Dams.
§299.15.Evaluation of Existing Dams.
§299.16.Interim Alternatives.
§299.17.Emergency Management.
§299.18.Variance.
This agency hereby certifies that the proposal
has been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803563
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
(Editor's note: The text of the following sections proposed
for repeal will not be published. The sections may be examined in
the offices of the Texas Commission on Environmental Quality or in
the Texas Register office, Room 245, James Earl Rudder Building, 1019
Brazos Street, Austin.)
STATUTORY AUTHORITY
These repeals are proposed under the authority granted to the commission
in Texas Water Code (TWC), §5.012, which provides that the commission
is the agency responsible for implementing the constitution and laws
of the state relating to conservation of natural resources and protection
of the environment; §5.013, which establishes the commission's
authority over various statutory programs, such as dam safety; §5.103
and §5.105, which establish the commission's general authority
to adopt rules; §12.052, which establishes the commission's authority
to promulgate rules for the safe construction, maintenance, repair,
and removal of dams located in this state; and §7.002, which
authorizes the commission to enforce provisions of the TWC.
These proposed repeals implement TWC, §§5.103, 5.105, and 12.052.
§299.21.Applicability.
§299.22.Approval of Plans and Specifications.
§299.23.Content of Construction Plans and Specifications.
§299.24.Maintenance of Records.
§299.25.Construction Progress Report.
§299.26.Construction Inspection.
§299.27.Plan and/or Specification Changes and Amendments.
§299.28.Noncompliance with Approved Plans and Specifications.
§299.29.Deliberate Impoundment.
§299.30.Certificate of Completion.
§299.31.Record Drawings and Permanent Reference Mark.
This agency hereby certifies that the proposal
has been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803565
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
(Editor's note: The text of the following section proposed
for repeal will not be published. The section may be examined in the
offices of the Texas Commission on Environmental Quality or in the
Texas Register office, Room 245, James Earl Rudder Building, 1019
Brazos Street, Austin.)
STATUTORY AUTHORITY
The repeal is proposed under the authority granted to the commission
in Texas Water Code (TWC), §5.012, which provides that the commission
is the agency responsible for implementing the constitution and laws
of the state relating to conservation of natural resources and protection
of the environment; §5.013, which establishes the commission's
authority over various statutory programs, such as dam safety; §5.103
and §5.105, which establish the commission's general authority
to adopt rules; §12.052, which establishes the commission's authority
to promulgate rules for the safe construction, maintenance, repair,
and removal of dams located in this state; and §7.002, which
authorizes the commission to enforce provisions of the TWC.
The proposed repeal implements TWC, §§5.103, 5.105, and 12.052.
§299.51.Removal of Dams and Reservoirs.
This agency hereby certifies that the proposal
has been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803568
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
(Editor's note: The text of the following section proposed
for repeal will not be published. The section may be examined in the
offices of the Texas Commission on Environmental Quality or in the
Texas Register office, Room 245, James Earl Rudder Building, 1019
Brazos Street, Austin.)
STATUTORY AUTHORITY
The repeal is proposed under the authority granted to the commission
in Texas Water Code (TWC), §5.012, which provides that the commission
is the agency responsible for implementing the constitution and laws
of the state relating to conservation of natural resources and protection
of the environment; §5.013, which establishes the commission's
authority over various statutory programs, such as dam safety; §5.103
and §5.105, which establish the commission's general authority
to adopt rules; §12.052, which establishes the commission's authority
to promulgate rules for the safe construction, maintenance, repair,
and removal of dams located in this state; and §7.002, which
authorizes the commission to enforce provisions of the TWC.
The proposed repeal implements TWC, §§5.103, 5.105, and 12.052.
§299.61.Emergency Action.
This agency hereby certifies that the proposal
has been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803570
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
STATUTORY AUTHORITY
These new sections are proposed under the authority granted to
the commission in Texas Water Code (TWC), §5.012, which provides
that the commission is the agency responsible for implementing the
constitution and laws of the state relating to conservation of natural
resources and protection of the environment; §5.013, which establishes
the commission's authority over various statutory programs, such as
dam safety; §5.103 and §5.105, which establish the commission's
general authority to adopt rules; §12.052, which establishes
the commission's authority to promulgate rules for the safe construction,
maintenance, repair, and removal of dams located in this state; and §7.002,
which authorizes the commission to enforce provisions of the TWC.
These proposed new sections implement TWC, §§5.103, 5.105, and 12.052.
§299.1.Applicability.
(a) This chapter applies to design, review, and approval
of construction plans and specifications; and construction, operation
and maintenance, inspection, repair, removal, emergency management,
site security, and enforcement of dams that:
(1) have a height greater than or equal to 25 feet
and a maximum storage capacity greater than or equal to 15 acre-feet,
as described in paragraph (2) of this subsection;
(2) have a height greater than six feet and a maximum
storage capacity greater than or equal to 50 acre-feet; or
Figure: 30 TAC §299.1(a)(2) (.pdf)
(3) are a high- or significant-hazard dam as defined
in §299.14 of this title (relating to Hazard Classification Criteria),
regardless of height or maximum storage capacity.
(b) This chapter provides the requirements for dams,
but does not relieve the owner from meeting the requirements in Texas
Water Code (TWC), Chapter 11, and Chapters 213, 295, and 297 of this
title (relating to Edwards Aquifer; Water Rights, Procedural; and
Water Rights, Substantive; respectively). All applicable requirements
in those chapters will still apply.
(c) This chapter does not apply to:
(1) dams designed by, constructed under the supervision
of, and owned and maintained by federal agencies such as the Corps
of Engineers, International Boundary and Water Commission, and the
Bureau of Reclamation;
(2) embankments constructed for roads, highways, and
railroads, including low-water crossings, that may temporarily impound
floodwater, unless designed to also function as a detention dam;
(3) dikes or levees designed to prevent inundation by floodwater;
(4) off-channel impoundments authorized by the commission
under TWC, Chapter 26; and
(5) above-ground water storage tanks.
(d) All dams must meet the requirements in this chapter,
including those that are exempt from the requirements in Subchapter
C of this chapter (relating to Construction Requirements) and those
that are granted an exception as defined in §299.5 of this title
(relating to Exception).
§299.2.Definitions.
The following words and terms in this section are in addition
to the definitions in §3.2 of this title (relating to Definitions).
The words and terms in this section, when used in this chapter, have
the following meanings.
(1) Abandon--The owner no longer maintaining a dam
for a period of ten years, or refusing to maintain the dam.
(2) Accepted engineering practices--The application
of design and analysis methods that are commonly used by professional
engineers in their field of expertise and are well documented in published
design manuals, codes of practice, text books, and engineering journals.
(3) Alteration--Any change to a dam or appurtenant
structures that affects the integrity, safety, and operation of the
dam, including, but not limited to:
(A) changing the height of a dam;
(B) increasing the normal pool or principal spillway
elevation, or changing the hydraulic capability of the principal spillway; or
(C) changing the original elevation, physical dimensions,
or hydraulic capability of an emergency spillway.
(4) Appurtenant structures--The outlet works and controls,
spillways and controls, gates, valves, siphons, access structures,
bridges, berms, drains, hydroelectric facilities, instrumentation,
and other structures related to the operation of a dam.
(5) Breach--An excavation or opening, either controlled
of a result of a failure of the dam, through a dam or spillway that
is capable of completely draining the reservoir down to the approximate
original topography so the dam will no longer impound water, or partially
draining the reservoir to lower impounding capacity.
(6) Breach analysis--The analyses of potential dam
failure scenarios, including overtopping and piping (magnitude, duration,
and location), using accepted engineering practices, to evaluate downstream
hazard potential or to develop inundation maps.
(7) Breach inundation area--An area that would be flooded
as a result of a dam failure.
(8) Closure of dam--The commencement of placing backfill
within the closure section of the dam.
(9) Closure section--The section of the dam left open
during construction of a proposed dam in order to pass floodwaters
through the dam without endangering the dam.
(10) Commence construction--An actual, visible activity
beyond planning or land acquisition that initiates the beginning of
the construction of a dam in the manner specified in the approved
construction plans and specifications for that dam. The action must
be performed in good faith with the intent to continue with the construction
through completion.
(11) Conceptual design--A design that presents a location
and proposed plan of the dam and appurtenant structures and elevations
of all pertinent features of the dam.
(12) Construction--Building a proposed dam and appurtenant
structures capable of storing water.
(13) Construction change order--A document recommended
by the owner's professional engineer and signed by the owner's contractor
and the owner that authorizes a significant addition, deletion, or
revision of the approved construction plans and specifications that
has a material impact on the safety and integrity of the dam.
(14) Dam--Any barrier or barriers, with any appurtenant
structures, constructed for the purpose of either permanently or temporarily
impounding water.
(15) Dam failure--breach and uncontrolled release of the reservoir.
(16) Deficient dam--A dam that fails to meet the requirements
of this chapter and poses a threat to human life or property.
(17) Deliberate impoundment--The intentional impoundment
of water in the reservoir, including:
(A) closing the lowest planned outlet or spillway;
(B) blocking the diversion works that are used during
construction to divert water around the construction area; and
(C) beginning the closure of the dam.
(18) Design flood--The flood used in the design and
evaluation of a dam and appurtenant structures, particularly for determining
the size of spillways, outlet works, and the effective crest of the dam.
(19) Detention dam--A dam that has an impoundment that
is normally dry and has an ungated outlet structure that is designed
to completely drain the water impounded during a flood within five days.
(20) Drawdown--The change in surface elevation of a
reservoir due to a withdrawal of water from the reservoir.
(21) Effective crest of the dam--The elevation of the
lowest point on the crest (top) of the dam, excluding spillways.
(22) Emergency action plan--A written document prepared
by the owner or the owner's professional engineer describing a detailed
plan to prevent or lessen the effects of a failure of the dam or appurtenant
structures.
(23) Emergency repairs--Any repairs, considered to
be temporary in nature, necessary to preserve the integrity of the
dam and prevent a possible failure of the dam.
(24) Emergency spillway--An auxiliary spillway designed
to pass a large, but infrequent, volume of flood flow, with a crest
elevation higher than the principal spillway or normal operating level.
(25) Engineering inspection--Inspection performed by
a professional engineer, or under the supervision of a professional
engineer, to evaluate the condition, safety, and integrity of the
dam and appurtenant structures to determine if the dam and appurtenant
structures meet applicable rules and accepted engineering practices,
including a field inspection and review of records for design, construction,
and performance.
(26) Enlargement--Any change in, or addition to, an
existing dam or reservoir that raises, or may raise, the normal storage
capacity of the reservoir impounded by the dam.
(27) Existing dam--Any dam under construction or completed
as of the effective date of these rules.
(28) Fetch--The straight-line distance across a reservoir subject to wind forces.
(29) Hazard classification--A measure of the potential
for loss of life, property damage, or economic impact in the area
downstream of the dam in the event of a failure or malfunction of
the dam or appurtenant structures. The hazard classification does
not represent the physical condition of the dam.
(30) Height of dam--The difference in elevation between
the natural bed of the watercourse or the lowest point on the downstream
toe of the dam, whichever is lower, and the effective crest of the dam.
(31) Inundation map--A map delineating the area that
would be flooded by a particular flood event, or a dam failure.
(32) Loss of life--Human fatalities that would result
from a flood-induced or piping failure of the dam, without considering
evacuation or other emergency actions that could be taken.
(33) Main highways--Roads classified as a rural arterial
system by the Texas Department of Transportation, including interstate
highways, United States highways, and state highways.
(34) Maintenance--Those tasks that are generally recurring
and are necessary to keep the dam and appurtenant structures in a
sound condition, free from defect or damage that could hinder the
dam's functions as designed, including adjacent areas that also could
affect the function and operation of the dam.
(35) Maintenance inspection--Visual inspection of the
dam and appurtenant structures by the owner or owner's representative
to detect apparent signs of deterioration, other deficiencies, or
any other areas of concern.
(36) Maximum storage capacity--The volume, in acre-feet,
of the impoundment created by the dam at the effective crest of the
dam. For purposes of calculating maximum storage capacity for the
Inventory of Dams as described in §299.7 of this title (relating
to Inventory of Dams), only water that can be stored above natural
ground level (not in excavations in the reservoir) or that could be
released by a failure of the dam is considered in assessing the storage
volume. The maximum storage capacity may decrease over time due to
sedimentation or increase if the reservoir is dredged.
(37) Minimum freeboard--The difference in elevation
between the effective crest of the dam and the maximum water surface
elevation resulting from routing the design flood appropriate for the dam.
(38) Minor highways--Roads classified as a rural collector
road or rural local road by the Texas Department of Transportation,
including county roads and Farm-to-Market roads not used to provide
service to schools.
(39) Modification--Any structural alteration of a dam,
the spillways, the outlet works, or other appurtenant structures that
could influence or affect the integrity, safety, and operation of the dam.
(40) Normal storage capacity--The volume, in acre-feet,
of the impoundment created by the dam at the lowest uncontrolled spillway
crest elevation, or at the maximum elevation of the reservoir at the
normal (non-flooding) operating level.
(41) NAD83 conus datum--The North American Datum of
1983 is a reference system used to obtain the spherical coordinates
of a point on the earth's surface. The standard North American Datum
of 1983 must be used for all latitude and longitude measurements.
(42) NAVD88 datum--The North American Vertical Datum
of 1988 is a reference system used to obtain vertical measurements
on the earth's surface. The North American Vertical Datum of 1988
must be used for all vertical measurements recorded with a global
positioning system receiver.
(43) Outlet--A conduit or pipe controlled by a gate
or valve, or a siphon, that is used to release impounded water from
the reservoir.
(44) Owner--Any person who can be one or more of the following:
(A) holds legal possession or ownership of an interest in a dam;
(B) is the fee simple owner of the surface estate of
the tract of land on which the dam is located if actual ownership
of the dam is uncertain, unknown, or in dispute unless the person
can demonstrate by appropriate documentation, including a deed reservation,
invoice, bill of sale, or by other legally acceptable means that the
dam is owned by another person or persons;
(C) is a sponsoring local organization that has an
agreement with the Natural Resources Conservation Service for a dam
constructed under the authorization of the Flood Control Act of 1944
(as amended), Public Law 78-534, the Watershed Protection and Flood
Prevention Act, 1954 (as amended), Public Law 83-566, the pilot watershed
program under the Flood Prevention of the Department of Agriculture
Appropriation Act of 1954, Public Law 156-67, or Subtitle H of Title
XV of the Agriculture and Flood Act of 1981, the Resource Conservation
and Development Program; or
(D) has a lease, easement, or right-of-way to construct,
operate, or maintain a dam.
(45) Piping--The progressive removal of soil particles
from a dam by percolating water, leading to development of channels
or flow paths.
(46) Principal spillway--The primary or initial spillway
engaged during a rainfall runoff event that is designed to pass normal flows.
(47) Probable maximum flood (PMF)--The flood magnitude
that may be expected from the most critical combination of meteorologic
and hydrologic conditions that are reasonably possible for a given
watershed.
(48) Probable maximum precipitation (PMP)--The theoretically
greatest depth of precipitation for a given duration that is physically
possible over a given size storm area at a particular geographical
location at a certain time of the year.
(49) Professional engineer--An individual licensed
by the Texas Board of Professional Engineers to engage in the practice
of engineering in the state of Texas, with experience in the investigation,
design, construction, repair, and maintenance of dams.
(50) Proposed dam--Any dam not yet under construction.
(51) Reconstruction--Removal and replacement of an
existing dam or appurtenant structures.
(52) Rehabilitation--The completion of all work necessary
to extend the service life of a dam and meet the safety and performance
standards of this chapter.
(53) Removal--The complete elimination of a dam, the
appurtenant structures, and the reservoir to the extent that no water
can be impounded by the dam or reservoir and the approximate original
topography of the dam and reservoir area is restored.
(54) Repairs--Any work done on a dam that may affect
the integrity, safety, and operation of the dam, including, but not
limited to:
(A) excavation into the embankment fill or foundation of a dam; or
(B) removal or replacement of major structural components
of a dam or appurtenant structures.
(55) Reservoir--A body of water impounded by a dam.
(56) Safe manner--Operating and maintaining a dam in
sound condition, free from defect or damage that could hinder the
dam's functions as designed.
(57) Seal--To affix a professional engineer's seal
to each sheet of construction plans or to an engineering report or
required document.
(58) Secondary highways--Roads classified as a rural
major collector road by the Texas Department of Transportation, including
Farm-to-Market roads used to provide service to schools.
(59) Secure location--A building that is locked and
accessible to the owner and owner's representative.
(60) Spillway--An appurtenant structure that conducts
outflow from a reservoir.
(61) Sponsoring local organization--any political subdivision
of the state, or other entity, with the authority to carry out, maintain,
or operate work of improvement installed with the assistance of the
federal government.
(62) Stability analysis--The analytical procedure for
determining the most critical factor of safety for a slope.
(63) Substantially complete--A dam under construction
that is complete except for minor correction of items identified in
the final construction inspection and that can be operated in a safe
manner to the dam's full functional capability.
§299.3.General.
(a) As part of an evaluation to determine if the dam
and appurtenant structures constitute a significant threat to human
life or property, the executive director may require the owner to
obtain the services of an independent team of professional engineers
or other dam experts, at the owner's expense, to determine the adequacy
of the design, construction, or operation of the dam if safety considerations
warrant an independent review. The requirements for use of the independent
team of professional engineers or other dam experts will be included
in a guideline developed by the executive director. The executive
director shall submit the requirement in writing to the owner and
shall provide a list of engineers and other dam experts. The owner
shall submit the qualifications and size of the team to the executive
director for any comments prior to beginning the independent review.
(b) When an owner submits an application for a water
rights permit to either construct a dam, reconstruct, modify, enlarge,
rehabilitate, alter, or repair an existing dam, or authorize an existing
dam without making any changes to the dam, the owner shall submit
the following:
(1) a conceptual design of the construction for a proposed
dam and appurtenant structures, or proposed reconstruction, modification,
enlargement, rehabilitation, alteration, or repair of an existing dam;
(2) the geotechnical, hydrologic, and hydraulic reports
for the proposed site, if the reports have been completed; and
(3) other pertinent information on an existing dam
using a form provided by the executive director.
(4) The executive director shall provide a technical
review of these documents as described in §281.19 of this title
(relating to Technical Review).
§299.4.Professional Engineer.
(a) For all dams subject to the executive director's
review under this chapter, a professional engineer shall:
(1) prepare all plans and specifications;
(2) prepare evaluations, analyses, or reports required by this chapter;
(3) observe the progress and the quality of the construction
of proposed dams or reconstruction, modification, enlargement, rehabilitation,
alteration, repair, or removal of existing dams to determine, in general,
if the construction is proceeding according to the approved construction
plans and specifications. It is understood that the professional engineer
is not responsible for the contractor's means, methods, techniques,
sequences, or procedures of construction selected by the contractor,
or the safety precautions and programs incident to the work of the
contractor; and
(4) either perform or supervise engineering inspections,
as defined in §299.2 of this title (relating to Definitions),
of high- and significant-hazard dams and large, low-hazard dams, as
defined in §299.13 and §299.14 of this title (relating to
Size Classification Criteria; and Hazard Classification Criteria;
respectively).
(b) The executive director may waive these requirements
based on §299.5 of this title (relating to Exception).
§299.5.Exception.
(a) The executive director may grant an exception to
any or all of paragraphs (1) - (9) of this subsection if the executive
director determines that the physical conditions involved or consequences
of potential failure, when evaluated using accepted engineering practices,
make the requirements unnecessary:
(1) §299.4 of this title (relating to Professional Engineer);
(2) §299.22 of this title (relating to Review
and Approval of Construction Plans and Specifications);
(3) §299.23 of this title (relating to Maintenance
of Construction Records);
(4) §299.24 of this title (relating to Construction Progress Reports);
(5) §299.25 of this title (relating to Construction Inspection);
(6) §299.26 of this title (relating to Construction Change Orders);
(7) §299.28 of this title (relating to Deliberate Impoundment);
(8) §299.30 of this title (relating to Record Drawings); and
(9) §299.31 of this title (relating to Permanent Reference Mark).
(b) The owner shall submit the request for an exception
in writing to the executive director. The request may include:
(1) cost-benefit analyses;
(2) detailed engineering studies prepared by a professional engineer; and
(3) any other pertinent information.
(c) The executive director's decision to approve or
deny the request for an exception must be in writing and specify the
extent of the exception granted or denied and the executive director's
reasons for granting or denying the exception.
§299.6.Changing Ownership of Dams.
When a change in ownership of a dam occurs, each new owner
shall notify the executive director in writing within 90 days following
the transaction and provide:
(1) the name, address, and telephone number of the new owner(s);
(2) the date of ownership transfer;
(3) the name and telephone number of the individual
who will be responsible for operation and maintenance of the dam; and
(4) a certified copy or photocopy of instruments recorded
in the office of the county clerk showing transfer of the dam to a
new owner.
§299.7.Inventory of Dams.
The executive director shall maintain an inventory of dams
that includes information on:
(1) ownership;
(2) physical dimensions of the dam;
(3) hazard classification;
(4) normal and maximum storage capacity;
(5) use of reservoir, including the water rights permit, if applicable;
(6) inspection date;
(7) location; and
(8) condition of the dam.
This agency hereby certifies that the proposal
has been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803562
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
STATUTORY AUTHORITY
These new sections are proposed under the authority granted to
the commission in Texas Water Code (TWC), §5.012, which provides
that the commission is the agency responsible for implementing the
constitution and laws of the state relating to conservation of natural
resources and protection of the environment; §5.013, which establishes
the commission's authority over various statutory programs, such as
dam safety; §5.103 and §5.105, which establish the commission's
general authority to adopt rules; §12.052, which establishes
the commission's authority to promulgate rules for the safe construction,
maintenance, repair, and removal of dams located in this state; and §7.002,
which authorizes the commission to enforce provisions of the TWC.
These proposed new sections implement TWC, §§5.103, 5.105, and 12.052.
§299.11.General.
The executive director shall evaluate the hydrologic, hydraulic,
and structural adequacy of the dam in determining whether a proposed
or existing dam is considered a deficient dam.
(1) The executive director shall evaluate the hydrologic
and hydraulic adequacy of the dam and spillways using the criteria
in the most current version, at the time of the evaluation, of the
agency's Hydrologic and Hydraulic Guidelines for Dams in Texas.
(2) The executive director may also take into consideration
the condition of the dam, including the possibility that the dam might
be endangered by:
(A) overtopping;
(B) seepage;
(C) piping;
(D) settlement;
(E) erosion;
(F) cracking;
(G) sinkholes;
(H) earth movement;
(I) uplift;
(J) overturning;
(K) failure of gates or operation of gates;
(L) failure of spillways;
(M) failure of conduits; or
(N) other conditions, as appropriate.
§299.12.Classification of Dams.
(a) The executive director shall classify all proposed
and existing dams based on size (small, intermediate, or large) and
downstream hazard (low, significant, or high) and not on the physical
condition of the dam.
(b) The executive director may reclassify the hazard
classification of a dam at any time based on:
(1) an inspection and downstream hazard evaluation
by the executive director;
(2) a report of an inspection and downstream hazard
evaluation by the owner's professional engineer;
(3) a breach analysis performed by either the executive
director or the owner's professional engineer as described in §299.15(a)(4)(A)(i)
of this title (relating to Hydrologic and Hydraulic Criteria for Dams); or
(4) a review of current aerial photography and topographic
maps, along with information obtained in the field.
§299.13.Size Classification Criteria.
The executive director shall classify dams for size based on
the larger of the height of the dam or the maximum storage capacity.
§299.14.Hazard Classification Criteria.
The executive director shall classify dams for hazard based
on either potential loss of human life or property damage, in the
event of failure or malfunction of the dam or appurtenant structures,
within affected developments, that are existing at the time of the
classification. The classification may include use of a breach analysis,
as defined in §299.15(a)(4)(A)(i) of this title (relating to
Hydrologic and Hydraulic Criteria for Dams). The classification must
be according to the following.
(1) Low. A dam in the low-hazard potential category has:
(A) no loss of human life expected (no permanent inhabitable
structures in the breach inundation area downstream of the dam); and
(B) minimal economic loss (located primarily in rural
areas where failure may damage occasional farm buildings, limited
agricultural improvements, and minor highways as defined in §299.2(38)
of this title (relating to Definitions)).
(2) Significant. A dam in the significant-hazard potential category has:
(A) loss of human life possible (one to six lives or
one or two inhabitable structures in the breach inundation area downstream
of the dam); or
(B) appreciable economic loss, located primarily in
rural areas where failure may cause:
(i) damage to isolated homes;
(ii) damage to secondary highways as defined in §299.2(58) of this title;
(iii) damage to minor railroads; or
(iv) interruption of service or use of important public
utilities, including the design purpose of the utility.
(3) High. A dam in the high-hazard potential category has:
(A) loss of life expected (seven or more lives or three
or more inhabitable structures in the breach inundation area downstream
of the dam); or
(B) excessive economic loss, located primarily in or
near urban areas where failure would be expected to cause extensive
damage to:
(i) public facilities;
(ii) agricultural, industrial, or commercial facilities;
(iii) important public utilities, including the design
purpose of the utility;
(iv) main highways as defined in §299.2(33) of this title; or
(v) railroads used as a major transportation system.
§299.15.Hydrologic and Hydraulic Criteria for Dams.
(a) Hydrologic criteria.
(1) Minimum hydrologic criteria for proposed dams.
The following minimum hydrologic criteria includes those proposed
dams to be constructed according to Texas Water Code, §11.142.
(A) A proposed dam design must meet the minimum design
flood hydrograph criteria.
Figure: 30 TAC §299.15(a)(1)(A)
(B) The minimum design flood hydrograph must be based
on the size and hazard classification of a proposed dam at the time
of the design and calculated using the criteria in the most current
version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines of Dams in Texas.
(C) Proposed dams and spillways or dams and spillway
to be reconstructed, modified, enlarged, rehabilitated, or altered
using hydrologic procedures of the Natural Resources Conservation
Service will be acceptable, provided that the procedures are shown
to be equal to or more conservative than the procedures provided in
the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas.
(2) Exemptions to minimum hydrologic criteria for proposed
dams. Any dam designed to withstand overtopping without failure of
the dam, including the foundation and abutments, as demonstrated by
studies prepared by the owner's professional engineer will be exempt
from the minimum hydrologic criteria.
(3) Minimum hydrologic criteria for existing dams.
The following criteria applies to dams that existed before the effective
date of this subchapter.
(A) An existing dam that was required to meet 100%
of the probable maximum flood (PMF) before the effective date of these
rules and is shown by an evaluation by a professional engineer to
meet 75% or more of the PMF will not be required to be upgraded to
meet minimum hydrologic criteria in paragraph (1)(A) of this subsection
and the dam will be considered adequate to meet the minimum hydrologic
criteria, provided the owner:
(i) has an emergency action plan that meets the requirements
in §299.61 of this title (relating to Emergency Action Plans);
(ii) has an operation and maintenance program for the
dam as described in §299.43 of this title (relating to Operation
and Maintenance);
(iii) has an inspection program that has been implemented
as described in §299.42 of this title (relating to Inspections); and
(iv) submits an annual report to the executive director
documenting compliance with the requirements in clauses (ii) and (iii)
of this subparagraph, beginning 12 months after the effective date
of this section.
(B) A dam that was required to meet the minimum hydrologic
criteria before the effective date of these rules, but is shown by
an evaluation by a professional engineer to meet the minimum hydrologic
criteria in paragraph (1)(A) of this subsection, will not be required
to be upgraded and the dam will be considered adequate to meet the
minimum hydrologic criteria.
(C) An existing dam that does not meet the minimum
hydrologic criteria in paragraph (1)(A) of this subsection or the
size or hazard classification has been raised and the dam does not
meet the minimum hydrologic criteria in paragraph (1)(A) or this subsection
for the new size or hazard classification may require that the owner
submit to the executive director any of the following, prepared by
a professional engineer:
(i) final construction plans and specifications as
described in §299.22 of this title (relating to Review and Approval
of Construction Plans and Specifications) for modifying, enlarging,
or altering the dam or spillways to meet the minimum hydrologic criteria
as described in paragraph (1)(A) of this subsection;
(ii) an analysis or other option to request a reduction
in the minimum hydrologic criteria as described in paragraph (4) of
this subsection; or
(iii) a plan for alternatives to upgrading as described
in §299.17 of this title (relating to Alternatives to Upgrading Dams).
(D) An existing dam that meets the requirements of
subparagraph A of this paragraph and is required to be modified due
to structural deficiencies shall be required for the owner to submit
to the executive director final construction plans and specifications
for the structural modifications as described in §299.22 of this
title. The dam will not be required to be upgraded to meet the minimum
design criteria in paragraph (1)(A) of this subsection.
(4) Reduction of minimum hydrologic criteria. The minimum
hydrologic criteria may be reduced as follows.
(A) The owner may request that the executive director
reduce the minimum hydrologic criteria if the owner submits:
(i) dam breach analysis, prepared by a professional
engineer and using the normal storage capacity non-flood event, the
barely overtopping flood event, and the PMF event, if applicable,
that demonstrate existing downstream improvements would not be adversely
affected, which is defined as the downstream flooding differentials
being less than or equal to one foot between breach and non-breach
simulations in the affected area;
(ii) one or more technical options included in the
most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines of Dams in Texas
, demonstrating that existing downstream improvements
would not be adversely affected;
(iii) documentation of the purchase, or an easement
for, the property downstream of the dam that would be impacted by
a dam failure and showing that it has been dedicated to non-residential
and non-commercial use; or
(iv) documentation that the property downstream has
been dedicated by the property owner to non-residential and non-commercial use.
(B) The executive director shall evaluate the owner's
request for reduction in the minimum hydrologic criteria to determine
if the request is appropriate. If the executive director agrees with
the analysis, the executive director shall approve the request in writing.
(C) If the executive director does not agree with the
owner's request for reduction in the minimum hydrologic criteria,
the executive director shall deny the request in writing.
(b) Hydraulic criteria for proposed dams or dams proposed
to be reconstructed, modified, enlarged, rehabilitated, or altered.
(1) The owner shall have a professional engineer evaluate
the hydraulic adequacy of the dam and spillways using the guidelines
in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines of Dams in Texas.
(2) The owner shall have a professional engineer address
the stability of the spillways to determine if the spillways will
adequately meet the minimum design storm without being significantly damaged.
(3) The owner shall have a professional engineer determine
a minimum freeboard for a proposed large size dam as defined in §299.13
of this title (relating to Size Classification Criteria) as outlined
in the most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas.
(c) Hydraulic criteria for existing dams. If it becomes
necessary for an owner of an existing dam to reevaluate the hydraulic
adequacy of the dam and spillways, the owner shall have a professional
engineer evaluate the hydraulic adequacy of the dam and spillways
using the guidelines in the most current version, at the time of the
analysis, of the agency's Hydrologic and
Hydraulic Guidelines of Dams in Texas.
§299.16.Structural Evaluation of Dams.
(a) The owner shall have a professional engineer submit
a geotechnical, geological, and structural evaluation in a report
to the executive director with the final construction plans and specifications
as described in §299.22 of this title (relating to Review and
Approval of Construction Plans and Specifications) to support the
design of a proposed dam or a dam that is proposed to be reconstructed,
or structurally modified, enlarged, rehabilitated, or altered. The
report must include, as applicable:
(1) details of the geology of the project site and vicinity;
(2) location and logs of test borings, pits, and shafts;
(3) results of field and laboratory tests on structural
and foundation materials;
(4) seepage studies;
(5) stability analyses of embankments, spillways, retaining
walls, and inlet structures, as described in subsection (b) of this
section; and
(6) recommendations concerning:
(A) embankment slopes, crest width, and berms;
(B) core trench size and depths;
(C) moisture-density and strength requirements;
(D) soil dispersion requirements;
(E) minimum compressive strength for concrete;
(F) construction sequence procedures and techniques
for excavations and embankments;
(G) types of compaction equipment; and
(H) seepage control requirements.
(b) The owner shall have a professional engineer develop
a stability analysis as outlined in the most current version, at the
time of the analysis, of the agency's Design
and Construction Guidelines for Dams in Texas to support the
design of proposed large- and intermediate-size dams, as defined in §299.13
of this title (relating to Size Classification Criteria), and large-
and intermediate-size dams that are proposed to be reconstructed or
structurally modified, enlarged, rehabilitated, or altered. The analysis
must be submitted to the executive director with the final construction
plans and specifications as described in §299.22 of this title.
(c) The executive director may require the owner of
an existing dam to have a professional engineer perform a geotechnical
and structural evaluation or a stability analysis and submit a report,
as described in subsections (a) and (b) of this section, following
an inspection, as described in §299.42 of this title (relating
to Inspections), if the executive director determines that the dam
was found to be deficient and the integrity of the dam was threatened.
If the owner has a professional engineer prepare a report, the owner
shall submit the professional engineer's report to the executive director
for review upon completion of the report.
(d) When a person proposes one of the following activities
near the owner's dam, the owner or the executive director may request
that the person have a professional engineer perform an evaluation
to determine if the integrity of the dam would be compromised. If
the person has a report prepared by a professional engineer, the person
shall submit the evaluation report to the executive director and the
owner for review and approval before any work is performed for a proposal to:
(1) dredge the reservoir within 200 feet of the dam;
(2) install a utility line or pipeline in the dam or
in the spillways that requires significant excavation in the dam or spillways;
(3) construct a road across the dam or spillways or within 200 feet of the dam;
(4) drill oil or gas wells or perform oil or gas exploration
within 200 feet of the dam and spillways; or
(5) blast within 1/2 mile of the dam.
§299.17.Alternatives to Upgrading Dams.
(a) An owner may elect to implement alternative methods,
instead of upgrading the dam using structural methods, to meet minimum
hydrologic criteria by submitting to the executive director:
(1) a plan for meeting the requirements in §299.15(a)(3)
of this title (relating to Hydrologic and Hydraulic Criteria for Dams);
(2) a plan for meeting the requirements in §299.15(a)(4) of this title;
(3) a plan for removing the dam, as described in §299.51
of this title (relating to Removal or Breach of Dams);
(4) a plan for lowering the reservoir level to a level
that will allow it to meet the appropriate minimum hydrologic criteria; or
(5) a plan using a combination of structural and non-structural
methods as proposed by the owner's professional engineer.
(b) The executive director shall review the owner's
proposal and respond as described in §299.22(e) of this title
(relating to Review and Approval of Construction Plans and Specifications).
This agency hereby certifies that the proposal has
been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803564
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
STATUTORY AUTHORITY
These new sections are proposed under the authority granted to
the commission in Texas Water Code (TWC), §5.012, which provides
that the commission is the agency responsible for implementing the
constitution and laws of the state relating to conservation of natural
resources and protection of the environment; §5.013, which establishes
the commission's authority over various statutory programs, such as
dam safety; §5.103 and §5.105, which establish the commission's
general authority to adopt rules; §12.052, which establishes
the commission's authority to promulgate rules for the safe construction,
maintenance, repair, and removal of dams located in this state; and §7.002,
which authorizes the commission to enforce provisions of the TWC.
These proposed new sections implement TWC, §§5.103, 5.105,
and 12.052.
§299.21.Applicability.
(a) This subchapter applies only to construction requirements,
including submittal, review, and approval of engineering plans and
specifications, inspections, reports, and records, for the construction
of a proposed dam or the reconstruction, modification, enlargement,
rehabilitation, alteration, or repair of an existing dam:
(1) requiring a water rights permit authorization;
(2) requiring an Edwards Aquifer protection plan;
(3) originally designed and constructed with the assistance
and written concurrence of the Natural Resources Conservation Service
under authorization of the Flood Control Act of 1944 (as amended),
Public Law 78-534, the Watershed Protection and Flood Prevention Act
of 1954 (as amended), Public Law 83-566, the pilot watershed program
under the Flood Prevention of the Department of Agriculture Appropriation
Act of 1954, Public Law 156-67, or Subtitle H of Title XV of the Agriculture
and Flood Act of 1981, the Resource Conservation and Development Program,
but being proposed to be reconstructed, modified, enlarged, rehabilitated,
altered, or repaired without the assistance and written concurrence
of the Natural Resources Conservation Service;
(4) used for temporary detention purposes and impounding
a maximum storage capacity of 200 acre-feet or more; or
(5) that is small and classified as either significant-
or high-hazard, as defined in §299.13 and §299.14 of this
title (relating to Size Classification Criteria; and Hazard Classification
Criteria; respectively), and exempt from a water rights permit under
Texas Water Code, §11.142.
(b) This subchapter does not apply to:
(1) dams for which an exception is approved according
to §299.5 of this title (relating to Exception) to the extent
for which the exemption is granted;
(2) proposed dams designed and constructed, or existing
dams designed and modified, rehabilitated, or repaired, with the assistance
and written concurrence of the Natural Resources Conservation Service
under authorization of the Flood Control Act of 1944 (as amended),
Public Law 78-534, the Watershed Protection and Flood Prevention Act
of 1954 (as amended), Public Law 83-566, the pilot watershed program
under the Flood Prevention of the Department of Agriculture Appropriation
Act of 1954, Public Law 156-67, or Subtitle H of Title XV of the Agriculture
and Flood Act of 1981, the Resource Conservation and Development Program;
(3) proposed dams designed and constructed, or existing
dams designed and modified, rehabilitated, or repaired for mining
purposes and approved and inspected by the Mine Safety and Health
Administration;
(4) small, low-hazard dams, as defined in §299.13
and §299.14 of this title, exempted from a water rights permit
under Texas Water Code, §11.142; and
(5) maintenance or emergency repairs, as defined in §299.2
of this title (relating to Definitions).
§299.22.Review and Approval of Construction Plans and Specifications.
(a) General.
(1) The owner shall submit final construction plans
and specifications, which are sealed, signed, and dated by a professional
engineer, to the executive director for review and approval before
commencing construction of a proposed dam or the reconstruction, modification,
enlargement, rehabilitation, alteration, or repair of an existing
dam. Emergency repairs are defined in §299.2(23) of this title
(relating to Definitions) and §299.45 of this title (relating
to Emergency Repairs).
(2) The executive director shall not issue approval
of final construction plans and specifications for construction of
a proposed dam or the reconstruction, modification, enlargement, rehabilitation,
alteration, or repair of an existing dam until a water rights permit
or an Edwards Aquifer protection plan, if required, is issued.
(3) The executive director shall not issue approval
of final construction plans and specifications for construction of
a proposed dam or the reconstruction, modification, enlargement, rehabilitation,
alteration, or repair of an existing dam unless the plans and specifications
include language, or design criteria, that requires the proposed contractor
to develop a Storm Water Pollution Prevention Plan and submit a Notice
of Intent (NOI) for coverage under the State of Texas Construction
General Permit (TXR150000), if applicable.
(4) The owner shall not allow construction of a proposed
dam or the reconstruction, modification, enlargement, rehabilitation,
alteration, or repair of an existing dam to be commenced before the
executive director's review of the final construction plans, specifications,
and other engineering reports and the owner receives written approval
of the final construction plans and specifications. The owner shall
provide a copy of the executive director's written approval to the
contractor before commencing construction.
(5) Construction of a proposed dam or the reconstruction,
modification, enlargement, rehabilitation, alteration, or repair of
an existing dam shall be performed according to the final construction
plans and specifications approved by the executive director unless
construction change orders have been approved as indicated in §299.26
of this title (relating to Construction Change Orders).
(b) Construction plans.
(1) Construction plans for proposed dams must be 22
inches by 34 inches in size. The plans may be reduced to 11 inches
by 17 inches in size if all details are clearly legible and an accurate
scale is included. A scale must be included on all sheets of the construction
plans. The plans must include the following, as applicable:
(A) a vicinity map that shows the location of the proposed
dam and appurtenant structures with respect to:
(i) boundaries of political subdivisions;
(ii) streams;
(iii) highways;
(iv) railroads;
(v) pipelines;
(vi) transmission lines; and
(vii) utilities;
(B) a topographic map of the dam site with:
(i) contour intervals not to exceed five feet;
(ii) latitude and longitude (in decimal degrees to
six decimal places) of the midpoint of the dam using the North American
Vertical Datum of 1988 conus datum; and
(iii) a superimposed plan of the dam showing the locations of any:
(I) spillways;
(II) outlet conduit;
(III) borings and test pits;
(IV) possible borrow areas; and
(V) other structures.
(C) a profile of the dam site taken on the long axis of the dam showing:
(i) the location of the outlet conduit and each spillway;
(ii) the proposed bottom of the core trench; and
(iii) elevations of all features.
(D) a profile of each spillway along its long axis;
(E) a log of all borings showing the classification
of materials encountered below the surface, if not provided in a separate
geotechnical report;
(F) a cross section of the dam at maximum section showing
complete details and dimensions;
(G) detailed sections of outlet conduits, control works,
and spillways with a sufficient number and detail to delineate all
of these features;
(H) the proposed location of all permanent instrumentation,
pressure cells, settlement plates, piezometers, inclinometers, slope
indicator casings, data acquisition systems, or other devices;
(I) the requirements, or design criteria, for the proposed
contractor to develop a Storm Water Pollution Prevention Plan and
submit a NOI, if applicable, or authorization under TXR150000; and
(J) other design standards as described in the most
current version, at the time of the design, of the agency's Design and Construction Guidelines for Dams in Texas.
(2) Construction plans for the reconstruction, modification,
enlargement, rehabilitation, alteration, or repair of existing dams
must be 22 inches by 34 inches in size. The plans may be reduced to
11 inches by 17 inches in size if all details are clearly legible
and an accurate scale is included. A scale must be included on all
sheets of the construction plans. The plans must include the following,
as applicable:
(A) a vicinity map that shows the location of the dam
and spillways with respect to:
(i) boundaries of political subdivisions;
(ii) streams;
(iii) highways;
(iv) railroads;
(v) pipelines;
(vi) transmission lines; and
(vii) utilities.
(B) detailed sections of the dam, spillways, outlet
conduit, or control works being enlarged, altered, or repaired with
sufficient detail to delineate the work to be performed;
(C) a log of all borings, if necessary, showing the
classification of materials encountered below the surface, if not
provided in a separate geotechnical report;
(D) the requirements, or design criteria, for the proposed
contractor to develop a Storm Water Pollution Prevention Plan and
submit a NOI, if applicable or authorization under TXR150000; and
(E) other design criteria as described in the most
current version, at the time of the design, of the agency's Design and Construction Guidelines for Dams in Texas.
(c) Specifications. The specifications must include the following:
(1) the requirements for the various types of materials
to be used in the construction or reconstruction, modification, enlargement,
rehabilitation, alteration, or repair of the dam, spillways, outlet
conduits, and control works;
(2) a provision that plans and specifications will
not be substantially changed without either written approval of the
executive director before the work is started, or notification of
the changes as defined in §299.26 of this title;
(3) a requirement that the proposed contractor develop
and implement a Storm Water Pollution Prevention Plan, if applicable,
and submit an NOI for authorization under TXR150000; and
(4) other design specifications as described in the
most current version, at the time of the design, of the agency's Design and Construction Guidelines for Dams in Texas.
(d) Engineering reports and plans.
(1) Engineering reports that may be required by the
executive director for review include:
(A) a geotechnical, geological, and structural evaluation
report that includes the information described in §299.16 of
this title (relating to Structural Evaluation of Dams);
(B) a stability analysis for proposed large- and intermediate-size
dams as defined in §299.13 of this title (relating to Size Classification
Criteria), and large- and intermediate-size dams that are proposed
to be reconstructed or structurally modified, enlarged, rehabilitated,
or altered, as described in §299.16 of this title;
(C) a hydrologic and hydraulic report for proposed
dams and dams that are to be reconstructed, modified, enlarged, rehabilitated,
altered, or repaired, that includes the information described in the
most current version, at the time of the analysis, of the agency's Hydrologic and Hydraulic Guidelines for Dams in Texas;
(D) a report on proposed instrumentation for proposed
large dams and existing large dams, as defined in §299.13 of
this title, that are to be reconstructed, modified, enlarged, rehabilitated,
altered, or repaired. This report must include:
(i) types and locations of proposed instrumentation;
(ii) depths of instrumentation; and
(iii) frequency and duration of data collection; or
(E) any reports prepared for addressing site-specific
conditions and recommendations.
(2) Engineering plans that may be required by the executive
director for review include:
(A) a quality control and assurance plan for all proposed
dams. This plan must include:
(i) designation and qualifications of the on-site inspector(s);
(ii) designation of a testing laboratory;
(iii) types and frequency of tests to be conducted; and
(iv) a construction schedule.
(B) a plan for closure of any proposed dam that requires
a closure section. This plan must include:
(i) the amount of construction that would need to be
completed before closure would start;
(ii) the sequence to be followed during closure; and
(iii) the estimated time to complete closure.
(C) a plan for addressing possible emergencies that
threaten the integrity of the dam for all proposed high- and significant-hazard
dams during construction. This plan must include:
(i) a flow chart for notification of emergency management
officials and the downstream public;
(ii) identification of possible emergencies that could
occur during construction and potential consequences;
(iii) technical requirements for addressing any possible emergencies; and
(iv) responsibilities of all parties.
(e) Review and approval process.
(1) The executive director shall review the final construction
plans, specifications, and engineering reports and plans according
to the most current version, at the time of the design, of the agency's Design and Construction Guidelines for Dams in Texas.
(2) If the final construction plans and specifications
meet the requirements of this chapter and accepted engineering practices,
the executive director shall issue written approval to the owner unless
the plans and specifications are for a proposed dam and have been
submitted as part of the application for a water rights permit or
for an Edwards Aquifer protection plan.
(A) If the final construction plans and specifications
are for a proposed dam and have been submitted as part of the application
for a water rights permit, the executive director shall advise the
owner that the plans and specifications meet the requirements of this
chapter and accepted engineering practices. However, the executive
director shall not issue written approval of the final construction
plans and specifications until the water rights permit is issued and
a time limitation section, in compliance with Texas Water Code, Chapter
11, has been added to the water rights permit requiring construction
of a proposed dam or the reconstruction, modification, enlargement,
rehabilitation, alteration, or repair of an existing dam to be started
and completed within specified time frames.
(B) If the final construction plans and specifications
are for a proposed dam and have been submitted as part of the application
for an Edwards Aquifer protection plan, the executive director shall
not issue written approval of the final construction plans and specifications
until the Edwards Aquifer protection plan is issued by the appropriate
regional office.
(3) If the final construction plans and specifications
do not meet the requirements of this chapter, the executive director
shall provide the owner written comments on the items needing revision.
(4) After receipt of the revised final construction
plans and specifications or an addendum to the plans and specifications,
the executive director shall review and issue written approval to
the owner if all requirements in this chapter and accepted engineering
practices have been met.
(5) If all requirements still have not been met, the
executive director shall either provide the owner written comments
on the items still needing revision or schedule a meeting with the
owner to discuss the items needing revision.
(6) Upon submission of the revised, and agreed on,
final construction plans and specifications or an addendum to the
plans and specifications, the executive director shall issue written
approval to the owner if applicable rules and accepted engineering
practices have been met.
(f) Time limitations on approval of final construction
plans and specifications.
(1) If construction of a proposed dam or the reconstruction,
modification, enlargement, rehabilitation, alteration, or repair of
an existing dam is not commenced within four years of the executive
director's approval of final construction plans and specifications,
the approval will be subject to reevaluation. If rules, regulations,
and accepted engineering practices or the downstream hazard classification
have changed during the four-year period, the approval may be considered
invalid regardless of any extension of time authorizations given according
to Chapter 295 of this title (relating to Water Rights, Procedural)
and Chapter 297 of this title (relating to Water Rights, Substantive).
(2) If the executive director determines that the approval
is invalid, the executive director shall notify the owner in writing
that new construction plans, specifications, and other engineering
reports must be submitted before the work may commence.
(3) The new construction plans and specifications must
meet the requirements of the rules and regulations in effect at the
time of the reevaluation.
§299.23.Maintenance of Construction Records.
(a) The owner shall maintain construction records during
construction of a proposed dam or the reconstruction, modification,
enlargement, rehabilitation, alteration, or repair of an existing
dam, which include:
(1) approved construction plans and specifications;
(2) approved construction change orders;
(3) construction test results as described in subsection (b) of this section;
(4) approval letters; and
(5) construction inspection reports and other engineering
reports that may be developed during construction.
(b) The owner shall furnish copies of the construction
test results for high- and significant-hazard dams to the executive
director for review at least once a month during the construction
period to document compliance with the approved plans and specifications
and the requirements in this chapter. The test results to be submitted
must include:
(1) soil moisture-density test results;
(2) soil dispersion test results; and
(3) concrete trial batch design test and compression test results.
(c) The owner shall also record:
(1) final bottom width and elevations of core and cutoff trenches;
(2) structural excavations;
(3) documentation of permanent sheet piles or bearing piles; and
(4) documentation of foundation grouting, de-watering
problems, or observations during the construction period of any instruments
installed to measure movements, stresses, and pore pressure.
(d) The owner shall maintain the construction records
as described in subsections (a) - (c) of this section in a secure
location at the construction site or at a location designated by the
owner that is immediately accessible to the owner until the completion
of construction.
(e) After completion of construction, the owner shall
transfer the construction records in subsections (a) - (c) of this
section to a permanent, secure location designated by the owner that
is immediately accessible to the owner as described in §299.46
of this title (relating to Records).
§299.24.Construction Progress Reports.
(a) The owner shall have a professional engineer provide
the following information to the executive director in writing within
ten working days after construction on the dam commences:
(1) the actual start date;
(2) the contractor's name and address; and
(3) the name and telephone number of the professional
engineer or inspector that will be on site during construction.
(b) The owner shall have a professional engineer submit
monthly reports of progress on high- and significant-hazard dams to
the executive director by the tenth of each month during construction.
The report must include:
(1) the work accomplished during the month;
(2) the percent of the contract time used;
(3) the percentage of completion of the project on the date of the report;
(4) a description of problem areas encountered during construction;
(5) the dates of the reporting period; and
(6) any changes in the contact information.
§299.25.Construction Inspection.
(a) The owner shall have a professional engineer, or
a qualified inspector, provided the inspector is under the direct
supervision of the owner's professional engineer, conduct inspections
of the construction work to determine if the work is in compliance
with approved construction plans, specifications, and accepted engineering
practices.
(b) The executive director may make periodic inspections
of the construction to determine if the dam is in compliance with
approved plans and specifications. If the executive director's inspection
reveals that the dam is not being constructed according to the approved
construction plans and specifications, the executive director shall
notify the owner by telephone and in writing as outlined in the most
current version, at the time of the evaluation, of the agency's Design and Construction Guidelines for Dams in Texas
of the deficiency items or violations noted. The executive
director shall direct the owner to take the necessary action to bring
the project into compliance with the approved plans and specifications
within 30 days after being notified.
(c) The owner, at the owner's expense, shall submit
documentation of the work or tests performed or sufficient information
to enable the executive director to determine if conformity with approved
plans and specifications is accomplished.
§299.26.Construction Change Orders.
(a) The owner shall submit any proposed changes to
the approved construction plans and specifications to the executive
director for review and approval as a construction change order as
defined in §299.2(13) of this title (relating to Definitions).
The construction change order must be signed, sealed, and dated by
a professional engineer.
(b) The owner shall submit a construction change order
before work starts on the proposed changes, if possible. If there
is an emergency requiring immediate action, a construction change
order may be submitted after the work is performed. However, the owner
or the owner's professional engineer shall inform the executive director
by telephone or electronic mail of the action being taken as soon
as the situation allows, but no later than 24 hours after becoming
aware of the emergency or the need for a change order. If the time
needed for an approval of a change order will require that the construction
be halted, the work may be performed once the construction change
order is signed, sealed, and dated by the owner's professional engineer
and submitted for review. However, if the construction change order
is not approved, the owner shall be responsible for having any work
performed or modified to reflect the approved construction change
order, as needed.
(c) The executive director shall review a construction
change order according to the most current version, at the time of
the review, of the agency's Design and Construction
Guidelines for Dams in Texas.
(d) The executive director may request that the owner
submit a construction change order if, during construction, the executive
director finds that changes to the construction plans and specifications
are necessary to ensure the integrity of the dam.
(e) If the proposed construction change order would
result in a change in the permitted water rights, the owner shall
submit an application for an amendment of the water rights permit.
§299.27.Closure of Dam.
(a) The owner shall have a professional engineer submit
a written request to close the dam to the executive director for approval
as described in the most current version, at the time of the closure,
of the agency's Design and Construction Guidelines
for Dams in Texas before beginning closure of the dam. The
request must include:
(1) a copy of the owner's emergency action plan; and
(2) documentation that all parts of the proposed plan
for closure of the dam, as described in §299.22(d)(2)(B) of this
title (relating to Review and Approval of Construction Plans and Specifications),
have been met.
(b) The owner may begin closure of the dam after receiving
written approval from the executive director.
(c) The owner shall notify the executive director in
writing that the gate operation plan has been completed with the request
for closure of the dam as described in §299.32 of this title
(relating to Gate Operation Plan).
§299.28.Deliberate Impoundment.
(a) The owner of a dam and reservoir designed to impound
more than 1,000 acre-feet at normal storage capacity shall submit
a written request to the executive director to begin deliberate impoundment
of water, as defined in §299.2(17) of this title (relating to
Definitions). The owner shall submit a letter from the owner's professional
engineer stating that the dam is substantially complete.
(b) The owner may begin deliberate impoundment after
receiving written approval from the executive director.
§299.29.Notification of Completion.
(a) The owner shall have the professional engineer
of record submit written notification, which is sealed, signed, and
dated, to the executive director within 45 calendar days after the
work is substantially completed on the construction of a proposed
dam or the reconstruction, modification, enlargement, rehabilitation,
alteration, or repair of an existing dam. This notification may be
submitted separately from the record drawings.
(b) The owner's professional engineer shall state that,
to the best of the professional engineer's knowledge, the construction
or reconstruction, modification, enlargement, rehabilitation, alteration,
or repair was completed in substantial compliance with the approved
plans and specifications and any approved construction change orders.
(c) For projects excepted under §299.5 of this
title (relating to Exception), the owner shall notify the executive
director in writing that construction or reconstruction, modification,
enlargement, rehabilitation, alteration, or repair was completed.
§299.30.Record Drawings.
(a) Within six months after final completion of construction,
the owner shall submit to the executive director a complete set of
record drawings of the project for filing with the permanent records.
These record drawings must show all revisions made during construction,
including the permanent reference mark(s); be sealed, signed, and
dated by the professional engineer; and be identified as final record
drawings.
(b) If no changes were made during construction, the
owner may submit in writing a statement, which is signed, sealed,
and dated by the professional engineer, that no changes were made
during construction.
§299.31.Permanent Reference Mark.
The owner of a proposed dam or a dam proposed to be reconstructed,
modified, enlarged, rehabilitated, altered, or repaired shall have
the professional engineer of record establish one or more permanent
reference mark(s) for future use near, but separate from, the project.
Accurate location(s) and elevation(s) above mean sea level for the
permanent reference mark(s) must be shown on the record drawings.
Horizontal and vertical measurements recorded with a global positioning
system (GPS) receiver must be based on the North American Datum of
1983 and the North American Vertical Datum of 1988 horizontal and
vertical reference datums. Elevation data must be recorded using a
survey instrument or survey grade GPS receiver. Latitude and longitude
measurements must be provided in decimal degrees to six decimal places.
§299.32.Gate Operation Plan.
The owner shall have a professional engineer develop a gate
operation plan, as described in §299.44(c) of this title (relating
to Gate Operation Plan), for the owner of a proposed dam with a gated
principal spillway before completion of construction.
§299.33.Operation and Maintenance.
(a) The owner shall develop operation and maintenance
procedures as described in §299.43 of this title (relating to
Operation and Maintenance) for all proposed dams before completion
of construction.
(b) If applicable, the owner shall provide the date
that the owner will turn over the operation and maintenance of the
dam to a property owner association, homeowner association, or other
designated group and the new contact information in writing to the
executive director.
This agency hereby certifies that the proposal has
been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803566
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
STATUTORY AUTHORITY
These new sections are proposed under the authority granted to
the commission in Texas Water Code (TWC), §5.012, which provides
that the commission is the agency responsible for implementing the
constitution and laws of the state relating to conservation of natural
resources and protection of the environment; §5.013, which establishes
the commission's authority over various statutory programs, such as
dam safety; §5.103 and §5.105, which establish the commission's
general authority to adopt rules; §12.052, which establishes
the commission's authority to promulgate rules for the safe construction,
maintenance, repair, and removal of dams located in this state; and §7.002,
which authorizes the commission to enforce provisions of the TWC.
These proposed new sections implement TWC, §§5.103, 5.105, and 12.052.
§299.41.Owner's Responsibilities.
(a) The owner shall be responsible for operating and
maintaining the dam and appurtenant structures in a safe manner.
(b) The owner shall be responsible for addressing all
maintenance and safety concerns at the dam and appurtenant structures
identified during any inspections conducted by the executive director
or the owner.
(c) The owner shall ensure that necessary maintenance,
repairs, alterations, or modifications are initiated and completed
in a timely manner following any inspection.
(d) Nothing in this chapter or in orders issued by
the commission shall be construed to relieve an owner of a dam or
reservoir of the legal duties, obligations, or liabilities incident
to ownership or operation.
§299.42.Inspections.
(a) Periodic engineering inspections by the executive director.
(1) The executive director may enter any person's property
at any time for the purpose of inspecting any dam to determine if
the dam is being maintained in a safe manner.
(2) The executive director shall perform periodic engineering
inspections of dams based on hazard classification, as defined in §299.14
of this title (relating to Hazard Classification Criteria), on the
following frequency.
(A) High-hazard dams shall be inspected once every five years.
(B) Significant-hazard dams shall be inspected once every five years.
(C) Large dams, as defined in §299.13 of this
title (relating to Size Classification Criteria), in the low-hazard
classification shall be inspected once every five years.
(D) Small and intermediate dams, as defined in §299.13
of this title, in the low-hazard classification shall not be included
in the periodic inspection program. These dams may be inspected for
the purposes of:
(i) determining hazard classification;
(ii) assessing condition of the dam following an emergency
such as a flooding event;
(iii) assessing condition of the dam that could threaten
the integrity of the dam as a result of a request by the owner;
(iv) assessing the condition of the dam as a result
of a complaint; or
(v) assessing the condition of a dam as a result of
a request from someone other than the owner.
(3) The executive director's engineering inspection
may consist of:
(A) conducting a visual inspection and evaluation of
the condition of the dam and appurtenant structures, the downstream
area, and any other areas affected by the dam;
(B) taking measurements of elevations, dimensions,
slopes, and locations of the dam and appurtenant structures;
(C) taking photographs for documentation;
(D) conducting an evaluation of the hazard classification
to determine if the classification should be changed as a result of
the inspection;
(E) reviewing and evaluating the owner's operation,
maintenance, and inspection programs and all other records; and
(F) reviewing the owner's emergency action plan, including
the gate operation plan if applicable.
(4) The executive director shall prepare a written
inspection report that provides the findings from the inspection and
lists recommendations for actions to be taken to assist the owner
in maintaining the continued integrity, safety, and operation of the
dam. The executive director may require the owner to have the owner's
professional engineer perform hydrologic, hydraulic, or structural
evaluations of the dam as described in Subchapter B of this chapter
(relating to Design and Evaluation of Dams). The executive director
shall provide the owner with a copy of the written report, or letter,
as soon as practical after the inspection.
(5) The owner shall provide a written response to the
executive director, if requested, and include a plan of action with
time frames for addressing all of the executive director's recommendations
from the inspection.
(b) Inspections by the owner.
(1) The owner, or the owner's representative, shall
inspect the dam and appurtenant structures on a regular time frame
as part of the owner's operation and maintenance procedures, as defined
in §299.43 of this title (relating to Operation and Maintenance),
following significant rainfall events, and during emergency events
as described in §299.61 of this title (relating to Emergency
Action Plans). The owner or the owner's representative shall perform
maintenance inspections at least once a year.
(2) The owner shall notify the executive director by
telephone or electronic mail within 24 hours and in writing within
five days after becoming aware of any problems or damage that pose
a threat to the dam's safety, integrity, or operation.
(3) The owner shall submit a copy of all engineering
inspection reports prepared by the owner's professional engineer under
this section to the executive director for review within 45 calendar
days after receipt of the report from the professional engineer. The
report prepared by the owner's professional engineer must consist
of the inspection date, description of the items observed during the
inspection, the findings, and recommendations.
(4) The owner may elect to have an engineering inspection
by a professional engineer more frequently than described in subsection
(a)(2) of this section. The executive director may use the engineering
inspection report prepared for the owner by the professional engineer
in lieu of making a periodic inspection as described in subsection
(a)(2) of this section. A report prepared by a professional engineer
with the Federal Energy Regulatory Commission, Natural Resources Conservation
Service, Bureau of Reclamation, Corps of Engineers, or Mine Safety
and Health Administration may also be used in lieu of the periodic
inspection described in subsection (a)(2) of this section.
§299.43.Operation and Maintenance.
(a) The owners of all dams shall develop and implement
an operation and maintenance program. The owner may use the most current
version, at the time of the plan development, of the agency's Guidelines for Operation and Maintenance of Dams in Texas
, manual, a checklist, or some other procedure to demonstrate
implementation of the program. Operation and maintenance activities
that must be addressed include, but are not limited to:
(1) the schedules for both engineering and maintenance
inspections performed by the owner or the owner's professional engineer;
(2) any restrictions imposed by the original professional engineer's design;
(3) a list of maintenance items and a schedule for
addressing each item, including:
(A) replacing riprap;
(B) eliminating animal burrows;
(C) removing blockage from the principal spillway inlet
and outlet structures and removing obstructions from the emergency
spillways, including fences;
(D) lubricating, repairing, painting, and exercising
gates or valves, if in working condition, or if applicable;
(E) removing corrosion on gates and other metal appurtenant structures;
(F) sealing of cracks and joints in concrete;
(G) preventing or controlling erosion, including animal
and vehicular trails and wave action erosion;
(H) eliminating small trees (less than or equal to
four inches in diameter) and brush on the dam and all trees and brush
in the spillways and adjacent to concrete structures;
(I) maintaining adequate grass cover on earthen dams and spillways;
(J) maintaining proper function of foundation or toe drains; and
(K) correcting any other items that may impact the
dam or appurtenant structures; and
(4) if applicable, a plan for monitoring instrumentation
in the dam and appurtenant structures, to include:
(A) a list of all types of instruments, instrument number, and locations;
(B) schedules and procedures for reading and maintenance
of each instrument; and
(C) a list of critical readings for each instrument
and the process to follow if critical readings are measured.
(b) The owner shall document operation and maintenance
activities undertaken and shall provide the documentation to the executive
director for review as soon as possible upon request of the executive
director.
§299.44.Gate Operation Plan.
(a) The owners of all existing intermediate- and large-size
dams, as defined in §299.13 of this title (relating to Size Classification
Criteria), with gated principal spillways shall have their professional
engineer develop a gate operation plan within two years after the
effective date of the rules. The owner's professional engineer shall
notify the executive director in writing that the gate operation plan
has either been completed or a gate operation plan exists that meets
the requirement of this section.
(b) The gate operation plan must include:
(1) gate procedures for use during normal operating
conditions, flood events, and power failures; and
(2) a method for coordinating releases with owners
of other dams in the river basin, if applicable.
(c) The gate operation plan shall be considered an
appendix to the owner's emergency action plan. If the owner submits
a copy of the gate operation plan to the executive director, the executive
director shall file it with the owner's emergency action plan in the
agency's confidential, permanent records.
§299.45.Emergency Repairs.
(a) The owner shall undertake emergency repairs under
the supervision of a professional engineer and implement the emergency
action plan as soon as possible after the emergency is discovered
and evaluated. The owner may start emergency repairs without approval
from the executive director.
(b) The owner shall notify the executive director by
telephone or electronic mail of the action being taken as soon as
the emergency situation allows, but no more than 12 hours after the
emergency is discovered and evaluated.
(c) The owner shall have a professional engineer develop
plans for permanent repairs as soon as the emergency is over. The
owner shall have a professional engineer submit the plans for review
and approval, as described in §299.22 of this title (relating
to Review and Approval of Construction Plans and Specifications).
§299.46.Records.
(a) All owners shall maintain records, if available,
on the inspection, operation, and maintenance of their dams, including,
but not limited to:
(1) inspection checklists, reports, and correspondence;
(2) a log of all operation and maintenance activities undertaken;
(3) a gate operation plan, if applicable;
(4) a log of all repairs undertaken, including the
date of the repairs and the work performed;
(5) a log of instrumentation readings, if applicable;
(6) a log of all flood events and emergencies; and
(7) approved plans, record drawings, specifications,
approval letters, construction records, and other engineering and
design reports.
(b) Owners shall maintain legible or electronic copies
in a secure location, designated by the owner, that is immediately
accessible to the owner for the life of the dam.
(c) Owners shall provide copies of all records or access
to view the records to the executive director upon request.
(d) An owner shall provide all records to a new owner
when there is an ownership change.
This agency hereby certifies that the proposal has
been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803567
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
STATUTORY AUTHORITY
These new sections are proposed under the authority granted to
the commission in Texas Water Code (TWC), §5.012, which provides
that the commission is the agency responsible for implementing the
constitution and laws of the state relating to conservation of natural
resources and protection of the environment; §5.013, which establishes
the commission's authority over various statutory programs, such as
dam safety; §5.103 and §5.105, which establish the commission's
general authority to adopt rules; §12.052, which establishes
the commission's authority to promulgate rules for the safe construction,
maintenance, repair, and removal of dams located in this state; and §7.002,
which authorizes the commission to enforce provisions of the TWC.
These proposed new sections implement TWC, §§5.103, 5.105,
and 12.052.
§299.51.Removal or Breach of Dams.
(a) Owners proposing to remove or breach a dam, or
owners ordered to remove a deficient dam by the executive director,
the commission, or court action, shall submit final plans and specifications
to the executive director for review and approval before start of
work to remove or breach the dam.
(b) The owner shall have a professional engineer submit
to the executive director sealed, signed, and dated plans for removing
or breaching a dam as outlined in the most current version, at the
time of the design, of the agency's Dam Removal Guidelines.
(c) The owner may be required to address environmental
or social impacts as described in the most current version, at the
time of the design, of the agency's Dam Removal Guidelines
, which may require approval from other agencies
before construction can begin.
(d) The owner may be required to restore the property
to the condition of the site before the dam was constructed.
(e) If the plans for removal or breaching meet the
requirements in subsection (b) of this section, the executive director
shall issue written approval to the owner.
(f) The owner shall provide the executive director
within 45 days after completion of the breach or removal a notification
of completion. The executive director shall conduct an inspection
after receipt of notification of completion to verify that the removal
or breach has been completed in agreement with the plans.
§299.52.Abandonment of Dams.
If an owner abandons a dam at any time, the owner shall remove
or breach the dam, as described in §299.51 of this title (relating
to Removal or Breach of Dams), at the owner's expense, to eliminate
any hazard to life and property downstream.
This agency hereby certifies that the proposal has
been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803569
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
STATUTORY AUTHORITY
These new sections are proposed under the authority granted to
the commission in Texas Water Code (TWC), §5.012, which provides
that the commission is the agency responsible for implementing the
constitution and laws of the state relating to conservation of natural
resources and protection of the environment; §5.013, which establishes
the commission's authority over various statutory programs, such as
dam safety; §5.103 and §5.105, which establish the commission's
general authority to adopt rules; §12.052, which establishes
the commission's authority to promulgate rules for the safe construction,
maintenance, repair, and removal of dams located in this state; and §7.002,
which authorizes the commission to enforce provisions of the TWC.
These proposed new sections implement TWC, §§5.103, 5.105,
and 12.052.
§299.61.Emergency Action Plans.
(a) The owners of all high- and significant-hazard
dams, as defined in §299.13 of this title (relating to Size Classification
Criteria) and §299.14 of this title (relating to Hazard Classification
Criteria), shall prepare an emergency action plan to be followed by
the owner in the event or threat of a dam emergency.
(b) The owner of an existing high- or significant-hazard
dam shall submit the emergency action plan to the executive director
for review within two years after the effective date of the rules.
(c) The owner of a proposed high- or significant-hazard
dam shall submit the emergency action plan to the executive director
before either requesting closure of the dam or upon completion of
construction of the dam, if the dam does not require a closure section.
(d) The owner shall prepare the emergency action plan
using guidelines provided by the executive director or using a format
approved by the executive director before the plan is prepared. If
an owner owns more than one dam, the owner shall prepare a plan, with
timelines, for preparing emergency action plans based on priority
determined by hazard and submit the plan to the executive director
for review.
(e) The executive director shall review the emergency
action plan and provide any comments in writing to the owner.
(f) The executive director shall file the emergency
action plan in the agency's confidential, permanent records.
(g) The owner shall review the emergency action plan
annually, update the emergency action plan as necessary, and submit
a copy of the updated portions of the emergency action plan to the
executive director annually beginning three years after the effective
date of this section. If the emergency action plan was reviewed by
the owner and no updates were necessary, the owner shall submit written
notification to the executive director that no updates to the emergency
action plan have been adopted or implemented.
(h) The owner shall perform a table top exercise of
the emergency action plan on the frequency provided in the owner's
emergency action plan, or at least every five years, with emergency
management personnel in areas downstream of the dam.
§299.62.Security of Dams.
(a) Owners of high-hazard dams that are notified in
writing by the executive director within six months of the effective
date of these rules of dams that may need increased security shall
address:
(1) security at the owner's dams to prevent unauthorized operation or access; and
(2) backup power requirements to ensure operation of
the dam and appurtenant structures.
(b) The owner shall develop a security plan for the
dam within two years of being notified by the executive director and
shall submit the security plan to the executive director for review
and comment.
(c) The executive director shall file the security
plan in the agency's confidential, permanent files.
This agency hereby certifies that the proposal has
been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803571
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
STATUTORY AUTHORITY
These new sections are proposed under the authority granted to
the commission in Texas Water Code (TWC), §5.012, which provides
that the commission is the agency responsible for implementing the
constitution and laws of the state relating to conservation of natural
resources and protection of the environment; §5.013, which establishes
the commission's authority over various statutory programs, such as
dam safety; §5.103 and §5.105, which establish the commission's
general authority to adopt rules; §12.052, which establishes
the commission's authority to promulgate rules for the safe construction,
maintenance, repair, and removal of dams located in this state; and §7.002,
which authorizes the commission to enforce provisions of the TWC.
These proposed new sections implement TWC, §§5.103, 5.105, and 12.052.
§299.71.Enforcement.
(a) If the executive director alleges violations of
this chapter, enforcement action may be pursued according to Texas
Water Code, Chapter 7 and §70.5 of this title (relating to Remedies).
Remedies include:
(1) seeking an emergency order from the commission
to either reconstruct, modify, alter, or repair the deficient dam
or remove the dam as described in §299.72 of this title (relating
to Emergency Orders); or
(2) referring to the Office of the Attorney General
for civil judicial action, including the assessment of civil penalties
and injunctive relief.
(b) An owner who willfully fails or refuses to take
appropriate action within the time frames addressed in the appropriate
executive director enforcement letters is liable for a penalty of
not more than $5,000 a day for each day the violation continues.
§299.72.Emergency Orders.
According to the provisions of Texas Water Code, §12.052,
and Chapter 35 of this title (relating to Emergency and Temporary
Orders and Permits; Temporary Suspension or Amendment of Permit Conditions),
the commission may issue emergency orders, without notice to the owner,
directing the owner of a deficient dam to take immediate and appropriate
action to remedy situations posing a threat to human life or property.
This agency hereby certifies that the proposal has
been reviewed by legal counsel and found to be within the agency's
legal authority to adopt.
Filed with the Office of the Secretary of State on July 11, 2008.
TRD-200803572
Robert Martinez
Director, Environmental Law Division
Texas Commission on Environmental Quality
Earliest possible date of adoption: August 24, 2008
For further information, please call: (512) 239-2548
SUBCHAPTER B. DESIGN AND EVALUATION OF DAMS
SUBCHAPTER C. CONSTRUCTION REQUIREMENTS
SUBCHAPTER D. REMOVAL OF DAMS
SUBCHAPTER E. EMERGENCY ACTION
SUBCHAPTER A. GENERAL PROVISIONS
SUBCHAPTER B. DESIGN AND EVALUATION OF DAMS
SUBCHAPTER C. CONSTRUCTION REQUIREMENTS
SUBCHAPTER D. OPERATION AND MAINTENANCE OF DAMS
SUBCHAPTER E. REMOVAL OR BREACH OF DAMS
SUBCHAPTER F. EMERGENCY MANAGEMENT
SUBCHAPTER G. ENFORCEMENT