TITLE 16.ECONOMIC REGULATION

Part 1. RAILROAD COMMISSION OF TEXAS

Chapter 3. OIL AND GAS DIVISION

16 TAC §3.95, §3.97

The Railroad Commission of Texas proposes amendments to §3.95, relating to Underground Storage of Liquid or Liquefied Hydrocarbons in Salt Formations, and §3.97, relating to Underground Storage of Gas in Salt Formations. Consistent with the Commission's wish to further the goals of safety and the prevention and control of pollution, the Commission proposes the amendments in order to reduce the possibility of explosion and fire at such facilities and enhance the safety of such facilities in light of the gas release and fire at the Moss Bluff Hub Partners, LP natural gas storage facility and incidents at several liquid hydrocarbon storage facilities.

On August 19, 2004, a gas release and fire occurred at the Moss Bluff Hub Partners Hydrocarbon Storage facility in Liberty County, Texas. The incident occurred during "de-brining," when brine was being extracted from the cavern through a well string at the same time as gas was injected into the cavern through casing. Investigation revealed that the likely initiating event at Moss Bluff was a separation of the brine string at or above 3724-feet below the ground surface within the gas-bearing area of the storage cavern. Gas entered the brine string, reached the surface, and flowed into the above-ground brine piping. The emergency shut-down valve on the above-ground brine piping appeared to have operated properly, because investigators recovered it in the closed state. The evidence suggests that transient mechanical forces or "water hammer" produced by the sudden pressure surge caused the surface piping to fracture between the wellhead and the emergency shutdown valve. The break occurred at a location in the piping that had experienced wall loss due to internal corrosion. This break in the above-ground brine piping initially fueled the fire. The geometry of the surface piping directed gas and fire downward at the base of the wellhead, weakening the assembly that attached the wellhead to the casing. Eventually the entire wellhead assembly separated from the casings and was ejected to the side and gas began escaping vertically through the production casing. The fire self-extinguished for approximately 28 seconds before reigniting.

Investigation of this incident revealed unexpectedly extensive internal corrosion of the brine piping. This piping was transferred from service on another storage well, installed, and successfully pressure tested in 2000. Past experience had not indicated corrosion to be a problem. Inspection and testing of such piping is not a requirement under current provisions of §3.95 and §3.97.

Two other incidents resulted in the surface release of stored liquefied petroleum gas (LPG) in 2000 and crude oil in 2005 at underground liquid hydrocarbon storage facilities in Texas. These incidents were associated with the remote location of an emergency shutdown valve from the wellhead (crude oil release) and water hammer-induced pressure transient rupture of the surface piping nipple (LPG release).

After considering the findings of the investigation of these incidents, the Commission determined that new safety requirements were necessary and, on December 7, 2004, directed staff to initiate rulemaking to establish such requirements. These proposed amendments incorporate new requirements for integrity management of surface piping, location of emergency shutdown valves, fire suppression capabilities, data acquisition, and record retention.

In January 2005, staff sent a questionnaire to all operators of underground hydrocarbon storage facilities to gather additional information concerning the current status of construction, maintenance, operations, and record keeping. In addition, in May 2005, staff held a workshop to review operator responses from the questionnaire and to gather input from affected operators to evaluate the advisability, cost, and effectiveness of potential new safety regulations. The Commission also published on its website a draft of the proposed amendments for informal comment. Staff has used the input from these forums in drafting these proposed amendments.

The Commission proposes amendments to §3.95(a), relating to definitions, to amend the definition of "emergency shutdown valve" to substitute the term "wellhead" for "well." The Commission also proposes to amend the definition of "hydrocarbon storage well or storage well" to clarify that the well includes the storage wellhead, casing, tubing, borehole, and cavern.

The Commission proposes to add two new definitions. The Commission proposes to define the term "storage wellhead" as "equipment installed at the surface of the wellbore, including the casinghead and tubing head, spools, block or wing valves, and instrument flanges." In addition, the proposed new definition limits the length of spool pieces to less than six feet to allow the operator flexibility in aligning wellheads, emergency shutdown valves, and surface piping. The limitation on length is necessary because investigation results indicate that long spool pieces are subject to failure by water hammer effects. Industry input suggested limiting spool piece length to six feet.

The Commission proposes to add a new definition for the term "surface piping" as "any pipe within a storage facility that is directly connected to a storage well, outboard of the emergency shutdown valve, exclusive of tubing and casing, and used to transport product, brine, or fresh water to or from a storage well whether such pipe is above or below ground level."

New definitions for "storage wellhead" and "surface piping" are needed because other proposed rule amendments specify that the emergency shutdown valve must be located between the storage wellhead and surface piping and such terms are not defined in the current rule.

The Commission proposes to amend §3.95(c)(4) to specify that the required permit by that section is necessary for storing saltwater or brine in a pit, as well as for disposing of saltwater or other oil and gas waste arising out of or incidental to the creation, operation, or maintenance of an underground hydrocarbon storage facility.

The Commission proposes to amend §3.95(d), relating to standards for underground storage zone, to change the heading of subsection (d)(1) from "Impermeable salt formation" to "Geologic, construction, and operating performance," to more accurately describe the subject matter of this subdivision.

The Commission proposes substantive amendments to §3.95(h), relating to safety. The Commission proposes to amend §3.95(h) to specify that active storage wells must possess a functional emergency shutdown valve when the well is in service, notwithstanding compliance time periods for configuring the emergency shutdown valve on the wellhead. The Commission proposes to change the heading of §3.95(h)(2) from "Emergency shutdown valves" to "Storage wellhead" to reflect the fact that the Commission is proposing safety requirements for the entire storage wellhead, not just the emergency shutdown valves. The Commission proposes to amend §3.95(h)(2)(B) to require that, within three years of the effective date of this rule or in conjunction with the next scheduled mechanical integrity test of the storage well, the operator shall install, as required, emergency shutdown valves in a position between the storage wellhead and the product and brine surface piping of each of hydrocarbon storage well and, if required, between the storage wellhead and fresh water surface piping of the well. The Commission also proposes that no product, brine, or fresh water surface piping may be installed between the storage wellhead and the emergency shutdown valve. The proposed amendment also allows an operator to request, within one year of the effective date of the section, an exception to the storage wellhead configuration or compliance date of this subparagraph and propose an alternative configuration for approval by the Commission or its designee.

The proposed amendment mandating the location of the emergency shutdown valve directly between the wellhead and surface piping is intended to increase the safety of the emergency shutdown system. The current rule does not address the physical positioning of the emergency shutdown valve. Experience has shown that the emergency shutdown valve is most effective when the valve is flanged directly to the wellhead. The recent gas release and wellhead failure at a gas storage facility resulted, in part, from the location of an emergency valve on surface piping approximately 35 feet from the wellhead. After the emergency shutdown valve closed as designed, a pressure transient believed related to water hammer fractured the brine surface piping allowing gas to escape and ignite. A water hammer-induced pressure transient also is implicated in at least two release incidents associated with surface piping at liquid hydrocarbon storage facilities operating at Mont Belvieu.

The Commission proposes to change the heading of §3.95(h)(3) from "Brine and fresh water piping" to "Product, brine and fresh water surface piping" to expand the requirements to the product piping and to clarify that the requirements in the paragraph apply to surface piping. The Commission proposes to add a new subparagraph (A), which requires that the product surface piping be designed for the permitted maximum allowable operating pressure on the hydrocarbon side of the well. The Commission proposes to amend §3.95(h)(3)(B) (formerly subparagraph (A)) to require that brine surface piping be designed for the maximum operating pressure on the brine side of the well and designed to transport, under emergency conditions, product to the brine system vapor control system.

The Commission proposes to amend §3.95(h)(3)(C) (redesignated from subparagraph (B)) to clarify that the requirements in the subparagraph pertain to fresh water surface piping, and to clarify the requirement that such piping must be designed to withstand the permitted maximum allowable operating pressure of the hydrocarbon side of the well unless it is equipped with an emergency shut down valve.

The Commission proposes to amend §3.95(h)(4)(C), regarding overfill detection and automatic shut-in methods, to require that, within one year of the effective date of the proposed amendments, each storage cavern shall have at least two required devices or methods of overfill detection. Currently, the rule does not specify that the devices or methods must be redundant. It has always been the intent of the Commission that in the event of the failure of some component, another method of overfill detection would remain functional. The Commission intends to insure the failure of a single device does not disable both methods of overfill detection. The Commission proposes to amend subsection (h)(4)(C)(ii) to allow operators the flexibility of using pressure transducers on the brine piping in addition to pressure switches.

The Commission proposes to amend §3.95(h)(5) and (6), relating to leak detectors and Brine system gas vapor control, respectively, to delete references to deadlines that already have already passed. The Commission proposes to amend subsection (h)(7), relating to fire detection devices or methods, to add requirements for fire control systems and to delete reference to a deadline that has already passed. The Commission proposes to add new subparagraph (C) to require that, within three years of the effective date of the amendment, fire suppression capability be available at each storage wellhead in active storage service. The proposed new subparagraph allows an operator to request Commission approval of an exception to this schedule or the fire suppression requirement as long as the request includes a proposal for an alternate schedule or means of protection from wellhead fire and provided the request is made within one year of the effective date of the amendments.

The fire suppression requirement is intended to provide protection for rescue personnel and equipment cooling. The absence of such fire control systems contributed to the complete wellhead failure of a gas storage well and damage to adjacent structures associated with the gas release and fire at Moss Bluff Hub Partners. The fire suppression capability is not necessarily directed towards capacity sufficient to extinguish a wellhead fire. Extinguishing such a fire could be an imprudent course of action, unless the source of the leak was found and repaired. Rather, the fire suppression capability should be sufficient to provide for short-term protection for emergency personnel and for cooling of structures and wellheads potentially affected by a fire at a wellhead or surface pipe.

The Commission proposes to amend §3.95(h)(8), relating to emergency response plan, to delete reference to a deadline that already has passed.

The Commission proposes to amend §3.95(h)(9)(B), relating to notification of emergency or uncontrolled release, to require that an operator file with the Commission, within 30 days of any emergency, significant loss of fluids, significant mechanical failure, or other problem that increases the potential for an uncontrolled release, a written report on the root cause of the incident, and file with the Commission, within 90 days of an incident, a written report describing the operational changes, if any, that will be implemented to reduce the likelihood of the recurrence of a similar incident. The current rule requires only written confirmation of an event within five working days of the event. The proposed amendments will make hydrocarbon storage operations safer in the future by better helping the Commission, and operators, identify causes of uncontrolled releases and make corrections to prevent or reduce releases.

The Commission proposes to amend §3.95(h)(10) relating to public education, §3.95(h)(12) relating to employee safety training, §3.95(h)(13), relating to warning systems and alarms, and §3.95(h)(14), relating to wind socks, to delete references to deadlines that already have passed.

The Commission proposes to amend §3.95(h)(15), relating to Barriers, to delete reference to a deadline that already has passed and to require barriers around above ground hydrocarbon piping, process equipment and storage vessels in areas within 100 feet of a public road, in addition to the current requirement that barriers be placed where vehicles normally may be expected to travel. The Commission proposes this amendment because at least one incident has occurred when a driver lost control of a vehicle on a public road, allowing the vehicle to leave the roadway, and impact surface piping at a gas storage facility.

The Commission proposes to add new subsection (h)(16), relating to wellhead, surface piping, and related equipment, to require that such piping and equipment be designed, installed, and operated in accordance with engineering standards appropriate to the expected service conditions to which the piping and equipment will be subject. In addition, the Commission proposes to require that, within one year of the effective date of the rule amendments, the operator must report the Commission the particular engineering standards under which the wellhead equipment, product, fresh water, and brine surface piping, and related equipment are designed, installed, tested, maintained and operated.

The Commission proposes to amend subsection (k)(1) to clarify that the operating pressure of each hydrocarbon storage well may not exceed the permitted maximum allowable operating pressure. This proposed change is intended to conform the rule language generally accepted use of the phrase "maximum allowable operating pressure."

The Commission proposes to amend §3.95(l), relating to Monitoring requirements, to add a new paragraph (5) on data recording, which would require that, within three years of the effective date of the amendments, operators have in place and functioning a system to electronically record all liquid and gas pressures, injection volumes, and rates at least once per minute and that operators shall record emergency actuations of the emergency shutdown valve. This increased frequency of data recording is needed to insure that operators record sufficient information relating to physical conditions that immediately precede an accident or incident to help diagnose root causes. Experience with several incidents at hydrocarbon storage facilities has revealed that operational data were not recorded at a sufficient frequency to help diagnose the root cause of the incident.

The Commission proposes to change the heading of subsection (n) from "Records retention" to "Operations, construction, and maintenance records retention." The proposed amendments to this subsection would require that operators retain electronic records of well pressures, flow rates, hydrocarbon volumes for three months instead of five years. The proposed amendments also add to the record keeping requirement for each well, flow rates and hydrocarbon volumes and deletes interface levels from each well. Because these operational data are primarily intended to diagnose accidents and incidents, long-term retention is unwarranted. The Commission proposes to change the heading of subsection (n)(2) from "Equipment data" to "Construction and maintenance data" and to require an operator to retain for the life of the facility documents and records pertaining to installation, inspection, maintenance, and testing of equipment required under subsections (h) and (l), and to expand the record keeping requirements to documents and records pertaining to drilling, mining, and completion of storage wells. The extension of the retention period is prudent and necessary to insure that critical information on well construction, well testing, and safety equipment testing be retained for the life of the facility. It is often necessary to examine the results of past tests and procedures to properly interpret current test results, especially for tests that have recurrence intervals of five years, such as mechanical integrity tests. Obviously, in such cases where these records are currently unavailable, the Commission does not intend for the new requirement to be applied retroactively. However, with the new requirement the Commission intends to insure that if the records are currently available, they will be preserved for the life of the facility, and will pass to future owners or operators of the facilities should ownership or operatorship of a facility be transferred.

The Commission proposes to change the heading of §3.95(o) from "Testing" to "Testing and Maintenance." Proposed new subsection (o)(1), would require that all hydrocarbon storage wells drilled into salt domes and having a single casing string cemented to the surface to have the casing inspected by mechanical, ultrasonic, or magnetic methods at least once every five years and after each workover that involves physical changes to the cemented casing string. Currently, all operators of liquid hydrocarbon storage wells drilled into salt domes and having a single casing string cemented to the surface are required by permit to have the casing inspected by mechanical, ultrasonic, or magnetic methods at least once every five years. Since the Commission and operators agreed to the permit conditions requiring such testing, the tests have detected significant casing damage prompting the operators at four facilities to repair the damage before a significant leak could occur. Nitrogen-brine mechanical integrity tests are not capable of detecting most classes of casing damage. The proposed amendment would insure that in the event of transfer of ownership of well facilities, the new operators are bound to the same requirements of previous owners.

The Commission proposes to add a new paragraph (3) to subsection (o), relating to storage wellhead, to require operators to inspect and pressure test storage wellhead components to 125 percent of permitted maximum allowable operating pressure in conjunction with the hydrocarbon storage well integrity test schedule. Although it is typical industry practice to test wellhead components in conjunction with a storage well mechanical integrity test, such tests currently are not mandated by rule.

The Commission proposes to add new paragraph (4) to subsection (o), relating to product, freshwater, and brine surface piping. The new paragraph would require, within three years of the effective date of this section or in conjunction with the storage well integrity testing, that all product, freshwater and brine surface piping within a hydrocarbon storage facility be maintained according to a piping integrity management plan and that within one year, the operator must submit such a plan to the Commission or its designee for approval by the Commission or its designee. This proposed amendment aligns the requirements for the testing and maintenance of surface piping within storage facilities with current testing and maintenance requirements for pipelines transporting hazardous materials.

The Commission proposes amendments to §3.97, relating to Underground Storage of Gas in Salt Formations. The Commission proposes amendments to §3.97(a) to amend the definitions of "emergency shutdown valve," "gas storage well or storage well," and "leak detector," and to add new definitions for the terms "storage wellhead" and "surface piping." The Commission proposes to amend the definition of "emergency shutdown valve" to substitute "wellhead" for "well." The Commission proposes to amend the definition of "gas storage well or storage well" to clarify that the term includes the storage wellhead, casing, tubing, borehole, and cavern. The Commission proposes to amend the definition of "leak detector" to include "fire" detectors. Leak detectors must be capable of detection by chemical or physical means the presence of gas or the escape of gas or the presence of flame or heat of a fire. References to "vapor" are deleted from the definition because the natural gas in a storage cavern is not technically a vapor, because there is no natural gas liquid in the system.

The Commission proposes to add a definition of "storage wellhead" to mean the equipment installed at the surface of the wellbore, including the casinghead and tubing head, spools, block or wing valves, and instrument flanges. In addition, the proposed language would limit the length of spool pieces to less than six feet to allow operators flexibility in aligning wellheads, emergency shutdown valves, and surface piping. The limitation on length is necessary to prevent the installation of unnecessarily long spool pieces, which are subject to failure by water hammer effects as was the case at the recent gas release and fire at the gas storage facility described above. The Commission proposes to define "surface piping" as any pipe within a storage facility that is directly connected to a storage well, exclusive of tubing and casing, and used to transport gas, brine, or fresh water to or from a storage well whether such pipe is above or below ground level. New definitions for "storage wellhead" and "surface piping" are needed because other proposed rule amendments specify that the emergency shutdown valve must be located between the storage wellhead and surface piping and such terms are not defined in the current rule.

The Commission proposes to amend the title of §3.97(d)(1) from "Impermeable salt formation" to "Geologic, construction and operating performance" to more accurately describe the subject matter of this subdivision.

The Commission proposes to amend §3.97(e)(3), relating to notice and hearing, to correct a typographical error.

The Commission proposes to amend §3.97(h), relating to safety, to specify that active storage wells must possess a functional emergency shutdown valve when the well is in service, notwithstanding compliance time periods for configuring the emergency shutdown valve on the wellhead. The Commission proposes to amend §3.97(h)(2), relating to emergency shut down valves, to change the title of the paragraph to "Storage wellhead" and to modify subparagraph (A) to require that, within three years of the effective date of these amendments or in conjunction with the next mechanical integrity test of the storage cavern, the operator install, as required, emergency shutdown valves in a position between the wellhead and the gas injection/withdrawal surface piping of each storage well and between the wellhead and any brine or fresh water surface piping. In addition, the Commission proposes to add a requirement that there may be no gas, brine, or fresh water piping between the wellhead and the emergency shutdown valve. The new language would allow an operator to request an exception to the storage wellhead configuration or compliance date and propose an alternative configuration or workover schedule provided the request and alternative proposal is are received within one year of the effective date of these amendments. The Commission or its designee must approve any such request.

The proposed amendment mandating the location of the emergency shutdown valve directly between the wellhead and surface piping is intended to enhance the safety of the emergency shutdown system. The current rule does not address the physical positioning of the emergency shutdown valve. Experience has shown that the safest location for the emergency shutdown valve is flanged directly to the wellhead. The recent gas release and wellhead failure at a gas storage facility resulted, in part, from the location of an emergency valve on surface piping. After the emergency shutdown valve closed as designed, a pressure transient believed related to water hammer fractured the brine surface piping allowing gas to escape and ignite.

The Commission proposes to add new subsection (h)(3), relating to gas, brine, and fresh water piping, which would require that gas surface piping be designed for the permitted maximum allowable operating pressure on the hydrocarbon side; that brine surface piping be designed for the maximum brine wellhead pressure; and that fresh water and brine surface piping be either isolated from the well or designed for the permitted maximum allowable operating pressure on the hydrocarbon side. This language is parallel to §3.95(h)(3)(C) for liquid storage wells where fresh water surface piping is more commonly installed.

The Commission proposes to amend renumbered subsection (h)(4), relating to cavern debrining and solution mining operations, to require that each storage well have two or more redundant devices or methods of overfill detection during cavern debrining operations or solution mining operations conducted with gas in storage in the same cavern. It has always been the intent of the Commission that, in the event of the failure of some component, another method of overfill detection remains functional. The Commission intends to enhance the likelihood that the failure of a single device does not disable both methods of overfill detection.

The Commission proposes to amend renumbered §3.97(h)(4)(i) and (ii) specifically to allow the use of pressure transducers in addition to pressure switches.

The Commission proposes to change the title of renumbered subsection (h)(5) from "Leak detectors" to "Leak or fire detectors," and to require that, within two years of the effective date of these amendments, a leak or fire detector be installed and in operation at each gas storage well and each structurally enclosed compressor site. The Commission proposes to delete the language in this paragraph concerning distance from a residence, commercial establishment, church, school, or small, and well defined outside area as well as the definition of "well defined outside area." Currently, the rule requires operators to install leak detectors only if a storage well or compressor station is within 100 yards of a residence, commercial establishment, church, school or public area. The proposed change would require operators to install leak or fire detectors regardless of the distance to commercial or public facilities. A major release incident at one of the gas storage facility demonstrated the potential for significant damage and risk to public heath and safety extends beyond 100 yards from a well or compressor station. The Commission proposes to make conforming amendments to subparagraph (B).

The Commission proposes to amend renumbered subsection (h)(6), relating to warning systems and alarms, to require that all leak or fire detectors or other methods that actuate the emergency shutdown valve be integrated with warning systems within two years of the effective date of these amendments.

The Commission proposes to amend renumbered subsection (h)(7) to remove a reference to a deadline that has already passed.

The Commission proposes to amend renumbered subsection (h)(8), relating to notification of emergency or uncontrolled release, to clarify that an operator must report to the Commission any significant loss of gas, as well as fluids. In addition, the amended language would require that the operator file with the Commission within 30 days of an incident a written report on the root cause of the incident and file with the Commission within 90 days of an incident a written report that describes the operational changes, if any, that will be implemented to reduce the likelihood of a recurrence of a similar incident. This language would replace the current requirement that requires that the operator report a significant loss of fluids and confirm the report in writing within five working days.

The Commission proposes to add a new paragraph (11) to subsection (h), relating to fire suppression capability, to require that, within three years of the effective date of these amendments, each operator have fire suppression capability to protect each wellhead and compression station, unless the operator requests within one year of the effective date of these amendments, and the Commission or its designee approves, an exception to the schedule or fire suppression requirement. The fire suppression requirement is intended to provide protection for rescue personnel and equipment cooling. The absence of such fire control systems contributed to the complete wellhead failure of a gas storage well and damage to adjacent structures associated with the gas release and fire at Moss Bluff Hub Partners. The fire suppression capability is not necessarily directed towards capacity sufficient to extinguish a wellhead fire. Extinguishing such a fire could be an imprudent course of action, unless the source of the leak was found and repaired. Rather, the Commission intends that the operator have capability sufficient to provide for short-term protection of emergency personnel protection and for cooling of structures and wellheads potentially affected by a fire from a well or surface pipe.

The Commission proposes to add a new paragraph (12) to subsection (h), relating to wellhead piping and related equipment, to require that all wellhead equipment, gas, fresh water, and brine surface piping and related equipment be designed, installed, tested, maintained, and operated in accordance with engineering standards appropriate to the expected service conditions to which the piping and equipment will be subject. In addition, within one year of the effective date of these amendments, the operator must report to the Commission the particular engineering standards under which wellhead equipment, gas, fresh water, and brine surface piping and related equipment are designed, installed, tested, maintained, and operated.

The Commission further proposes to add a new paragraph (13) to subsection (h), relating to barriers, which would require that, within one year of the effective date of these amendments, operators place barriers designed to prevent unintended impact by vehicles and equipment around above grade hydrocarbon piping, hydrocarbon processing equipment where vehicles normally may be expected to travel, or within 100 feet of a public road. The Commission proposes this amendment because at least one incident has occurred when a driver lost control of a vehicle on a public road, allowing the vehicle to leave the roadway, and impact above ground piping at a gas storage facility.

The Commission proposes to make other conforming amendments to subsection (h) and to update the rule to indicate that requirements for which previous versions of the rule established deadlines are now current requirements because the deadlines have passed.

The Commission proposes to amend §3.97(k), relating to Operating pressure, to insert "allowable" into the phrase "permitted maximum allowable operating pressure" and to specify that permitted maximum allowable operating pressure is that pressure identified on the Commission permit or order, or on the permit application.

The Commission proposes to amend §3.97(l)(1), relating to gas pressure, to make conforming amendments to clarify that pressure sensors must be integrated electronically with the emergency shutdown valve actuation system as required by the amendments in §3.97(h). The Commission also proposes to add a new paragraph (5), relating to data recording, which would require that, within three years of the effective date of these amendments, operators electronically record all liquid and gas pressures, injection volumes and rates at least once per minute and that operators record emergency actuations of the emergency shutdown valve. This proposed amendment is designed to aid in the analysis of upset conditions by requiring operators to record operational data at relatively high frequency. The lack of electronically recorded data on operational conditions at a sufficient frequency has hindered the ability of operators and the Commission to understand operating conditions immediately preceding incidents at storage facilities.

The Commission proposes to change the title of §3.97(n) from "Records retention" to "Operations, construction, and maintenance records retention," and to propose new records retention requirements. The Commission proposes to change the title of paragraph (1) from "Gas injection and withdrawal data" to "Operations data," and to amend this subsection to require that operators retain electronic records of well pressures, flow rates, gas volumes for three months instead of five years. Because these operational data are intended primarily to diagnose accidents and incidents, long-term retention is unwarranted. The Commission proposes to change the title of paragraph (2) from "Equipment data" to "Construction and maintenance data" and to amend this subsection to require that operators maintain documents and records on the drilling, mining, and completion of storage wells and the maintenance and testing of safety equipment required under subsections (h) and (l) and that those records be retained for the life of the facility. The extension of the retention period is prudent and necessary to insure that critical information on well construction, well testing, and safety equipment and testing is retained for the life of the facility. It is often necessary to examine the results of past tests and procedures to properly interpret current tests, especially tests that have recurrence intervals of five years, such as mechanical integrity tests. Obviously, in such cases where these records currently are unavailable, the Commission does not intend that the new requirement be applied retroactively. However, the new requirement would insure that if the records are currently available, they will be preserved for the life of the facility and will pass for retention purposes to future owners and/or operators of the facilities should ownership or operatorship of a facility be transferred.

The Commission proposes to amend §3.97(o), relating to Testing, to change the title to "Testing and maintenance." The Commission proposes to add a new paragraph (3), relating to "Storage wellhead," that would require that testing or inspection of storage wellhead components be performed in conjunction with the integrity test schedule of the hydrocarbon storage well. The Commission proposes to add a new paragraph (4), relating to "Fresh water, brine and gas surface piping," to require that all gas, brine, and fresh water surface piping be maintained according to a piping integrity management plan within three years or in conjunction with the testing of storage well integrity. Within one year of the effective date of this section, the operator must submit a piping integrity management plan for approval by the Commission or its designee. This proposed amendment aligns the requirements for the testing and maintenance of surface piping in a gas storage facility with current testing and maintenance requirements for pipelines transporting hazardous materials. Gas piping and fresh water and brine piping within storage facilities could, in emergency situations, transport hazardous materials.

Leslie Savage, Planning and Administration, Oil and Gas Division, has determined that for each year of the first five years the proposed amendments will be in effect, the fiscal implications as a result of enforcing or administering amended §3.95 and §3.97 will be negligible.

There will be no fiscal implications for local governments.

Texas Government Code, §2006.002 requires a state agency considering adoption of a rule that would have an adverse economic effect on small businesses or micro-businesses to reduce the effect if doing so is legal and feasible considering the purpose of the statutes under which the rule is to be adopted. Before adopting a rule that would have an adverse economic effect on small businesses, a state agency must prepare a statement of the effect of the rule on small businesses, which must include an analysis of the cost of compliance with the rule for small businesses and a comparison of that cost with the cost of compliance for the largest businesses affected by the rule, using cost for each employee, cost for each hour of labor, or cost for each $100 of sales.

Ms. Savage has determined that the proposed amendments would not affect any small or micro-businesses so there would be no cost of compliance for small businesses or micro-businesses. However, Commission staff has attempted to calculate the anticipated average economic cost of upgrading facilities to meet the proposed amendments to §3.95 and §3.97. Currently, there are 54 facilities in Texas at which liquid or liquefied hydrocarbons are stored in underground salt formations. There are approximately 497 storage wells at these 54 facilities. Many of these facilities already have in place the additional safety equipment that would be required under these proposed amendments. The Commission sent a survey to the operators of these facilities to determine the current equipment status and piping configuration at liquid hydrocarbon storage facilities, and the responses indicate that at least 29 percent and up to 37 percent of the liquid storage wells have emergency shutdown valves that already are located between the wellhead and surface piping or are attached to spool pieces. In addition, 89 percent of the wells associated with liquid storage operations have some form of fire suppression capability. Fire or leak detection devices already are required at wells in liquid hydrocarbon storage service, whereas only gas storage wells near public schools, churches or public areas are currently required to have leak or fire detection devices.

Most operators of liquid hydrocarbon storage facilities have some mechanism in place to verify the integrity of surface piping. Responses to the Commission's survey indicate that the operators of only 11 percent of the liquid hydrocarbon storage wells did not have a surface piping integrity management plan or did not know if a plan existed.

These statistics show that for the new safety proposals being contemplated in this rulemaking, a significant number of operators of liquid hydrocarbon storage wells already have met the proposed new requirements in this rulemaking.

The total anticipated average economic cost of complying with amendments regarding reinstalling emergency shutdown valves, installing fire monitors, and fire detectors during the first three years the section is in effect is estimated to exceed $4,000,000 for all of the 40 existing liquid hydrocarbon storage facilities and is estimated to exceed $1,000,000 for all of the 14 existing natural gas storage facilities. The Commission determined this anticipated average economic cost based upon information submitted to the Commission in response to the 2005 survey, and upon assumptions regarding costs of safety equipment and devices required under proposed amendments to §3.95. The Commission was unable to estimate the cost of complying with new requirements regarding data recording and retention.

In comparison to the estimated anticipated costs of complying with the proposed new requirement, the failure of a single gas storage well at a gas storage facility resulted in the loss of five billion cubic feet of gas at an estimated cost of $30,000,000. Damage to the surrounding facility is estimated to be in the millions of dollars.

Based on the response of operators of facilities storing natural gas in salt caverns to the Commission's survey, at least 58 percent and up to 75 percent of gas storage wells currently have emergency shutdown valves that already are located between the wellhead and surface piping or are attached to spool pieces. In addition, 36 percent of the gas storage wells have some form of fire suppression capability. Fire or leak detection devices already are required at wells in liquid storage service, whereas only gas storage wells near public schools, churches or public areas are required to have leak or fire detection devices. Currently, although no gas storage wells are located near public schools, churches or public areas, approximately 30 percent of the wells are protected by such devices.

Operator responses to the survey indicate that for all the major new safety proposals being contemplated, a significant number of operators of gas storage wells already have implemented many of the proposed amendments.

Ms. Savage has determined that for each year of the first five years that the amendments will be in effect the primary public benefit will be an increase in the safety of persons living and working in areas where liquid or liquefied hydrocarbons or natural gas or other gases are stored in underground formations. In addition, these amendments will increase safety of personal or public property located in such areas.

Comments on the proposal may be submitted to Rules Coordinator, Office of General Counsel, Railroad Commission of Texas, P.O. Box 12967, Austin, Texas 78711-2967; online at www.rrc.state.tx.us/rules/commentform.html; or by electronic mail to rulescoordinator@rrc.state.tx.us. The Commission specifically solicits comments regarding the estimated anticipated costs of the proposed amendments. The Commission will accept comments for 30 days after publication in the Texas Register . Comments should refer to Oil and Gas Docket No. 20-0245837. The Commission encourages all interested persons to submit comments no later than the deadline. The Commission cannot guarantee that comments submitted after the deadline will be considered. For further information, call Dr. Steve Seni at (512) 475-4439. The status of Commission rulemakings in progress is available at www.rrc.state.tx.us/rules/proposed.html.

The Commission proposes the amendments to §3.95 and §3.97 under (1) Texas Natural Resources Code, §81.051, which gives the Commission jurisdiction over all common carrier pipelines in Texas, oil and gas wells in Texas, persons owning or operating pipelines in Texas, and persons owning or engaged in drilling or operating oil or gas wells in Texas; (2) Texas Natural Resources Code, §81.052, which authorizes the Commission to adopt all necessary rules for governing and regulating persons and their operations under the jurisdiction of the Commission, including such rules as the Commission may consider necessary and appropriate to implement state responsibility under any federal law or rules governing such persons and their operations; (3) Texas Natural Resources Code, §85.041, which prohibits the purchase, acquisition, or sale, or the transporting, refining, processing, or handling in any other way, of oil or gas, produced in whole or in part in violation of any oil or gas conservation statute of this state or of any rule or order of the Commission under such a statute, and the purchase, acquisition, or sale, or the transporting, refining, processing, or handling in any other way, of any product of oil or gas which is derived in whole or in part from oil or gas or any product of either, which was in whole or part produced, purchased, acquired, sold, transported, refined, processed, or handled in any other way, in violation of any oil or gas conservation statute of this state, or of any rule or order of the Commission under such a statute; (4) Texas Natural Resources Code, §85.042, which authorizes the Commission to promulgate and enforce rules and orders necessary to carry into effect the provisions of §85.041, and to prevent that section's violation, and, when necessary, to make and enforce rules either general in their nature or applicable to particular fields for the prevention of actual waste of oil or operations in the field dangerous to life or property; (5) Texas Natural Resources Code, §85.201, which directs the Commission to make and enforce rules and orders for the conservation of oil and gas and prevention of waste of oil and gas; (6) Texas Natural Resources Code, §85.202, which authorizes the Commission to make rules and orders to prevent waste of oil and gas in drilling and producing operations and in the storage, piping, and distribution of oil and gas; to require dry or abandoned wells to be plugged in a manner that will confine oil, gas, and water in the strata in which they are found and prevent them from escaping into other strata; for the drilling of wells and preserving a record of the drilling of wells; to require wells to be drilled and operated in a manner that will prevent injury to adjoining property; to prevent oil and gas and water from escaping from the strata in which they are found into other strata; to provide rules for shooting wells and for separating oil from gas; to require records to be kept and reports made; and to provide for issuance of permits, tenders, and other evidences of permission when the issuance of the permits, tenders, or permission is necessary or incident to the enforcement of the Commission's rules or orders for the prevention of waste, and authorizes the Commission to do all things necessary for the conservation of oil and gas and prevention of waste of oil and gas and to adopt other rules and orders as may be necessary for those purposes; (7) Texas Natural Resources Code, §86.041, which grants the Commission broad discretion in administering the provisions of this chapter and to adopt any rule or order in the manner provided by law that the Commission finds necessary to effectuate the provisions and purposes of this chapter; (8) Texas Natural Resources Code, §86.042, which directs the Commission to adopt and enforce rules and orders to conserve and prevent the waste of gas; prevent the waste of gas in drilling and producing operations and in the piping and distribution of gas; require dry or abandoned wells to be plugged in a way that confines gas and water in the strata in which they are found and prevents them from escaping into other strata; provide for drilling wells and preserving a record of them; require wells to be drilled and operated in a manner that prevents injury to adjoining property; prevent gas and water from escaping from the strata in which they are found into other strata; require records to be kept and reports made; provide for the issuance of permits and other evidences of permission when the issuance of the permit or permission is necessary or incident to the enforcement of its blanket grant of authority to make any rules necessary to effectuate the law; and otherwise accomplish the purposes of this chapter; (9) Texas Natural Resources Code, §211.011, which gives the Commission jurisdiction over all salt dome storage of hazardous liquids and over salt dome storage facilities used for the storage of hazardous liquids; (10) Texas Natural Resources Code, §211.012, which directs the Commission to adopt safety standards and practices for the salt dome storage of hazardous liquids and the facilities used for that purpose that require the installation and periodic testing of safety devices at a salt dome storage facility; the establishment of emergency notification procedures for the operator of a facility in the event of a release of a hazardous substance that poses a substantial risk to the public; fire prevention and response procedures; employee and third-party contractor safety training with respect to the operation of the facility; and other requirements that the Commission finds necessary and reasonable for the safe construction, operation, and maintenance of salt dome storage facilities; (11) Texas Natural Resources Code, §211.013, which requires each owner or operator of a hazardous liquid salt dome storage facility to maintain records, make reports, and provide any information the Commission may require with respect to the construction, operation, or maintenance of the facility; and requires the Commission by rule to designate the records required to be maintained and the reports required to be filed by the owner or operator and shall provide forms for reports if necessary; (12) Texas Natural Resources Code, §117.012, which requires the Commission to adopt rules that include safety standards for and practices applicable to the intrastate transportation of hazardous liquids or carbon dioxide by pipeline and intrastate hazardous liquid or carbon dioxide pipeline facilities; and (13) Texas Utilities Code, §§121.201 - 121.210, which authorize the Commission to adopt safety standards and practices applicable to the transportation of gas and to associated pipeline facilities within Texas to the maximum degree permissible under, and to take any other requisite action in accordance with, 49 United States Code Annotated §60101, et seq .

Texas Natural Resources Code, §§81.051, 81.052, 85.041, 85.042, 85.201, 85.202, 86.041, 86.042, 211.011, 211.012, 211.013, and 117.012, and Texas Utilities Code, §§121.201 - 121.210 are affected by the proposed amendments.

Statutory authority: Texas Natural Resources Code, §§81.051, 81.052, 85.041, 85.042, 85.201, 85.202, 86.041, 86.042, 211.011, 211.012, 211.013, and 117.012, and Texas Utilities Code, §§121.201 - 121.210.

Cross-reference to statutes: Texas Natural Resources Code, §§81.051, 81.052, 85.041, 85.042, 85.201, 85.202, 86.041, 86.042, 211.011, 211.012, 211.013, and 117.012, and Texas Utilities Code, §§121.201 - 121.210.

Issued in Austin, Texas, on February 7, 2006.

§3.95.Underground Storage of Liquid or Liquefied Hydrocarbons in Salt Formations.

(a) Definitions. The following terms, when used in this section, shall have the following meanings, unless the context clearly indicates otherwise.

(1) - (4) (No change.)

(5) Emergency shutdown valve--A valve that automatically closes to isolate a hydrocarbon storage wellhead [ well ] from surface piping in the event of specified conditions that, if uncontrolled, may cause an emergency.

(6) - (7) (No change.)

(8) Hydrocarbon storage well or storage well--A well , including the storage wellhead, casing, tubing, borehole, and cavern, used for the injection or withdrawal of liquid or liquefied hydrocarbons into or out of an underground hydrocarbon storage facility.

(9) - (15) (No change.)

(16) Storage wellhead--Equipment installed at the surface of the wellbore, including the casinghead and tubing head, spools, block or wing valves, and instrument flanges. Spool pieces must have a length less than six feet to be considered a part of the storage wellhead.

(17) Surface piping--Any pipe within a storage facility that is directly connected to a storage well, outboard of the emergency shutdown valve, and exclusive of tubing and casing, and used to transport product, brine, or fresh water to or from a storage well whether such pipe is above or below ground level.

(18) [ (16) ] Underground hydrocarbon storage facility or storage facility--A facility used for the storage of liquid or liquefied hydrocarbons in an underground salt formation, including surface and subsurface rights, appurtenances, and improvements necessary for the operation of the facility.

(b) (No change.)

(c) Application.

(1) - (3) (No change.)

(4) Related activities. An application for a permit to store saltwater or brine in a pit or to dispose of saltwater or other oil and gas waste arising out of or incidental to the creation, operation, or maintenance of an underground hydrocarbon storage facility shall be filed in accordance with applicable Commission [ commission ] requirements.

(d) Standards for underground storage zone.

(1) Geologic, construction, and operating performance [ Impermeable salt formation ]. An underground hydrocarbon storage facility may be created, operated, or maintained only in an impermeable salt formation in a manner that will prevent waste of the stored hydrocarbons, uncontrolled escape of hydrocarbons, pollution of fresh water, and danger to life or property. Natural gas storage operations are not authorized under the provisions of this section. A permit under §3.97 of this title (relating to Underground Storage of Gas in Salt Formations) is required to convert from storage of liquid or liquefied hydrocarbons to storage of natural gas in an underground salt formation.

(2) (No change.)

(e) - (g) (No change.)

(h) Safety. The following safety requirements shall apply to all underground hydrocarbon storage facilities, except as specifically provided otherwise. Provided, however, the provisions of this subsection shall not apply to any hydrocarbon storage well that is out of service and disconnected from all surface piping. Notwithstanding the compliance time periods specified in [ paragraphs (1) - (15) of ] this subsection, a new storage facility permitted under this section must have all required safety measures and equipment in place before commencement of storage operations at the facility. All storage facilities that are permitted on the effective date of this section must have such safety measures and equipment in place within the period of time specified. Further, until such a facility has all the safety measures and devices required by paragraphs (2) - (7) and (13) - (16) [ (13) - (15) ] of this subsection in place, the facility must have an attendant on site at all times. Notwithstanding the compliance time periods specified in paragraph (2)(B) of this subsection, no storage well in active service may be operated without a fully functional emergency shutdown valve unless in compliance with specified conditions of paragraph (2)(C) of this subsection.

(1) (No change.)

(2) Storage wellhead [ Emergency shutdown valves ].

(A) The requirements of this paragraph do not apply to underground hydrocarbon storage facilities storing only crude oil.

(B) Within three [ two ] years of the effective date of this section, or in conjunction with the next scheduled integrity test of the storage well, the operator shall have installed emergency shutdown valves between the storage wellhead and [ shall be installed on ] the product and brine surface piping [ sides ] of each hydrocarbon storage well and, if required under paragraph (3) of this subsection, between the storage wellhead and [ on ] fresh water surface piping of [ to ] the well. The operator shall not install any product, brine, or fresh water surface piping between the storage wellhead and the emergency shutdown valve. Within one year of the effective date of the section, an [ An ] operator may request an exception to the storage wellhead configuration or compliance date of this subparagraph and propose an alternative configuration or workover schedule for approval by the Commission [ commission ] or its designee. A storage well that is out of service and is disconnected from surface piping shall be exempt from this requirement until reactivated for active hydrocarbon storage. Emergency shutdown valves shall meet the following requirements.

(i) - (iv) (No change.)

(C) (No change.)

(3) Product, brine, [ Brine ] and fresh water surface piping.

(A) Product surface piping shall be designed for the permitted maximum allowable operating pressure on the hydrocarbon side of the well.

(B) Brine surface piping shall be designed for the maximum brine wellhead pressure and to transport, under emergency conditions, product to the brine system gas vapor control system described in paragraph (6) of this subsection.

[(A) Brine piping from the wellhead to the emergency shutdown valve shall be designed for the maximum wellhead pressure on the hydrocarbon side of the well.]

(C) [ (B) ] Fresh water surface piping, if any, must either be:

(i) isolated from the wellhead when fresh water is not being injected into the well; or

(ii) designed for the permitted maximum allowable operating [ wellhead ] pressure on the hydrocarbon side of the well unless [ and ] equipped with an emergency shutdown valve.

(4) Overfill detection and automatic shut-in methods.

(A) - (B) (No change.)

(C) Within one year of the effective date of this section, each storage cavern shall have at least two [ one ] of the following redundant devices or methods in operation[ . Within two years of the effective date of this section, each storage cavern shall have at least two of the following devices or methods in operation ]:

(i) (No change.)

(ii) a preset pressure sensor switch or transducer on the brine piping that is set to automatically close all emergency shutdown valves in response to a preset pressure. This pressure sensor or transducer may be used in conjunction with weep hole(s) on a safety string that is concentric with the brine string, or in conjunction with weep hole(s) on the brine string;

(iii) - (v) (No change.)

(5) Leak detectors.

(A) (No change.)

(B) A [ Within two years of the effective date of this section, a ] leak detector shall be installed and in operation at the wellhead of each hydrocarbon storage well and at each process and transfer area and each surface vessel area that contains liquid or liquefied hydrocarbons. These leak detectors shall be integrated with the warning system required in paragraph (13)(A) of this subsection.

(C) Leak [ Within two years of the effective date of this section, leak ] detectors shall be installed and in operation at four locations that are evenly spaced around the perimeter of the brine pit(s).

(D) (No change.)

(6) Brine system gas vapor control.

(A) (No change.)

(B) Gas [ Within two years of the effective date of this section, gas ] vapor control devices shall be installed and in operation at each brine pit system to ignite or capture hydrocarbon vapors that are heavier than air. Control devices shall consist of at least one of the following:

(i) - (iv) (No change.)

(C) (No change.)

(7) Fire detection devices or methods and fire control systems .

(A) Fire [ Within two years of the effective date of this section, fire ] detection devices or methods shall be installed and in operation at all process and transfer areas. Fire detection devices or methods specified in this paragraph shall be integrated with the warning system required in paragraph (13)(A) of this subsection. Fire detection shall consist of at least one of the following:

(i) - (iii) (No change.)

(B) (No change.)

(C) Within three years of the effective date of this section, each storage wellhead in active storage service shall have fire suppression capability. Within one year of the effective date of this section, the operator may request an exception to the schedule or fire suppression requirement of this subparagraph and propose an alternative schedule or means of protection from wellhead fire for approval of the Commission or its designee.

(8) Emergency response plan. Each [ Within six months of the effective date of this section, each ] storage facility shall submit to the Commission [ commission ] a written emergency response plan. The plan shall address spills and releases, fires, explosions, loss of electricity, and loss of telecommunication services. The plan shall describe the storage facility's emergency response communication system, procedures for coordination of emergency communication and response activities with local emergency planning committees and other local authorities, use of warning systems, procedures for citizen and employee emergency notification and evacuation, and employee training. The initial plan must be designed based upon the existing safety measures at the facility. The plan shall be updated as changes in safety features at the facility occur, or as the Commission [ commission ] or its designee requires. The plan shall include a plat of the facility that shows the location of wells, processing areas, loading racks, brine pits, and other significant features at the site. A copy of the plan shall be provided to the local emergency response planning committee and to any other local governmental entity that submits a written request for a copy of the plan to the operator. Copies of the plan shall also be available at the storage facility and at the company headquarters.

(9) Notification of emergency or uncontrolled release.

(A) (No change.)

(B) Commission. The operator shall report to the appropriate Commission [ commission ] district office as soon as practicable any emergency, significant loss of fluids, significant mechanical failure, or other problem that increases the potential for an uncontrolled release. The operator shall file with the Commission within 30 days of the incident a written report on the root cause of the incident. The operator shall file with the Commission within 90 days of the incident a written report that describes the operational changes, if any, that have been or will be implemented to reduce the likelihood of a recurrence of a similar incident [ confirm the report in writing within five working days ].

(10) Public education. Each [ Within six months of the effective date of this section, each ] facility operator shall establish a continuing educational program to inform residents within a one-mile radius of a hydrocarbon storage facility of emergency notification and evacuation procedures.

(11) (No change.)

(12) Employee safety training.

(A) Each [ Within six months of the effective date of this section, each ] operator shall prepare and implement a plan to train and test each employee at each underground hydrocarbon storage facility on operational safety to the extent applicable to the employee's duties and responsibilities. The facility's emergency response plan shall be included in the training program.

(B) (No change.)

(13) Warning systems and alarms.

(A) All [ Within two years of the effective date of this section, all ] leak detectors, fire detectors, heat sensors, pressure sensors, and emergency shutdown instrumentation shall be integrated with warning systems that are audible and visible in the local control room and at any remote control center. The circuitry shall be designed so that failure of a detector or heat sensor, excluding meltdown and fused devices, to function will activate the warning.

(B) A manually operated alarm shall be installed at each attended storage facility [ within two years of the effective date of this section ]. The alarm shall be audible in areas of the facility where personnel are normally located.

(14) Wind socks. At [ Within one year of the effective date of this section, at ] least one wind sock that is visible at any time from any normal work location within the storage facility shall be installed at the facility.

(15) Barriers. Barriers [ Within one year of the effective date of this section, barriers ] designed to prevent unintended impact by vehicles and equipment shall be placed around above-grade hydrocarbon piping, hydrocarbon process equipment, and surface hydrocarbon storage vessels in areas where vehicles may normally be expected to travel or within 100 feet of a public road .

(16) Wellhead, surface piping, and related equipment. All wellhead equipment, product, fresh water, and brine surface piping, and related equipment shall be designed, installed, and operated in accordance with engineering standards to the expected service conditions to which the piping and equipment will be subject. Within one year of the effective date of this section, the operator shall report to the Commission the particular engineering standards under which wellhead equipment, product, fresh water, and brine surface piping, and related equipment are designed, installed, tested, maintained, and operated.

(i) - (j) (No change.)

(k) Operating requirements.

(1) Operating pressure. The operating pressure of each hydrocarbon storage well shall not exceed the permitted maximum allowable operating pressure for that well. The permitted maximum allowable operating pressure is that pressure specified in the Commission [ commission ] permit or order, or, if not specified in the permit or order, that pressure stated in the application or the application for amendment to a permit or order. The maximum operating pressure at the shoe of the lowermost cemented casing shall not exceed 0.8 pounds per square inch per foot of depth.

(2) (No change.)

(l) Monitoring requirements.

(1) - (4) (No change.)

(5) Data recording. Within three years of the effective date of this section, operators shall have installed and have functioning equipment to electronically record all liquid and gas pressures and injection volumes and rates at a frequency of at least once per minute, and all actuations of the emergency shutdown valve.

(m) (No change.)

(n) Operations, construction, and maintenance records [ Records ] retention.

(1) Hydrocarbon injection and withdrawal data. The operator shall retain for three months all electronic [ five years ] records of hydrocarbon storage well pressures, flow rates, hydrocarbon volumes [ interface levels (if any), hydrocarbons ] injected into and withdrawn from each well, and the hydrocarbon inventory of each cavern.

(2) Construction and maintenance [ Equipment ] data. The operator shall retain for the life of the facility [ five years ] documents and records pertaining to the drilling, mining, and completion of storage wells and [ installation, ] inspection, maintenance, and testing of equipment required under subsections (h) and (l) of this section , and shall transfer all such documents and records to any new owner and/or new operator of the facility . Records of any test of a safety device required under subsection (h) of this section shall be available for on-site inspection within 10 days of the date of the test.

(3) Extension during investigation. Any documents or records that contain information pertinent to the resolution of any pending regulatory enforcement proceeding shall be retained beyond the prescribed retention [ five-year ] period until the resolution of such proceeding.

(o) Testing and Maintenance .

(1) Each hydrocarbon storage well drilled into a salt dome and having a single casing string cemented to the surface shall have the casing inspected by mechanical, ultrasonic, or magnetic methods at least once every five years and after each workover that involves physical changes to the cemented casing string.

(2) [ (1) ] Integrity tests. Each hydrocarbon storage well shall be tested for integrity prior to being placed into service, at least once every five years, and after each workover that involves physical changes to any cemented casing string. The following requirements apply to all such integrity tests.

(A) A hydrocarbon storage well shall be tested for integrity by the nitrogen-brine interface method or an alternative approved by the Commission [ commission ], or its designee.

(B) A test procedure shall be filed with the Commission [ commission ] for approval at least 10 days before the test date.

(C) The operator shall notify the district office at least five days prior to conducting any integrity test.

(D) A complete record of each integrity test shall be filed in duplicate with the district office within 30 days after testing is completed. The record shall include a chronology of the test, copies of all downhole logs, storage well completion information, pressure readings, volume measurements, temperature logs and readings, and an explanation of the test results that addresses the precision of the test in terms of a calculated leak rate.

(E) Storage well pressures shall be allowed to stabilize to a rate of change of less than 10 psi in 24 hours before the testing period begins.

(3) Storage Wellhead. Storage wellhead components, including spool pieces, shall be inspected and pressure tested to 125 percent of the permitted maximum allowable operating pressure in conjunction with hydrocarbon storage well integrity test schedule.

(4) Product, fresh water, and brine surface piping. Within three years of the effective date of this section, or in conjunction with the storage well integrity testing, all product, freshwater, and brine surface piping shall be maintained according to the facility's piping integrity management plan. Within one year of the effective date of this section, the operator shall submit a piping integrity management plan for approval by the Commission or its designee.

(5) [ (2) ] Alternative monitoring. An operator may request the Commission [ commission ] or its designee to approve storage well pressure monitoring as an alternative to integrity testing for hydrocarbon storage wells that are out of storage service. An out-of-service storage well must be tested for integrity according to the procedures specified in paragraph (2) [ (1) ] of this subsection before it may be returned to storage service.

(p) - (r) (No change.)

§3.97.Underground Storage of Gas in Salt Formations.

(a) Definitions. The following terms, when used in this section, shall have the following meanings, unless the context clearly indicates otherwise.

(1) - (3) (No change.)

(4) Emergency shutdown valve--A valve that automatically closes to isolate a gas storage wellhead [ well ] from surface piping in the event of specified conditions that, if uncontrolled, may cause an emergency.

(5) (No change.)

(6) Gas storage well or storage well--A well used for the injection or withdrawal of natural gas or any other gaseous substance into or out of an underground gas storage facility , including the storage wellhead, casing, tubing, borehole, and cavern .

(7) Leak or fire detector--A device capable of detecting by chemical or physical means the presence of gas [ hydrocarbon vapor ] or the escape of gas or the presence of flame or heat of a fire [ vapor through a small opening ].

(8) - (11) (No change.)

(12) Storage wellhead--Equipment installed at the surface of the wellbore, including the casinghead and tubing head, spools, block or wing valves, and instrument flanges. Spool pieces must have a length less than six feet to be considered a part of the storage wellhead.

(13) Surface piping--Any pipe within a storage facility that is directly connected to a storage well, outboard of the emergency shutdown valve, and exclusive of tubing and casing, and used to transport gas, brine, or fresh water to or from a storage well whether such pipe is above or below ground level.

(14) [ (12) ] Underground gas storage facility or storage facility--A facility used for the storage of natural gas or any other gaseous substance in an underground salt formation, including surface and subsurface rights, appurtenances, and improvements necessary for the operation of the facility.

(b) - (c) (No change.)

(d) Standards for underground storage zone.

(1) Geologic, construction, and operating performance [ Impermeable salt formation ]. An underground gas storage facility may be created, operated, or maintained only in an impermeable salt formation in a manner that will prevent waste of the stored gases, uncontrolled escape of gases, pollution of fresh water, and danger to life or property. This section does not authorize storage of liquid or liquefied hydrocarbons in an underground salt formation. A permit under §3.95 of this title (relating to Underground Storage of Liquid or Liquefied Hydrocarbons in Salt Formations) is required to convert from storage of natural gas to storage of liquid or liquefied hydrocarbons in an underground salt formation.

(2) (No change.)

(e) Notice and hearing.

(1) - (2) (No change.)

(3) Notice by publication. The applicant shall make diligent efforts to ascertain the name and address of each person identified under paragraph (1)(A) - (D) of this subsection. The exercise of diligent efforts to ascertain names and addresses of such persons shall require an examination of the county records where [ here ] the facility is located and an investigation of any other information of which the applicant has actual knowledge. If, after diligent efforts, the applicant has been unable to ascertain the name and address of one or more persons required to be notified under paragraph (1)(A) - (D) of this subsection, the notice requirements for those persons are satisfied by the publication of the notice of application as required in paragraph (2) of this subsection. The applicant must submit an affidavit to the Commission specifying the efforts that were taken to identify each person whose name and/or address could not be ascertained.

(4) - (5) (No change.)

(f) - (g) (No change.)

(h) Safety. The following safety requirements shall apply to all underground gas storage facilities. Provided, however, that the provisions of this subsection shall not apply to any natural gas storage well that is out of service and disconnected from surface piping. Notwithstanding the compliance time periods specified in this subsection, a new underground gas storage facility permitted under this section must have all required safety measures and equipment in place before commencement of storage operations at the facility. All existing storage facilities must have such safety measures and equipment in place within the period of time specified. Notwithstanding the compliance time periods specified in paragraph (2)(B) of this subsection, no storage well in active service may be operated without a fully functional emergency shutdown valve unless in compliance with specified conditions of paragraph (2)(C) of this subsection.

(1) (No change.)

(2) Storage wellhead [ Emergency shutdown valves ].

(A) Within three [ two ] years of the effective date of this section, or in conjunction with the next integrity test of the storage well, the operator shall have installed emergency shutdown valves between the wellhead and [ shall be installed on ] the gas injection/withdrawal surface piping of each storage well and between the wellhead and [ on ] any brine or fresh water surface piping [ that is connected at the wellhead ]. The operator shall not install any gas, brine, or fresh water surface piping between the wellhead and the emergency shutdown valve. Within one year of the effective date of this section, the [ An ] operator may request an exception to the storage wellhead configuration or compliance date of this subparagraph and propose an alternative configuration or workover schedule for approval by the Commission [ commission ], or its designee. A storage well that is out of service and is disconnected from surface piping shall be exempt from this requirement until reactivated for active gas storage. Emergency shutdown valves shall meet the following requirements : [ . ]

(i) - (iv) (No change.)

(B) (No change.)

(3) Gas, brine, and fresh water surface piping.

(A) Gas surface piping shall be designed for the permitted maximum allowable operating pressure on the hydrocarbon side of the well.

(B) Brine piping shall be designed for the maximum brine wellhead pressure.

(C) Fresh water and brine surface piping, if any, must either be:

(i) isolated from the wellhead when fresh water or brine is not being injected into the well; or

(ii) designed for the maximum allowable operating pressure on the hydrocarbon side of the well unless equipped with an emergency shutdown valve.

(4) [ (3) ] Cavern debrining and solution mining operations.

(A) Within one year of the effective date of this section, each storage well shall have two [ one ] or more of the following redundant devices or methods in operation during cavern debrining operations or during solution mining operations that are conducted with gas in storage in the same cavern. [ Within two years from the effective date of this section, each storage well shall have two or more of the following devices or methods in operation during cavern debrining operations or during solution mining operations that are conducted in a cavern with gas in storage in the same cavern. ] These devices are designed to prevent the release of gas into the brine and fresh water systems connected to the well during cavern debrining operations or during solution mining operations that are conducted with gas in storage in the same cavern. Gas release prevention shall consist of at least two of the following redundant devices or methods:

(i) emergency shutdown valves equipped with pressure sensor switches or transducers set to automatically close emergency shutdown valves on the brine side of the wellhead and on the fresh water piping, if any, in response to preset pressures on the brine and fresh water piping of the well;

(ii) weep hole(s) on the brine return string in conjunction with a preset pressure sensor switch or transducer on the brine piping that is set to automatically close emergency shutdown valves on the brine side of the wellhead and on the fresh water piping, if any, in response to a preset pressure;

(iii) a device on the brine return string or brine piping that detects hydrocarbon in the brine by physical or chemical characteristics and that is set to automatically close emergency shutdown valves on the brine side of the wellhead and on the fresh water piping, if any, in response to hydrocarbon detection;

(iv) an instrument that detects a rapid increase in the brine flow rate indicative of hydrocarbon in the brine and that is set to automatically close emergency shutdown valves on the brine side of the wellhead and on the fresh water piping, if any, in response to a preset flow rate or differential flow rate; or

(v) an alternative device or method approved by the Commission [ commission ].

(B) Solution mining of a cavern may occur while gas is in storage, provided that the injection of fresh water and the injection of gas do not occur simultaneously within the same cavern.

(5) [ (4) ] Leak or fire detectors.

(A) Within two years of the effective date of this section, a leak or fire detector shall be installed and in operation at each gas storage well and each structurally enclosed compressor site [ that is 100 yards or less from a residence, commercial establishment, church, school, or small, well-defined outside area, and at each structurally enclosed compressor site. For purposes of this section, the term "small, well-defined outside area" means an area such as a playground, recreation area, outdoor theater, or other place of public assembly that is occupied by 20 or more persons on at least five days a week for 10 weeks in any 12-month period. The days and weeks need not be consecutive ].

(B) Leak or fire detectors shall be tested twice each calendar year at intervals not to exceed 7 1/2 months, and, when defective, repaired or replaced within 10 days. Leak or fire detectors shall be integrated with warning systems required in paragraph (6)(A) [ (5)(A) ] of this subsection.

(6) [ (5) ] Warning systems and alarms.

(A) Within two years of the effective date of this section, all leak or fire detectors and [ pressure ] sensors or methods that actuate the emergency shutdown valve shall be integrated with warning systems that are audible and visible in the control room and at any remote control center. The circuitry shall be designed so that failure of a leak or fire detector to function will activate the warning.

(B) A manually operated audible alarm shall be installed at each attended storage facility [ within 180 days of the effective date of this section ]. The alarm shall be audible in areas of the facility where personnel are normally located.

(7) [ (6) ] Emergency response plan. Each [ Within six months of the effective date of this section, each ] storage facility shall submit to the Commission [ commission ] a written emergency response plan. The plan shall address gas releases, fires, explosions, loss of electricity, and loss of telecommunication services. The plan shall describe the facility's emergency response communication system, procedures for coordination of emergency communication and response activities with local authorities, use of warning systems, procedures for citizen and employee emergency notification and evacuation, and employee training. The plan shall also include a plat of the facility showing the locations of wells, processing areas, and other significant features at the facility. The initial plan must be designed based upon the existing safety measures at the facility. The plan shall be updated as changes in safety features at the facility occur, or as the Commission [ commission ] or its designee requires. A copy of the plan shall be provided to the local emergency response committee and to any other local governmental entity that submits a written request for a copy of the plan to the operator. Copies of the plan shall also be available at the storage facility and at the company headquarters.

(8) [ (7) ] Notification of emergency or uncontrolled release.

(A) Emergency response personnel. Each operator shall notify the county sheriff's office, the county emergency management coordinator, and any other appropriate public officials which are identified in the emergency response plan of any emergency that could endanger nearby residents or property. Such emergencies include, but are not limited to, an uncontrolled release of hydrocarbons from a storage well or a leak or fire at any area of the storage facility. The operator shall give notice as soon as practicable following the discovery of the emergency. At the time of the notice, the operator shall also report an assessment of the potential threat to the public.

(B) Commission. The operator shall report to the appropriate Commission [ commission ] district office as soon as practicable any emergency, significant loss of gas or fluids, significant mechanical failure, or other problem that increases the potential for an uncontrolled release. The operator shall file with the Commission within 30 days of the incident a written report on the root cause of the incident. Within 90 days of the incident, the operator shall file with the Commissioner a written report that describes the operational changes, if any, that have been or will be implemented to reduce the likelihood of a recurrence of a similar incident [ confirm the report in writing within five working days ].

(9) [ (8) ] Annual emergency drill. Annually, each operator shall conduct a drill that tests response to a simulated emergency. Written notice of the drill shall be provided to the appropriate Commission district office, the county emergency management coordinator, and the county sheriff's office at least seven days prior to the drill. Local emergency response authorities shall be invited to participate in all such drills. The operator shall file a written evaluation of the drill and plans for improvements with the appropriate district office and the county emergency management coordinator within 30 days after the date of the drill.

(10) [ (9) ] Employee safety training.

(A) Each [ Within six months of the effective date of this section, each ] operator shall prepare and implement a plan to train and test each employee at each underground gas storage facility on operational safety to the extent applicable to the employee's duties and responsibilities. The facility's emergency response plan shall be included in the training program.

(B) Each operator shall hold a safety meeting with each contractor prior to the commencement of any new contract work at an underground gas storage facility. Emergency measures, including safety and evacuation measures specific to the contractor's work, shall be explained in the contractor safety meeting.

(11) Fire suppression capability.

(A) Within three years of the effective date of this section, each operator shall have fire suppression capability to protect each wellhead and compression station.

(B) Within one year of the effective date of this section, the operator may request an exception to the schedule or fire suppression requirement of this subparagraph and propose an alternative schedule or means of protection from wellhead fire for approval of the Commission or its designee.

(12) Wellhead, piping, and related equipment.

(A) All wellhead equipment, gas, fresh water, and brine surface piping, and related equipment shall be designed, installed, tested, maintained, and operated in accordance with engineering standards to the expected service conditions to which the piping and equipment will be subject.

(B) Within one year of the effective date of this section, the operator shall report to the Commission the particular engineering standards under which wellhead equipment, gas, fresh water, and brine surface piping, and related equipment are designed, installed, tested, maintained, and operated.

(13) Barriers. Within one year of the effective date of this section, barriers designed to prevent unintended impact by vehicles and equipment shall be placed around above grade hydrocarbon piping, hydrocarbon process equipment where vehicles may normally be expected to travel, or within 100 feet of a public road.

(i) - (j) (No change.)

(k) Operating pressure.

(1) Not to exceed maximum. The operating pressure of each gas storage well shall not exceed the permitted maximum allowable operating pressure for that well. The permitted maximum allowable operating pressure is that pressure specified in the Commission [ commission ] permit or order, or, if not specified in the permit or order, that pressure stated in the application or the application for amendment to a permit or order.

(2) (No change.)

(l) Monitoring requirements.

(1) Gas pressure. Gas pressure on the injection/withdrawal casing or tubing or piping connected thereto shall be equipped with a pressure sensor to continuously monitor the wellhead pressure. Pressure sensors shall be integrated electronically with the warning systems , [ and ] alarms , and emergency shutdown valve actuation system as required in subsection (h)(2)(A) and (6)(A) [ (h)(5)(A) ] of this section.

(2) - (4) (No change.)

(5) Data recording. Within three years of the effective date of this section, operators shall have installed and have functioning equipment to electronically record all liquid and gas pressures and injection volumes and rates at a frequency of at least once per minute, and all actuations of the emergency shutdown valve.

(m) (No change.)

(n) Operations, construction, and maintenance records [ Records ] retention.

(1) Operations [ Gas injection and withdrawal ] data. The operator shall retain for three months the electronic [ five years ] records of storage well pressures, volumes of gases injected and withdrawn, and the inventory of gas in storage.

(2) Construction and maintenance [ Equipment ] data. The operator shall retain for the life of the facility [ five years ] documents and records pertaining to the drilling, mining, and completion of storage wells, and the [ installation, ] inspection, maintenance, and testing of equipment relating to the safe operation of the storage facility required under subsections (h) and (l) of this section, and shall transfer all such documents and records to any new owner and/or new operator of the facility .

(3) Extension during investigation. The operator shall retain beyond the prescribed retention period any documents or records that contain operational data pertaining to the resolution of any pending regulatory enforcement proceedings until the resolution of such proceedings. [ Any documents or records that contain information pertinent to the resolution of any pending regulatory enforcement proceeding shall be retained beyond the five-year period until the resolution of such proceeding. ]

(o) Testing and Maintenance .

(1) - (2) (No change.)

(3) Storage Wellhead. Storage wellhead components, including spool pieces, shall be tested or inspected for integrity in conjunction with hydrocarbon storage well integrity test schedule.

(4) Fresh water, brine, and gas surface piping. Within three years of the effective date of this section, or in conjunction with the storage well integrity testing, all gas, freshwater, and brine surface piping shall be maintained according to the facility's piping integrity management plan. Within one year of the effective date of this section, the operator shall submit a piping integrity management plan for approval by the Commission or its designee.

(p) (No change.)

(q) Penalties.

(1) Penalties. Violations of this section may subject the operator to penalties and remedies specified in Texas Natural Resources Code, Title 3; Texas Utilities Code, Chapter 121 [ Texas Civil Statutes, Article 6053-3 ]; and other statutes administered by the Commission [ commission ].

(2) (No change.)

(r) (No change.)

This agency hereby certifies that the proposal has been reviewed by legal counsel and found to be within the agency's legal authority to adopt.

Filed with the Office of the Secretary of State on February 7, 2006.

TRD-200600634

Mary Ross McDonald

Managing Director

Railroad Commission of Texas

Earliest possible date of adoption: March 26, 2006

For further information, please call: (512) 475-1295


Chapter 9. LP-GAS SAFETY RULES

Subchapter A. GENERAL REQUIREMENTS

16 TAC §9.2, §9.52

The Railroad Commission of Texas proposes amendments to §9.2 and §9.52, relating to Definitions, and Training and Continuing Education Courses. The Commission proposes these amendments to clarify some wording and procedures for the training and continuing education requirements, and to add a procedure by which certificate holders may receive continuing education credit for completing certain Certified Employee Training Program (CETP) courses.

In §9.2, the Commission proposes to amend the definition of "CETP" to add a reference to the National Propane Gas Association (NPGA), or the authorized agents or successors to NPGA or to the Propane Education and Research Council (PERC). The amendment is necessary because PERC has authorized NPGA to provide CETP training, and because such training may be offered by these organizations' authorized agents rather than by the organizations themselves.

In §9.52, the Commission proposes most of the amendments to clarify the rule requirements. In subsection (a), and in paragraph (1) of subsection (a), the Commission proposes to delete some repetitive wording and to add a reference to the tables in subsection (h) of the rule. The Commission proposes the deletion of the repetitive wording so that the tables, which list all the training and continuing education courses offered or approved by the Commission and the categories to which they apply, will be the definitive list of the courses that may be presented for Commission credit by certified individuals in each covered category. The Commission proposes to delete subsections (a)(1) and (2), and to redesignate existing paragraphs (3) and (4) as paragraphs (1) and (2).

In subsection (b), the Commission proposes to add wording to refer to the tables in subsection (h), and to delete the repetitive list of categories in paragraph (1)(A). The Commission proposes to redesignate subsection (b)(1)(B) and (C) as (A) and (B). In newly-designated subsection (b)(1)(A), the Commission has added a May 31, 2007, deadline by which public employees who are certified as of June 1, 2006, shall complete their continuing education requirement. This is consistent with amendments the Commission made to §9.51, relating to General Requirements for Training and Continuing Education, adopted on January 24, 2006, published in the February 10, 2006, issue of the Texas Register (31 TexReg 843), and effective March 1, 2006.

In subsection (b)(3), the Commission proposes to delete the sentence referring to any employee of a state agency, county, municipality, school district, or other government subdivision not being required to pay the annual certificate renewal fee, to make this rule consistent with the Commission's recent amendments to §9.51 of this title, referenced in the previous paragraph.

The Commission proposes new subsection (c) to address a situation in which a current certificate holder passes a Commission examination for an additional certification that requires completion of a training course. In this situation, the Commission would assign the certificate holder a training deadline pursuant to the requirements of §9.52(a)(1) regarding the new certification. Upon completion of that training, the Commission would then assign the certificate holder a new continuing-education deadline pursuant to §9.52(b).

The Commission proposes to redesignate current subsections (c) through (g) as subsections (d) through (h). The Commission does not propose any changes to the four tables listing the training and continuing education requirements; however, they are included in this rulemaking because the Commission proposes to change the subsection designation from subsection (g) to subsection (h).

The Commission proposes new subsection (i) to specify the procedure by which current certificate holders may obtain continuing-education credit for completion of an approved CETP course. Tables 3 and 4 of subsection (h) specify the CETP courses approved by the Commission and the categories to which they apply. Under the proposed procedure, a certificate holder who has successfully completed a CETP class, including any applicable knowledge and skills assessments, as determined by the issuance of a National Propane Gas Association class certificate, must submit to the Commission, either through regular mail or electronic mail, the individual's name, address, telephone number, and Social Security number; the LP-gas certification currently held; the CETP class date; and a readable copy of the CETP class certificate. AFRED must review the material submitted within 30 business days of receipt and must notify the certificate holder if the request to award Railroad Commission continuing-education credit is approved, denied, or incomplete. The certificate holder will have 30 calendar days from the date of a notice of deficiency to supply the additional required information. Certificate holders requesting credit for CETP class attendance must submit such requests to allow processing time so that a request is finally approved by May 31 in order for the certificate holder to receive credit toward that deadline.

Dan Kelly, Director, Alternative Fuels Research and Education Division, has determined that for each year of the first five years the proposed amendments are in effect there will be no fiscal implications for state or local government as a result of enforcing or administering the amendments.

Mr. Kelly has also determined that the public benefit anticipated as a result of the amendments will be clarification of Commission requirements regarding training and continuing education generally, and in particular clarification of the procedures for certificate holders to add a new certification or to obtain credit for completion of approved CETP courses.

Texas Government Code, §2006.002 requires a state agency considering adoption of a rule that would have an adverse economic effect on small businesses or micro-businesses to reduce the effect if doing so is legal and feasible considering the purpose of the statutes under which the rule is to be adopted. Before adopting a rule that would have an adverse economic effect on small businesses, a state agency must prepare a statement of the effect of the rule on small businesses, which must include an analysis of the cost of compliance with the rule for small businesses and a comparison of that cost with the cost of compliance for the largest businesses affected by the rule, using cost for each employee, cost for each hour of labor, or cost for each $100 of sales.

Pursuant to Texas Government Code, §2006.002(c), the Commission cannot determine the cost of compliance for individual, small business, or micro-business LP-gas businesses, because under the proposed amendments, attending and requesting credit for attendance at a CETP course is voluntary, not mandatory. The Commission assumes that there are LP-gas businesses that meet the definitions of "micro-business" and "small business" set forth in Texas Government Code, §2006.001(1) and (2), respectively; however, the Commission does not have data showing the expense for each employee, the expense for each hour of labor, or the total sales revenue for any LP-gas business. In addition, the costs for any particular LP-gas business will vary based on that business' situation. Therefore, the Commission is not able to determine the exact cost of compliance based on the cost for each employee, the cost for each hour of labor, or the cost for each $100 of sales pursuant to Texas Government Code, §2006.002(c). Further, pursuant to Texas Government Code, §2006.002, the Commission finds that, considering that the purpose of Texas Natural Resources Code, Chapter 113, is to ensure the safe use of LP-gas, it is not feasible to reduce any adverse effect the proposed amendments could have on individuals, small businesses, or micro-businesses based on the size of the business.

Comments on the proposal may be submitted to Rules Coordinator, Office of General Counsel, Railroad Commission of Texas, P.O. Box 12967, Austin, Texas 78711-2967; online at www.rrc.state.tx.us/rules/commentform.html; or by electronic mail to rulescoordinator@rrc.state.tx.us. The Commission will accept comments for 30 days after publication in the Texas Register . The Commission encourages all interested persons to submit comments no later than the deadline. The Commission cannot guarantee that comments submitted after the deadline will be considered. For further information, call Mr. Thomas Petru at (512) 463-6930. The status of Commission rulemakings in progress is available at www.rrc.state.tx.us/rules/proposed.html.

The Commission proposes the amendments pursuant to Texas Natural Resources Code, §113.051, which authorizes the Commission to adopt rules relating to any and all aspects or phases of the LP-gas industry that will protect or tend to protect the health, welfare, and safety of the general public, and §113.052, which authorizes the Commission to adopt by reference, in whole or in part the published codes of the National Fire Protection Association as standards to be met in the design, construction, fabrication, assembly, installation, use, and maintenance of containers, tanks, appliances, systems, and equipment for the transportation, storage, delivery, use, and consumption of LP-gas or any one or more of these purposes.

Statutory authority: Texas Natural Resources Code, §§113.051 and 113.052.

Cross-reference to statute: Texas Natural Resources Code, Chapter 113.

Issued in Austin, Texas on February 7, 2006.

§9.2.Definitions.

In addition to the definitions in any adopted NFPA pamphlets, the following words and terms, when used in this chapter, shall have the following meanings, unless the context clearly indicates otherwise.

(1) - (10) (No change.)

(11) CETP--The [ Propane Education and Research Council's ] Certified Employee Training Program offered by the Propane Education and Research Council (PERC), the National Propane Gas Association (NPGA), or their authorized agents or successors .

(12) - (52) (No change.)

§9.52.Training and Continuing Education Courses.

(a) Training. Applicants for a new certification and applicants who have passed a certification examination but have not completed an applicable training course [ listed in this subsection, other than Category E, F, G, I, or J management-level individuals and except as stated in paragraph (4) of this subsection, ] shall complete [ attend at least eight hours of ] training as specified in the tables in subsection (h) of this section prior to their first certificate renewal deadline [ of May 31 of the appropriate year. Applicants for Category D, E, F, G, I, J, K, or M management-level certification shall attend the course or courses specified for the category ]. Category E management-level applicants shall attend the 80-hour class; Category F, G, I, and J management-level applicants shall attend the 16-hour class; and Category D, K and M management-level applicants and all [ other ] applicants for employee-level certifications that are subject to training requirements shall attend an eight-hour class. A certificate holder's training deadline shall not be extended if that individual retakes and passes an examination for the current category and level of certification. A training deadline shall be extended only after a certificate holder successfully completes an applicable training class.

[ (1) The following management- or employee-level applicants shall complete the training requirements:]

[ (A) Category D management-level;]

[ (B) Category E management-level;]

[ (C) Category F management-level;]

[ (D) Category G management-level;]

[ (E) Category I management-level;]

[ (F) Category J management-level;]

[ (G) Category K management-level;]

[ (H) Category M management-level;]

[ (I) Bobtail employee-level;]

[ (J) DOT portable cylinder filler employee-level;]

[ (K) Service and Installation employee-level;]

[ (L) Appliance service and installation employee-level;]

[ (M) Motor/mobile fuel dispensing employee-level; and]

[ (N) Recreational vehicle (RV) technician employee-level.]

[ (2) Training requirements for an applicant for license shall be fulfilled by all prospective company representatives and operations supervisors.]

(1) [ (3) ] Individuals who pass an employee-level rules examination between March 1 and May 31 of any year shall have until May 31 of the next year to complete any required training. Individuals who pass an employee-level rules examination at other times shall have until the next May 31 to complete any required training. Completion of AFT shall be in accordance with subsection (g) [ (f) ] of this section.

(2) [ (4) ] Applicants for company representative or operations supervisor [ who do not comply with the conditional qualification in §9.17(g) of this title (relating to Designation and Responsibilities of Company Representatives and Operations Supervisors) ] shall comply with the training requirements in this section prior to the Commission issuing a certificate.

(b) Continuing education. A certificate holder shall complete at least eight hours of continuing education every four years as specified in the tables in subsection (h) of this section . Upon fulfillment of this requirement, the certificate holder's next continuing education deadline shall be four years after the May 31 following the date of the most recent class the certificate holder has completed, unless the class was completed on May 31, in which case the deadline shall be four years from that date. A certificate holder's continuing education deadline shall not be extended if an examination for a current category and level of certification is retaken and passed; a continuing education deadline shall be extended only after a certificate holder successfully completes an applicable continuing education class. An individual who completes a continuing education class after the assigned deadline shall have four years from the original deadline to complete the next class.

(1) Continuing education requirements for certain categories.

[ (1) Individuals completing their continuing education requirements shall then have four years to complete the next eight-hour continuing education requirement (unless a new certification is added that requires training as specified in subparagraph (B) of this paragraph). ]

[ (A) Certificate holders with one of the following certificates shall complete the continuing education classroom instruction and any required AFT for that class: ]

[ (i) Category D management-level; ]

[ (ii) Category E management-level; ]

[ (iii) Category F management-level; ]

[ (iv) Category G management-level; ]

[ (v) Category I management-level; ]

[ (vi) Category J management-level; ]

[ (vii) Category K management-level; ]

[ (viii) Category M management-level; ]

[ (ix) Bobtail employee-level; ]

[ (x) DOT portable cylinder filler employee-level; ]

[ (xi) Service and Installation employee-level; ]

[ (xii) Appliance service and installation employee-level; ]

[ (xiii) Motor/mobile fuel dispensing employee-level; and ]

[ (xiv) Recreational vehicle (RV) technician employee-level. ]

(A) [ (B) ] Certificate holders who hold only a Category D, F, G, J, or K certificate as of the effective date of this section shall complete their initial continuing education requirement by May 31, 2005. Beginning September 1, 2005, Category M and recreational vehicle technician certificate holders shall have until May 31, 2006, to complete their initial continuing education requirement. Certificate holders who hold a Category D, F, G, J, K, or M certificate or a recreational vehicle technician certificate and who have more than one certification as of February 1, 2001, shall complete their continuing education requirement by the continuing education deadline assigned for the initial certificate. Public employees who are certified as of June 1, 2006, shall complete their continuing education requirement by May 31, 2007.

(B) [ (C) ] Certificate holders who are certified to perform LP-gas activities covered by different certifications shall complete the continuing education requirements for any one of the certifications held in order to maintain active status. For each subsequent continuing education requirement, such individuals shall be responsible for attending a different continuing education class relevant to one of the other certifications held.

(2) Certificate holders who attend a class offered by an outside instructor shall not be entitled to a refund of the annual renewal fee or any other fees or penalties required by the Commission.

(3) Individuals who have not paid the annual certificate renewal fee, including general installers and repairman exemption holders or members of the general public, shall not attend training or continuing education classes free of charge, but may request from the AFRED training section to attend classes at the charge specified in §9.51 of this title (relating to General Requirements for Training and Continuing Education). Such requests shall be in writing and handled at AFRED's discretion on an individual basis and if space is available in the requested class. [ Any employee of a state agency, county, municipality, school district, or other governmental subdivision is not required to pay the fee. ]

(4) Any certificate holder who has timely paid the annual certificate renewal fee but is not otherwise required to attend a Commission continuing education class may voluntarily attend a class, if space is available, by registering with the AFRED training section as specified in §9.51 of this title (relating to General Requirements for Training and Continuing Education).

(c) Adding a new certification. A current certificate holder who successfully completes an examination for an additional certification that requires completion of a training course shall be assigned a training deadline pursuant to subsection (a)(1) of this section. Upon completion of the required training, the certificate holder shall be assigned a continuing education date pursuant to subsection (b) of this section.

(d) [ (c) ] Train-the-Trainer classes. The Train-the-Trainer classes shall not count as credit towards the training or continuing education requirements.

(e) [ (d) ] Class materials. Individuals who attend AFRED-taught classes shall receive a copy of the class materials at no charge. Additional copies may be purchased from AFRED at the established price.

(f) [ (e) ] Certificates of completion. The AFRED training section shall issue a certificate of completion to each individual who completes an AFRED-taught class. Individuals shall retain the certificates as proof of completion of the class.

(g) [ (f) ] Advanced field training (AFT). Some classes may include AFT in addition to the classroom hours, during which class attendees shall perform LP-gas activities. AFT shall be properly completed within 30 calendar days of attending the class. All qualification tasks included in the AFT shall be completed. The AFT materials, including the qualification checklist and the certification page, shall be readily available at the licensee's Texas business location for review by an authorized Commission representative during normal business hours.

(1) The responsibility of certifying AFT activities shall not be delegated to an unauthorized individual. AFT qualification tasks shall be witnessed by an authorized individual, verified as being successfully completed, and the AFT form signed as follows:

(A) For licensees with only one company representative, that company representative shall self-certify the AFT.

(B) For licensees with more than one company representative, one company representative may certify the AFT of another company representative, but shall not self-certify.

(C) Company representatives shall certify operations supervisors' AFT.

(D) The company representative or an operations supervisor authorized by the licensee and in current good standing with the Commission shall certify the employees' AFT.

(E) If authorized, a Commission-approved outside instructor may certify any AFT.

(2) Other AFT situations shall be handled as follows:

(A) For a certified individual employed by a licensee, the licensee shall retain the most recently completed AFT material for each applicable category of the individual's certification in the individual's employment records.

(B) For an individual who ceases employment with a licensee, the licensee shall retain the latest required AFT material for at least two years from the date the individual is no longer employed by the licensee. The two-year period shall be based on the renewal period for the examination renewal fee penalty. The licensee shall provide a copy of the AFT material to the individual.

(C) For an individual who begins employment with a different licensee, the new licensee shall obtain a copy of the individual's AFT material from the individual and shall place the copy in the individual's employment records.

(D) An individual who is never employed by a licensee shall retain the most recently completed AFT material for each applicable category of the individual's certification in a safe location for at least two years from the date the class that required the AFT was attended.

(E) For an individual who is employed by a licensee when a class requiring AFT is attended, but who prior to the AFT's being certified becomes employed by a new licensee, the new licensee shall certify the individual's AFT.

(F) For an individual who is employed by a licensee when a class requiring AFT is attended, but who prior to the AFT's being certified ceases employment with the licensee and wishes to continue performing LP-gas activities, the individual shall contact a company representative or operations supervisor of another applicable licensee or an AFRED-approved outside instructor to complete the AFT and maintain the LP-gas certification.

(3) Individuals who attend the 80-hour Category E management- level class or the 16-hour Category F, G, I, or J management- level class shall perform any required AFT activities during the class.

(4) If AFT is required for a class, the AFT checklist outlining the specific activities to be performed shall be included in the class materials.

(h) [ (g) ] Available courses. Training and continuing education courses and other information are shown in Tables 1 through 4 of this subsection. Items on the tables marked with an "x" indicate courses that meet training or continuing education requirements for management-level or employee-level certificate holders in that category.

Figure: 16 TAC §9.52(h)

[ Figure: 16 TAC §9.52(g) ]

(i) Credit for attendance at CETP courses. A certificate holder who has successfully completed a CETP class, including any applicable knowledge and skills assessments, may receive credit toward the continuing education requirements specified in this section as follows:

(1) The CETP class shall be approved for the category of certificate held as indicated on Tables 3 and 4 in subsection (h) of this section.

(2) The successful completion of a CETP class is determined by a National Propane Gas Association class certificate, which is issued only after an individual has completed the prescribed course of study, including any related knowledge and skills assessments, for the applicable CETP job classification.

(3) To receive credit toward the Commission's continuing education requirements, the certificate holder shall submit the following information, clearly readable, by regular mail to AFRED, Railroad Commission of Texas, P.O. Box 12967, Austin, Texas 78711-2967, or by electronic mail to the following address: CETP-credit@rrc.state.tx.us.

(A) the individual's full name, address, telephone number, Social Security number;

(B) the LP-gas certification(s) currently held; and

(C) the CETP class date and a readable copy of the CETP class certificate for an approved CETP class as specified in Tables 3 and 4 of subsection (h) of this section. The CETP class attendance date shall be within one year of the certificate holder's continuing education deadline.

(4) AFRED shall review the submitted material within 30 business days of receipt and shall notify the certificate holder in writing that the request is approved, denied, or incomplete. If the material is incomplete, AFRED shall identify the necessary additional information required. The certificate holder shall file the additional information within 30 calendar days of the date of a notice of deficiency in order to receive credit for the CETP course attendance. Certificate holders requesting credit for CETP class attendance shall submit such requests to allow processing time so that a request is finally approved by May 31 in order for the certificate holder to receive credit toward that deadline.

This agency hereby certifies that the proposal has been reviewed by legal counsel and found to be within the agency's legal authority to adopt.

Filed with the Office of the Secretary of State on February 7, 2006.

TRD-200600633

Mary Ross McDonald

Managing Director

Railroad Commission of Texas

Earliest possible date of adoption: March 26, 2006

For further information, please call: (512) 475-1295


Part 2. PUBLIC UTILITY COMMISSION OF TEXAS

Chapter 26. SUBSTANTIVE RULES APPLICABLE TO TELECOMMUNICATIONS SERVICE PROVIDERS

Subchapter R. PROVISIONS RELATING TO MUNICIPAL REGULATION AND RIGHTS-OF-WAY MANAGEMENT

16 TAC §26.461, §26.465

The Public Utility Commission of Texas (commission) proposes amendments to §26.461, relating to Access Line Categories, and §26.465, relating to Methodology for Counting Access Lines and Reporting Requirements for Certificated Telecommunications Providers. These amendments are necessary to address the impact of Senate Bill 5 on the commission's telecommunications right-of-way rules under Subchapter R, Provisions Relating to Municipal Regulation and Rights-of-Way Management. Additional amendments to §26.465 are also necessary to remove outdated reporting deadlines and reporting requirements.

Senate Bill 5 amended §283.002, of the Local Government Code, by amending subdivision (2) and adding subdivision (7), which resulted in an expanded definition of the term "certificated telecommunications provider." The commission is amending §26.461 and §26.465 to implement this amendment. SB 5 also amended the Public Utility Regulatory Act (PURA) by adding §55.1735, relating to Charge for Pay Phone Access Line. The commission is amending §26.465, relating to Methodology for Counting Access Lines and Reporting Requirements for Certificated Telecommunications Provides, to clarify that payphones lines are classified as Category 2 access line. Finally, the commission is deleting §26.465(g), relating to reporting procedures and requirements, as the deadlines regarding initial reporting in that section are no longer relevant.

Elango "Raj" Rajagopal, Senior Policy Analyst, Infrastructure and Reliability Division, and Andrew Kang, Staff Attorney, Legal Division, have determined that for each year of the first five-year period the proposed amended sections are in effect, there will be no fiscal implications for state government as a result of enforcing or administering the sections.

Mr. Rajagopal and Mr. Kang have determined that for each year of the first five years the proposed amended sections are in effect, the public benefit anticipated as a result of enforcing these sections will be an equitable assessment of municipal access line fees from certificated telecommunications providers and voice service providers in a technology neutral manner. In doing so, the amendments recognize the changes in telecommunication technology.

Mr. Rajagopal and Mr. Kang have determined that there will be no adverse economic effect on small businesses or micro-businesses as a result of enforcing the sections. There is some anticipated economic cost to persons who are required to comply with the amended sections as proposed. However, the public benefit of imposing municipal fees in a non-discriminatory manner should outweigh those costs.

Mr. Rajagopal and Mr. Kang have also determined that for each year of the first five years the proposed sections are in effect there should be no effect on a local economy, and therefore no local employment impact statement is required under §2001.022 of the Administrative Procedure Act (APA).

The commission staff will conduct a public hearing on this rulemaking, if interested parties request a hearing pursuant to §2001.029 of the APA, or if a public hearing is deemed necessary by commission staff. The request for a public hearing must be received within 20 days after publication.

Comments on the proposed amendments may be submitted to the Filing Clerk, Public Utility Commission of Texas, 1701 North Congress Avenue, P.O. Box 13326, Austin, Texas 78711-3326, within 30 days after publication. Reply comments, if any, are due 45 days from the date of publication. Sixteen copies of comments to the proposed amendments are required to be filed pursuant to §22.71(c) of the commission's rules. Comments should be organized in a manner consistent with the organization of the proposed rules. The commission invites specific comments regarding the costs associated with, and benefits that will be gained by, implementation of the proposed amended sections. The commission will consider the costs and benefits in deciding whether to adopt the amended sections. In addition, staff seeks comments from interested parties on whether the proposed definition of "voice service" in §26.465 should also include a reference to 911 capabilities as suggested by the State of Texas as follows:

Voice services would mean services using a physical voice grade telecommunications connection or the cable or broadband transport facilities, or any combination of these facilities, between an end user customer's premises and a service provider's network that, when the digits 9-1-1 are dialed, provides the end user customer access to a public safety answering point through a permissible interconnection to the dedicated 9-1-1 network.

All comments should refer to Project Number 31973.

These amendments are proposed under the PURA §14.002, which provides the Public Utility Commission with the authority to make and enforce rules reasonably required in the exercise of its powers and jurisdiction. These amended sections are also proposed under the Texas Local Government Code §283.056(c)(3) and §283.058, which grant the commission the jurisdiction over municipalities, certificated telecommunications providers, and voice service providers, necessary to enforce Chapter 283 and to ensure that all other legal requirements are enforced in a competitively neutral, non-discriminatory, and reasonable manner. The amendments are necessary to implement Texas Local Government Code §283.002(2) and (7).

Cross Reference to Statutes: Public Utility Regulatory Act §14.002 and Texas Local Government Code §§283.056, 283.058, 283.002(2) and (7).

§26.461.Access Line Categories.

(a) - (b) (No change.)

(c) Definitions. The following words and terms when used in this subchapter, shall have the following meaning, unless the context clearly indicates otherwise.

(1) (No change.)

(2) Certificated telecommunications provider (CTP)--A person who has been issued a certificate of convenience and necessity, certificate of operating authority, or service provider certificate of operating authority by the commission to offer local exchange telephone service or a person who provides voice service .

(3) - (5) (No change.)

(6) Voice service--Voice communications services provided through wireline facilities located at least in part in the public right-of-way, without regard to the delivery technology, including Internet protocol technology. The term does not include voice service provided by a commercial mobile service provider as defined by 47 U.S.C. Section 332(d).

(d) Access line categories. There shall be three categories of access lines. The three categories shall be as follows:

(1) Category 1 shall include both analog and digital residential switched access lines and any residential voice service . It shall also include point-to-point private lines, whether residential or non-residential, only to the extent such lines provide burglar alarm or other similar security services.

(2) Category 2 shall include all analog and digital non-residential switched access lines and any non-residential voice service .

(3) (No change.)

§26.465.Methodology for Counting Access Lines and Reporting Requirements for Certificated Telecommunications Providers.

(a) - (b) (No change.)

(c) Definitions. The following words and terms when used in this section, shall have the following meaning, unless the context clearly indicates otherwise.

(1) (No change.)

(2) Transmission path--A path within the transmission media that allows the delivery of switched local exchange service or provides a voice service .

(A) - (B) (No change.)

(C) Services that constitute vertical features of a switched local exchange service or a voice service , such as call waiting, caller-ID, etc., [ that do not require a separate switched path, ] do not constitute a transmission path.

(D) (No change.)

(E) Packet voice services, without regard to the delivery technology, switched or not, and including Internet protocol technology, shall constitute a single transmission path.

(3) Voice service--voice communications services provided through wireline facilities located at least in part in the public rights-of-way, without regard to the delivery technology, including Internet protocol technology. The term does not include voice service provided by a commercial mobile service provider as defined by 47 U.S.C. Section 332 (d).

(4) [ (3) ] Wireless provider--A provider of commercial mobile service as defined by §332(d), Communications Act of 1934 (47 U.S.C. §151 et seq. ), Federal Communications Commission rules, and the Omnibus Budget Reconciliation Act of 1993 (Public Law 103-66).

(d) Methodology for counting access lines. A CTP's access line count shall be the sum of all lines counted pursuant to paragraphs (1), (2), [ and ] (3) , and (4) of this subsection, and shall be consistent with subsections (e) and [ , ] (f) [ and (g) ] of this section.

(1) - (3) (No change.)

(4) Voice service.

(A) The CTP shall count each end-use customer provided voice service as one access line. Services that constitute vertical or optional features of a voice service, or are bundled with the voice service shall not be counted as a separate access line.

(B) In the event a CTP is not able to identify the physical location of the end-use customer, that physical location shall be attributed to the municipality identified by the CTP's billing systems as the end-use customer's billing address.

(e) Lines to be counted. A CTP shall count the following access lines:

(1) - (6) (No change.)

(7) any other lines meeting the definition of access line as set forth in §26.461 of this title; [ and ]

(8) Lifeline lines ; [ . ]

(9) all voice service access lines provided to end-use customers that allow such end-use customers to receive calls that originate through or on the public switched telephone network and/or that allow such end-use customers to send calls that terminate on the public switched telephone network; and

(10) all retail pay telephone access lines.

(f) Lines not to be counted. A CTP shall not count the following lines:

(1) - (3) (No change.)

(4) lines used by any other affiliate of a CTP for interoffice transport; [ and ]

(5) any other lines that do not meet the definition of access line as set forth in §26.461 of this title ; [ . ]

(6) all voice service access lines provided to end-use customers which are offered at no cost or which do not allow such end-use customers to receive calls that originate through or on the public switched telephone network and/or that do not allow such end-use customers to send calls that terminate on the public switched telephone network, such as personal computer-to-personal computer voice connectivity; and

(7) Services that constitute vertical or optional features of a voice service, or are bundled with the voice service.

[(g) Reporting procedures and requirements.]

[(1) Who shall file. The record keeping, reporting and filing requirements listed in this section or in §26.467 of this title (relating to Rates, Allocation, Compensation, Adjustments and Reporting) shall apply to all CTPs in the State of Texas.]

[(2) Initial reporting requirements. ]

[(A) No later than January 24, 2000, a CTP shall file its access line count using the commission-approved Form for Counting Access Line or Program for Counting Access Lines with the commission. The CTP shall report the access line count as of December 31, 1998, except as provided in subparagraph (C) of this paragraph.]

[(B) A CTP shall not include in its initial report any access lines that are resold, leased, or otherwise provided to a CTP, unless it has agreed to a request from another CTP to include resold or leased lines as part of its access line report.]

[(C) A CTP that cannot file access line count as of December 31, 1998 shall file request for good cause exemption and shall file the most recent access line count available for December, 1999.]

[(D) A CTP shall not make a distinction between facilities and capacity leased or resold in reporting its access line count.]

(g) [ (h) ] Exemption. Any CTP that does not terminate a franchise agreement or obligation under an existing ordinance shall be exempted from subsequent reporting pursuant to §26.467 of this title unless and until the franchise agreement is terminated or expires on its own terms. Any CTP that fails to provide notice to the commission and the affected municipality by December 1, 1999 that it elects to terminate its franchise agreement or obligation under an existing ordinance, shall be deemed to continue under the terms of the existing ordinance. Upon expiration or termination of the existing franchise agreement or ordinance by its own terms, a CTP is subject to the terms of this section.

(h) [ (i) ] Maintenance and location of records. A CTP shall maintain all records, books, accounts, or memoranda relating to access lines deployed in a municipality in a manner which allows for easy identification and review by the commission and, as appropriate, by the relevant municipality. The books and records for each access line count shall be maintained for a period of no less than three years.

(i) [ (j) ] Proprietary or confidential information.

(1) The CTP shall file with the commission the information required by this section regardless of whether this information is confidential. For information that the CTP alleges is confidential and/or proprietary under law, the CTP shall file a complete list of the information that the CTP alleges is confidential. For each document or portion thereof claimed to be confidential, the CTP shall cite the specific provision(s) of the Texas Government Code, Chapter 552, that the CTP relies to assert that the information is exempt from public disclosure. The commission shall treat as confidential the specific information identified by the CTP as confidential until such time as a determination is made by the commission, the Attorney General, or a court of competent jurisdiction that the information is not entitled to confidential treatment.

(2) The commission shall maintain the confidentiality of the information provided by CTPs, in accordance with the Public Utility Regulatory Act (PURA) §52.207.

(3) If the CTP does not claim confidential treatment for a document or portions thereof, then the information will be treated as public information. A claim of confidentiality by a CTP does not bind the commission to find that any information is proprietary and/or confidential under law, or alter the burden of proof on that issue.

(4) Information provided to municipalities under the Local Government Code, Chapter 283, shall be governed by existing confidentiality procedures which have been established by the commission in compliance with PURA §52.207.

(5) The commission shall notify a CTP that claims its filing as confidential of any request for such information.

(j) [ (k) ] Report attestation. All filings with the commission pursuant to this section shall be in accordance with §22.71 of this title (relating to Filing of Pleadings, Documents and Other Materials) and §22.72 of this title (relating to Formal Requisites of Pleadings and Documents to Be Filed With the Commission). The filings shall be attested to by an officer or authorized representative of the CTP under whose direction the report is prepared or other official in responsible charge of the entity in accordance with §26.71(d) of this title (relating to General Procedures, Requirements and Penalties). The filings shall include a certified statement from an authorized officer or duly authorized representative of the CTP stating that the information contained in the report is true and correct to the best of the officer's or representative's knowledge and belief after inquiry.

(k) [ (l) ] Reporting of access lines that have been provided by means of resold services or unbundled facilities to another CTP. This subsection applies only to a CTP reporting access lines under §26.467 of this title (relating to Rates, Allocation, Compensation, Adjustments, and Reporting) that are provided by means of resold services or unbundled facilities to another CTP who is not an end-use customer. Nothing in this subsection shall prevent a CTP reporting another CTP's access line count from charging an appropriate, tariffed administrative fee for such service.

(l) [ (m) ] Commission review of the definition of access line.

(1) Pursuant to the Local Government Code §283.003, not later than September 1, 2002, the commission shall determine whether changes in technology, facilities, or competitive or market conditions justify a modification of the adoption of the definition of "access line" provided by §26.461 of this title. The commission may not begin a review authorized by this subsection before March 1, 2002.

(2) As part of the proceeding described by paragraph (1) of this subsection, and as necessary after that proceeding, the commission by rule may modify the definition of "access line" as necessary to ensure competitive neutrality and nondiscriminatory application and to maintain consistent levels of compensation, as annually increased by growth in access lines within the municipalities.

(3) After September 1, 2002, the commission, on its own motion, shall make the determination required by this subsection at least once every three years.

This agency hereby certifies that the proposal has been reviewed by legal counsel and found to be within the agency's legal authority to adopt.

Filed with the Office of the Secretary of State on February 10, 2006.

TRD-200600692

Adriana A. Gonzales

Rules Coordinator

Public Utility Commission of Texas

Earliest possible date of adoption: March 26, 2006

For further information, please call: (512) 936-7223